11 MAC Pt. 5, R. 2.1
through Rule 2.8 and Rule 2.9 of this part
Cite as 11 Miss. Admin. Code Pt. 5, R. 2.1
through Rule 2.8 and Rule 2.9 of this part.
(d) In addition to the codes of practice listed in §280.20, owners and operators may use military
construction criteria, such as Unified Facilities Criteria (UFC) 3-460-01, Petroleum Fuel
Facilities, when designing, constructing, and installing airport hydrant systems and UST systems
with field-constructed tanks.
§280.132 Additions, exceptions, and alternatives for UST systems with field-constructed
tanks and airport hydrant systems.
(a) Exception to piping secondary containment requirements. Owners and operators may use
single walled piping when installing or replacing piping associated with UST systems with field-
constructed tanks greater than 50,000 gallons and piping associated with airport hydrant systems.
Piping associated with UST systems with field-constructed tanks less than or equal to 50,000
gallons not part of an airport hydrant system must meet the secondary containment requirement
when installed or replaced.
(b) Upgrade requirements. Not later than October 5, 2021, airport hydrant systems and UST
systems with field-constructed tanks where installation commenced on or before October 5,
2018, must meet the following requirements or be permanently closed pursuant to Rule 2.7 of
this part.
(1) Corrosion protection. UST system components in contact with the ground thatroutinely
contain regulated substances must meet one of the following:
(i) Except as provided in paragraph (a) of this section, the new UST system performance
standards for tanks at §280.20(a) and for piping at §280.20(b); or
(ii) Be constructed of metal and cathodically protected according to a code of practice
developed by a nationally recognized association or independent testing laboratory and
meets the following:
(A) Cathodic protection must meet the requirements of §280.20(a)(2)(ii), (iii), and (iv)
for tanks, and §280.20(b)(2)(ii), (iii), and (iv) for piping.
(B) Tanks greater than 10 years old without cathodic protection must be assessed to
ensure the tank is structurally sound and free of corrosion holes prior to adding
cathodic protection. The assessment must be by internal inspection or another
method determined by the implementing agency to adequately assess the tank for
structural soundness and corrosion holes.
(2) Spill and overfill prevention equipment. To prevent spilling and overfilling associated with
product transfer to the UST system, all UST systems with field-constructed tanks and
airport hydrant systems must comply with new UST system spill and overfill prevention
equipment requirements specified in §280.20(c).
(c) Walkthrough inspections. In addition to the walkthrough inspection requirements in §280.38,
owners and operators must inspect the following additional areas for airport hydrant systems at
least once every 30 days if confined space entry according to the Occupational Safety and Health
Administration (see 29 CFR part 1910) is not required or at least annually if confined space entry
is required and keep documentation of the inspection according to §280.36(b).
(1) Hydrant pits—visually check for any damage; remove any liquid or debris; and check for
any leaks, and
(2) Hydrant piping vaults—check for any hydrant piping leaks.
(d) Release detection. Owners and operators of UST systems with field-constructed tanks and
airport hydrant systems must begin meeting the release detection requirements described in this
rule not later than October 5, 2021.
(1) Methods of release detection for field-constructed tanks. Owners and operators of field-
constructed tanks with a capacity less than or equal to 50,000 gallons must meet the
release detection requirements in Rule 2.4 of this part. Owners and operators of field-
constructed tanks with a capacity greater than 50,000 gallons must meet either the
requirements in Rule 2.4 (except §280.43(e) and (f) must be combined with inventory
control as stated below) or use one or a combination of the following alternative methods
of release detection:
(i) Conduct an annual tank tightness test that can detect a 0.5 gallon per hour leak rate;
(ii) Use an automatic tank gauging system to perform release detection at least every 30
days that can detect a leak rate less than or equal to one gallon per hour. This method
must be combined with a tank tightness test that can detect a 0.2 gallon per hour leak
rate performed at least every three years;
(iii) Use an automatic tank gauging system to perform release detection at least every 30
days that can detect a leak rate less than or equal to two gallons per hour. This method
must be combined with a tank tightness test that can detect a 0.2 gallon per hour leak
rate performed at least every two years;
(iv) Perform vapor monitoring (conducted in accordance with §280.43(e) for a tracer
compound placed in the tank system) capable of detecting a 0.1 gallon per hour leak
rate at least every two years;
(v) Perform inventory control (conducted in accordance with Department of Defense
Directive 4140.25; ATA Airport Fuel Facility Operations and Maintenance Guidance
Manual; or equivalent procedures) at least every 30 days that can detect a leak equal to
or less than 0.5 percent of flow-through; and
(A) Perform a tank tightness test that can detect a 0.5 gallon per hour leak rate at least
every two years; or
(B) Perform vapor monitoring or groundwater monitoring (conducted in accordance
with §280.43(e) or (f), respectively, for the stored regulated substance) at least
every 30 days; or
(vi) Another method approved by the implementing agency if the owner and operator can
demonstrate that the method can detect a release as effectively as any of the methods
allowed in paragraphs (d)(1)(i) through (v) of this section. In comparing methods, the
implementing agency shall consider the size of release that the method can detect and
the frequency and reliability of detection.
(2) Methods of release detection for piping. Owners and operators of underground piping
associated with field-constructed tanks less than or equal to 50,000 gallons must meet the
release detection requirements in Rule 2.4 of this part. Owners and operators of
underground piping associated with airport hydrant systems and field-constructed tanks
greater than 50,000 gallons must follow either the requirements in Rule 2.4 (except
§280.43(e) and (f) must be combined with inventory control as stated below) or use one or
a combination of the following alternative methods of release detection:
(i) Perform a semiannual or annual line tightness test at or above the piping operating
pressure in accordance with the table listed.
MAXIMUM LEAK DETECTION RATE PER TEST SECTION VOLUME
Test section volume
(gallons)
Semiannual test—leak
detection rate not to exceed
(gallons per hour)
Annual test—leak detection rate not to
exceed
(gallons per hour)
<50,000
1.0
0.5
≥50,000 to <75,000
1.5
0.75
≥75,000 to <100,000 2.0
1.0
≥100,000
3.0
1.5
(ii) Piping segment volumes ≥100,000 gallons not capable of meeting the maximum 3.0
gallon per hour leak rate for the semiannual test may be tested at a leak rate up to 6.0
gallons per hour according to the following schedule:
PHASE IN FOR PIPING SEGMENTS ≥100,000 GALLONS IN VOLUME
First test
Not later than October 5, 2021 (may use up to 6.0 gph leak rate).
Second test
Between October 5, 2021 and October 13, 2021 (may use up to 6.0 gph leak rate).
Third test
Between October 13, 2021 and October 13, 2022 (must use 3.0 gph for leak rate).
Subsequent
tests
After October 13, 2022, begin using semiannual or annual line testing according to
the Maximum Leak Detection Rate Per Test Section Volume table above.
(iii)Perform vapor monitoring (conducted in accordance with §280.43(e) for a tracer
compound placed in the tank system) capable of detecting a 0.1 gallon per hour leak
rate at least every two years;
(iv) Perform inventory control (conducted in accordance with Department of Defense
Directive 4140.25; ATA Airport Fuel Facility Operations and Maintenance Guidance
Manual; or equivalent procedures) at least every 30 days that can detect a leak equal to
or less than 0.5 percent of flow-through; and
(A) Perform a line tightness test (conducted in accordance with paragraph (d)(2)(i) of
this section using the leak rates for the semiannual test) at least every two years; or
(B) Perform vapor monitoring or groundwater monitoring (conducted in accordance
with §280.43(e) or (f), respectively, for the stored regulated substance) at least
every 30 days; or
(v) Another method approved by the implementing agency if the owner and operator can
demonstrate that the method can detect a release as effectively as any of the methods
allowed in paragraphs (d)(2)(i) through (iii) of this section. In comparing methods, the
implementing agency shall consider the size of release that the method can detect and
the frequency and reliability of detection.
(3) Recordkeeping for release detection. Owners and operators must maintain release
detection records according to the recordkeeping requirements in §280.45.
(e) Applicability of closure requirements to previously closed UST systems. When directed by
MDEQ, the owner and operator of an UST system with field-constructed tanks or airport hydrant
system permanently closed before October 13, 2015 must assess the excavation zone and close
the UST system in accordance with Rule 2.7 of this part if releases from the UST may, in the
judgment of the implementing agency, pose a current or potential threat to human health and the
environment.
APPENDIX 280.1 - GUIDELINES FOR THE EVALUATION OF
UNDERGROUND STORAGE TANK CATHODIC PROTECTION
SYSTEMS
SECTION 1 – GENERAL
1.1
Introduction ……………………………………………………………………………………………………..
SECTION 2 – REGULATIONS
2.1
Rules …………………………………………………………………………………………………………….
SECTION 3 – TYPES OF CATHODIC PROTECTION
3.1
General ………………………………………………………………………………………………………….
3.2
Galvanic Systems ……………………………………………………………………………………………...
3.3
Impressed Current Systems …………………………………………………………………………………..
SECTION 4 – QUALIFICATIONS TO TEST CATHODIC PROTECTION SYSTEMS
4.1
Qualifications …………………………………………………………………………………………………...
SECTION 5 – INSTALLATION/REPAIR OF CATHODIC PROTECTION SYSTEMS
5.1
Galvanic Systems ……………………………………………………………………………………………...
5.1.1
sti-P3® Tanks …………………………………………………………………………………………………....
5.1.2
Factory Coated Metallic Piping ……………………………………………………………………………….
5.1.3
Non-factory Coated Metallic Piping ………………………………………………………………………….
5.1.4
Metallic Piping Installation/Repair …………………….……………………………………………………...
5.2
Impressed Current Systems …………………………………………………………………………………..
5.2.1
Rectifier Adjustment ……………………………………………………………………………………………
SECTION 6 – CATHODIC PROTECTION TESTING
6.1
Equipment ………………………………………………………………………………………………………
6.1.1
Voltmeter/Ammeter …………………………………………………………………………………………….
6.1.2
Reference Electrode …………………………………………………………………………………………...
6.1.3
Lead Wires/Test Probes/Miscellaneous ……………………………………………………………………..
6.2
Test Criteria …………………………………………………………………………………………………….
6.3
Voltage (IR) Drops ……………………………………………………………………………………………..
6.4
Stray Current .…………………………………………………………………………………………………..
6.5
Dissimilar Metals/Bimetallic Couples ………………………………………………………………………...
6.6
Other Test Considerations …………………………………………………………………………………….
6.7
Continuity Testing ……………………………………………………………………………………………...
6.7.1
Continuity Testing of Galvanic Systems …………………………………………………………………….
6.7.2
Continuity Testing of Impressed Current Systems …………………………………………………………
6.8
Reference Electrode Placement …………………………………………………………………………….
6.8.1
General …………...……………………………………………………………………………………….…….
6.8.2
Local Placement ………………………………………………………………………………………………..
6.8.3
Remote Placement …………………………………………………………………………………………….
6.8.4
Galvanic Placement ……………………………………………………………………………………………
6.8.5
Impressed Current Placement ………………………………………………………………………………..
6.9
Soil Access ……………………………………………………………………………………………………..
6.10
Cathodic Protection Test Locations …………………………………………………………………………
6.10.1
Galvanically Protected (sti-P3® ) Tanks …………………………………………………………………..….
6.10.2
Galvanically Protected Metallic Piping ……………………………………………………………………....
6.10.3
Tanks Protected by Impressed Current ……………………………………………………………….…….
6.10.4
Piping Protected by Impressed Current ………………………………………………………………….….
6.10.5
“100 Foot Rule” for Piping …………………………………………………………………….………………
TABLE OF CONTENTS
SECTION 7 – DOCUMENTATION OF EVALUATION
7.1
Documentation …………………………………………………………………….…………………………...
7.1.1
As Built Drawings …………………………………………………………….………………………….……..
7.1.2
Site Drawing …………………………………………………………………….………………………………
7.1.3
MDEQ UST Cathodic Protection Evaluation Form ………………………….………………………….….
7.1.4
Pass/Fail/Inconclusive ………………………………………………………….………………………….….
7.2
Corrosion Expert’s Evaluation ………………………………………………….………………………….…
7.3
What if the Evaluation Result is Fail? …………..…………………….………………………….…..……...
LIST OF FIGURES
FIGURE 1
ILLUSTRATION OF REFERENCE ELECTRODE CALIBRATION …..…………………………...
FIGURE 2
GRAPHIC REPRESENTATION OF VOLTAGE DROP IN “ON” POTENTIAL ……………..…..
FIGURE 3
LOCAL REFERENCE ELECTRODE PLACEMENT FOR sti-P3® TANKS ………….…………...
FIGURE 4
REMOTE EARTH REFERENCE ELECTRODE PLACEMENT ……………………………..…….
FIGURE 5
LOCAL REFERENCE ELECTRODE PLACEMENT FOR GALVANICALLY PROTECTED
PIPING WHEN PIPING ANODES ARE AT TANKS …….………………………………………….
FIGURE 6
LOCAL REFERENCE ELECTRODE PLACEMENT FOR GALVANICALLY PROTECTED
PIPING WHEN PIPING ANODES ARE AT DISPENSERS ….……………………………………
FIGURE 7
LOCAL REFERENCE ELECTRODE PLACEMENT FOR GALVANICALLY PROTECTED
PIPING WHEN PIPING ANODES ARE AT BOTH ENDS OF THE PIPING ….…………………
FIGURE 8
LOCAL REFERENCE ELECTRODE PLACEMENT FOR GALVANICALLY PROTECTED PIPING WHEN
ANODES ARE INSTALLED AT CENTER OF PIPING OR LOCATION IS UNKNOWN …………………….
FIGURE 9
REFERENCE ELECTRODE PLACEMENT FOR TANKS PROTECTED BY IMPRESSED
CURRENT SYSTEM WHEN ANODES ARE EVENLY DISTRIBUTED ………………………….
FIGURE 10
REFERENCE ELECTRODE PLACEMENT FOR TANKS PROTECTED BY IMPRESSED
CURRENT SYSTEM WHEN ANODES ARE UNEVENLY DISTRIBUTED ……………………...
FIGURE 11
REFERENCE ELECTRODE PLACEMENT FOR METALLIC PIPING PROTECTED BY
IMPRESSED CURRENT SYSTEM …………………………………………………………………..
FIGURE 12
“100 FOOT RULE” FOR METALLIC PIPING PROTECTED BY GALVANIC OR IMPRESSED
CURRENT SYSTEM …………………………………………………………………………………..
FIGURE 13
EXAMPLE OF A SITE DRAWING CONSTRUCTED AS PART OF A UST SYSTEM
CATHODIC PROTECTION SURVEY ………………………………………………………………..
APPENDICES
APPENDIX A Industry Codes/Standards, References and Regulations
APPENDIX B Glossary
APPENDIX C Interpretation of Structure-to-Soil Potential Measurements (Voltages) Obtained on
Galvanic Cathodic Protection Systems
APPENDIX D Interpretation of Structure-to-Soil Potential Measurements (Voltages) Obtained on
Impressed Current Cathodic Protection Systems
APPENDIX E Continuity Testing Procedure for Galvanic/Impressed Current Systems
APPENDIX F Structure-to-Soil Test Procedure for Galvanic Cathodic Protection Systems
APPENDIX G Structure-to-Soil Test Procedure for Impressed Current Cathodic Protection Systems
APPENDIX H Checklist for Galvanic Cathodic Protection System Survey
APPENDIX I Checklist for Impressed Current Cathodic Protection System Survey
APPENDIX J Typical Potentials of Selected Metals
APPENDIX K Galvanic (Sacrificial Anode) Cathodic Protection System Evaluation Form
APPENDIX L Impressed Current Cathodic Protection System Evaluation Form
APPENDIX M Impressed Current Cathodic Protection System 60 Day Record of Rectifier Operation
SECTION 1 - GENERAL
1.1 Introduction
The purpose of this document is to establish the policy of this office regarding the evaluation of
cathodic protection systems operating on underground storage tank (UST) systems in the State of
Mississippi. While conducting structure-to-soil potential surveys is the primary means of testing
cathodic protection systems, other aspects related to the evaluation, installation, operation and repair
of cathodic protection systems are also addressed in this document where necessary.
Evaluation of cathodic protection systems to ensure they are functioning as intended has proven to
be one of the more problematic areas that has led to a great deal of confusion and various practices
among individuals engaged in the field of cathodic protection. Because the applicable regulations
contain no specific criteria and instead defer to industry standards, a large degree of latitude has
historically been provided for interpretation of what constitutes an acceptable evaluation.
Since there are many factors that can affect cathodic protection, there is understandably no
standard test method or "cookie-cutter" approach that will work at every site that has a cathodic
protection system in operation. Therefore, the primary intent of this policy is to create a level
playing field in which everyone engaged in the field of UST system cathodic protection in the
State of Mississippi understands what is expected. The second focus of this policy is to provide that
documentation sufficient to reproduce the results generated by a cathodic protection tester must be
established in order to conduct a valid cathodic protection evaluation. To this end, forms that must
be utilized when evaluating cathodic protection are included in Appendix K and L of this
document.
It is further necessary to understand that the creation of this policy has necessitated a
compromise to some degree. Every effort has been made so as not to place an unduly harsh
burden on the tank owners and contractors who operate in the State of Mississippi. At the same
time, it is necessary to be protective of human health and the environment to the degree required to
achieve the charge of the Mississippi Department of Environmental Quality (MDEQ). This
document represents the best efforts of the MDEQ to assure that cathodic protection systems
operate as intended and effectively mitigate corrosion while being mindful of the economic
constraints that must be considered.
Some of the more important points established with this guidance document are:
> Access to the soil directly over the structure that is being tested must be provided.
> Both "local" and "remote" structure-to-soil potentials must be obtained on galvanic systems.
> "Instant off' potentials must be obtained on all impressed current systems.
> Continuity/isolation must be established whenever a cathodic protection survey is conducted.
> Under certain conditions a "corrosion expert" must evaluate the cathodic protection survey.
> A person must meet certain minimum qualifications in order to conduct an effective
evaluation.
Simply conducting a structure-to-soil potential survey does not adequately evaluate a cathodic
protection system. Other considerations that may need to be addressed are outlined in the text of
this document and include: continuity measurements; evaluation of rectifier operation; current
distribution among an impressed current anode ground bed; consideration of voltage drops;
assurance of wiring integrity; continuity bonds; as built drawings and others.
This policy is not intended to replace any statute or regulatory requirement concerning the
installation, repair, operation or testing of cathodic protection systems. Rather, it is intended to
state the interpretation of the MDEQ with regard to the implementation of those rules and
regulations applicable to UST cathodic protection systems.
SECTION 2 - REGULATIONS 2.1
Rules
Federal and state laws require that any component of a UST system that routinely contains
product and is in contact with the soil must be protected from corrosion. If the UST component
in question is of metallic construction and it is in contact with the soil and/or water, it must be
cathodically protected. If it is cathodically protected it must also be coated with a suitable
dielectric material if the metallic component in question was installed after December 22, 1988.
The rules also require that all cathodic protection systems must be evaluated within six months
of installation/repair and once every three years thereafter. Consideration should be given to
evaluating impressed current systems on an annual basis since these types of systems are more
susceptible to failure or may be in need of adjustment on a more frequent basis in order to
provide adequate cathodic protection.
The MDEQ UST regulations reference several industry codes and practices and a listing of these
may be found in Appendix A of this document. Following are the pertinent paragraphs the UST
rules that are related to cathodic protection:
280.12
Definitions
"Cathodic Protection" is a technique to prevent corrosion of a metal surface by
making that surface the cathode of an electrochemical cell. For example, a tank
system can be cathodically protected through the application of either galvanic
anodes or impressed current.
"Cathodic protection tester" means a person who can demonstrate an
understanding of the principles and measurements of all common types of
cathodic protection systems as applied to buried or submerged metal piping and
tank systems. At a minimum, such persons must have education and experience in
soil resistivity, stray current, structure-to-soil potential, and component electrical
isolation measurements of buried metal piping and tank systems.
"Corrosion expert" means a person who, by reason of thorough knowledge of the
physical sciences and the principles of engineering and mathematics acquired by a
professional education and related practical experience, is qualified to engage in
the practice of corrosion control on buried or submerged metal piping systems and
metal tanks. Such a person must be accredited or certified as being qualified by
the National Association of Corrosion Engineers (NACE) or be a registered
professional engineer who has certification or licensing that includes education
and experience in corrosion control of buried or submerged metal piping systems
and metal tanks.
Performance Standards for New UST Systems
(a) (2) The tank is constructed of steel and cathodically protected in the following
manner:
(i) The tank is coated with a suitable dielectric material;
(ii) Field-installed cathodic protection systems are designed by a
corrosion expert;
(iii) Impressed current systems are designed to allow determination of
current operating status as required in 280.32 (c); and
(iv) Cathodic protection systems are operated and maintained in
accordance with 280.32.
Operation and Maintenance of Corrosion Protection
All corrosion protection systems must be operated and maintained to
continuously provide corrosion protection to the metal components of that
portion of the tank and piping that routinely contain regulated substances
and are in contact with the ground.
All UST systems equipped with cathodic protection systems must be
inspected for proper operation by a qualified cathodic protection tester in
accordance with the following requirements:
(1)
Frequency. All cathodic protection systems must be tested within 6
months of installation and at least every 3 years thereafter.
(2)
Inspection Criteria. The criteria that are used to determine that
cathodic protection is adequate as required by this section must be
in accordance with a code of practice developed by a nationally
recognized association.
(c)
UST systems with impressed current cathodic protection systems must
also be inspected every 60 days to ensure the equipment is running
properly.
(d)
For UST systems using cathodic protection, records of the operation of the
cathodic protection must be maintained (in accordance with 280.35) to
demonstrate compliance with the performance standards in this section.
These records must provide the following:
(1) The results of the last three inspections required in paragraph (c)
above;
(2) The results of testing from the last two inspections required in
paragraph (b) above.
280.34
Repairs Allowed
(e)
Within 6 months following the repair of any cathodically protected UST
system, the cathodic protection system must be tested in accordance with
280.32 (b) and (c) to ensure that it is operating properly.
SECTION 3 - TYPES OF CATHODIC PROTECTION
3.1
General
The two types of cathodic protection that are typically installed on UST systems are galvanic
(sacrificial anode) and impressed current systems. An attempt to explain the principles involved
in the theory of cathodic protection is beyond the scope of this document and it is assumed the
reader has a basic understanding of the subject. However, stated in the simplest terms, both of
these types of cathodic protection attempt to reverse the flow of electric current away from the
metal that is intended to be protected from corrosion. Both types of cathodic protection prevent
electric current from leaving the protected structure by supplying an electrical charge in the form
of DC power sufficient to overcome any current that would otherwise leave the structure. The
way in which the required electrical current is provided is what distinguishes the two types of
cathodic protection.
3.2
Galvanic Systems
Galvanic systems are also known as sacrificial anode systems because an anode (usually zinc or
magnesium) corrodes instead of the protected metal. Because the anode corrodes instead of the
metal that it is protecting, the anode is said to sacrifice itself. Sacrificial anodes are connected
directly to the structure to be protected by either welding or mechanical connection of lead wires.
Galvanic systems are generally limited to those tank components that are well coated with a
dielectric material (sti-P3® tanks or fusion bonded epoxy coated steel piping) because the
available current output of these systems is low. Attempts to protect long runs of uncoated piping
or uncoated tanks generally is not practical because the useful life of the anodes is too short or
the number of anodes needed is too great.
3.3
Impressed Current Systems
Impressed current systems are sometimes called rectifier systems because they utilize a device (a
rectifier) to convert an external AC power source to the required DC power source. In this type
of system, anodes are installed in the soil around the structure to be protected and the DC power
is supplied to the anodes through buried wires. The power to the rectifier cannot be interrupted
except when conducting maintenance or testing activities. Normally, a dedicated and protected
circuit is provided for the impressed current system so that the power cannot be inadvertently cut
off.
In impressed current systems the protected structure is bonded to the DC power system to
complete the electrical circuit. It is critical that the anodes are connected to the positive terminal
and the protected structure to the negative terminal of the rectifier. Reversal of the lead wires
will make the components of the tank system anodic and can cause a rapid failure of the tank
system due to corrosion. In addition, it is critical that all wire connections and splices are well
insulated. Any breaks in the wiring insulation will allow current to leave the wire at that point
and a rapid failure of the wire can occur due to corrosion.
Impressed current systems are generally installed on those tank systems that were installed prior
to the effective date of the UST regulations since these tanks usually do not have a good
dielectric coating. The level of cathodic protection provided by an impressed current system can
be adjusted since the voltage produced by the rectifier can be changed. Because conditions that
affect the level of cathodic protection needed are likely to change over time, adjustment of the
rectifier is frequently necessary.
SECTION 4 - QUALIFICATIONS TO TEST CATHODIC PROTECTION SYSTEMS
4.1 Qualifications
In order to test cathodic protection systems in the State of Mississippi, an individual must meet
certain minimum qualifications. It is the intent of the MDEQ that those individuals who meet the
minimum qualifications perform testing in a manner that is consistent with the policies of this
guidance document. Should an individual who meets the minimum qualifications as described
below not possess the knowledge and expertise needed to properly evaluate a cathodic protection
system, that individual should not attempt to undertake such an evaluation.
While it is not necessary to be an "expert" to test cathodic protection systems in most cases, it
should be recognized that the proper evaluation of the two types of cathodic protection systems
may require differing levels of expertise. Impressed current systems are inherently more
involved and require a higher level of understanding than galvanic systems. In addition, certain
circumstances and conditions may exist that would preclude an individual from making an
effective evaluation of a cathodic protection system without the assistance of someone who is
more qualified.
Because the testing of impressed current systems is inherently more complicated, someone who
is only minimally qualified as a "tester" should recognize that he may or may not be able to
properly evaluate all such systems. Galvanic cathodic protection systems that are operating as
designed are normally straightforward and a lesser degree of expertise is needed to properly
evaluate such systems. However, troubleshooting and/or repair of such systems may require
someone who has a higher level of expertise than a person who is only minimally qualified as a
tester.
Scenarios that require an expert to either conduct or evaluate the cathodic protection survey are
listed in Section 7.2 of this document. It should be recognized that there might be other
circumstances that require an expert although they may not be specifically listed. A listing of
those individuals who meet the qualifications of an expert (certified as either as a "corrosion
specialist" or a "cathodic protection specialist") can be found at the web site of NACE
International (www.nace.org).
Listed below are the minimum qualifications necessary to test cathodic protection:
> Anyone who meets the definition of "cathodic protection tester" as found in 40 CFR 280.10
is recognized as qualified to test cathodic protection.
> Anyone who holds a certification from NACE International which that organization
recognizes at a minimum as qualifying that person as a cathodic protection tester.
> Anyone who is certified by the MDEQ as a UST installer is recognized as being able to test
cathodic protection systems provided they are familiar with the concepts involved and abide
by the requirements contained within this guidance document. If a UST installer does not
understand the basic concepts related to the testing, maintenance and operation of cathodic
protection systems, that person should not attempt to evaluate such systems.
Should it be determined that a MDEQ certified UST installer is conducting evaluations of UST
cathodic protection systems in a manner that is not consistent with the intent of the MDEQ
policy, they may be subject to penalty and/or revocation of their UST installer certification upon
a determination of good cause by the Mississippi Commission on Environmental Quality.
SECTION 5 - INSTALLATION/REPAIR OF CATHODIC PROTECTION SYSTEMS
5.1 Galvanic Systems
5.1.1
sti-P3® Tanks
Anyone who is a MDEQ certified UST installer may repair the cathodic protection system of a
sti-P3® tank provided any provisions the tank manufacturer may have are also met. The design
requirements for the installation of additional sacrificial anodes to a sti-P3® tank may be met
without the need for a corrosion expert to design such, provided the provisions of the Steel Tank
Institute "Recommended Practice for the Installation of Supplemental Anodes for sti-P3® UST's
R-972-01" are followed. An evaluation of the cathodic protection system must be conducted
within six months of the installation/repair in accordance with the requirements of this document.
5.1.2 Factory Coated Metallic Piping
Installation of sacrificial anodes to factory coated (fusion bonded epoxy) metallic piping may be
accomplished without the design of a corrosion expert provided the provisions of the Steel Tank
Institute "Recommended Practice for Corrosion Protection of Underground Piping Networks
Associated with Liquid Storage and Dispensing Systems R892-91" are followed. As an
alternative, the practices as described in the Petroleum Equipment Institute "RP 100-2000
Recommended Practices for the Installation of Underground Liquid Storage Systems" may also
be followed when installing sacrificial anodes on factory coated piping.
5.1.3 Non-factory Coated Metallic Piping
The installation and/or repair of a galvanic cathodic protection system installed on metallic
piping that is not factory coated with a dielectric material may be accomplished by anyone who
is a MDEQ certified UST installer. However, the design of the galvanic cathodic protection
system must be accomplished by a corrosion expert. In addition, an evaluation of the cathodic
protection system must be conducted within six months of the installation/repair in accordance
with the requirements of this document.
5.1.4 Metallic Piping Repair/Installation
Provided below are some general observations that are commonly applicable to questions that
arise when attempting to meet the corrosion protection requirements on metallic piping and other
metallic components of a typical UST system.
Protected Components - Any metallic component of the piping system, including all metallic
nipples, ells, tees, couplings, unions, ball valves, etc. must be protected from corrosion if they are
in contact with the soil and/or water. Corrosion protection may be accomplished by either a)
isolating the component in question from contact with the soil and/or water or b)
coating/wrapping with a suitable dielectric material and cathodic protection. Any isolation boot
or containment sump designed to isolate the metallic component from contact with the soil must
also prevent water from contacting the component in question in order to eliminate the need for
cathodic protection. If the metallic component in question is cathodically protected, it must also
be coated/wrapped with a suitable dielectric material if it was installed after December 22, 1988.
Unprotected Components - Metallic components of the UST system that do not require
corrosion protection include: tank vent lines; any type of tank riser pipe; tank hold down straps;
remote tank fill lines and submersible turbine pump (STP) heads. Although the pump head
"routinely contains product", it is not required to meet the corrosion protection requirements and
may be in contact with the soil or submerged in water without the need for cathodic protection.
However, the pump head should remain visible (not buried) so that any obvious corrosion
problems or leaks that may be present can be observed and appropriate action taken to prevent or
repair any leaks.
Repair - Some confusion exists over whether or not metallic piping that has failed can be
repaired or must be replaced. "Repaired" as related to steel pipe involves the replacement of the
section of pipe that has failed. The entire run of steel piping does not have to be replaced but the
repair must consist of replacement of the section of pipe that has failed. Only steel pipe that is
factory coated with a dielectric material (fusion bonded epoxy) can be used to replace the failed
section of pipe regardless of whether the existing pipe is galvanized or coated steel. Under no
circumstances is it allowable to install galvanized piping when it is intended to serve as a product
transfer line. Because of the complexities that may be involved in the cathodic protection of
galvanized steel piping, a corrosion expert must evaluate and/or conduct the cathodic protection
survey after the repair.
Electrical Continuity - Dielectric unions are normally not installed if the piping is protected by
an impressed current system. It is essential that all metallic piping that is part of the UST system
is bonded to the negative circuit of the impressed current system if it is buried. It is normally
desirable to electrically isolate any metallic portion of the UST system that is not buried or
submerged in water from that portion that is buried/submerged.
Electrical Isolation - If metallic piping is galvanically protected, it is critical that effective
electrical isolation is provided. Failure to isolate the protected piping will result in premature
failure of the sacrificial anodes. Isolation can be difficult to achieve where cathodically
protected piping is present under dispensers that have shear valves present. This is due to the
requirement that the shear valve must be properly anchored to the island form. Particular care
should be exercised in these instances to assure proper isolation. If possible, the dielectric union
should be installed below the shear valve so that anchoring does not cause a continuity problem.
Screw Joints - Particular care should be taken when dealing with metallic piping that is
mechanically coupled with threaded screw joints. Any threaded joint in a metallic piping
material can serve as a break in the electrical continuity of the piping system. It has been
established that threaded couple pipe joints can develop enough electrical resistivity over time to
effectively isolate each section of a piping system. For obvious reasons, this is highly undesirable
in a cathodic protection system and you should ensure that electrical continuity is present
between any sections of piping that are intended to be protected. Jumper wires or welding may
be necessary across each pipe couple in order to assure electrical continuity between each section
of piping.
Flex Connectors - Any metallic flexible connector (including stainless steel) that is utilized on a
piping system must be protected from corrosion. The flex connector may be isolated from
contact with soil/water or cathodically protected. If the flex connector is cathodically protected,
it must also be coated/wrapped with a dielectric material if it was installed after December 22,
1988.
Containment Sumps - If metallic components of a piping system are installed in a containment
sump, the sump must be maintained dry. If a sump contains water and you are unable to keep the
water out, the metallic components must be protected from corrosion. The metallic components
may be protected by installing appropriate isolation boots (in the case of flex connectors) or
sacrificial anodes. If cathodic protection is necessary, the sump may or may not be filled with
clean sand to a depth adequate to bury the anode. Burial of the anode may help prevent an
oxidation film from forming on the anode (and causing passivation) in the event that standing
water is not always present in the sump. In either case, it is critical that the anode be installed
within the containment sump. Do not place the anode outside of the sump.
"Mixed" Piping - In those instances where fiberglass reinforced plastic or flexible piping is
connected to an existing metallic pipe (e.g. to extend a fueling island), a cathodic protection test
station or access to the soil where the two dissimilar materials are joined must be provided. This
is necessary to effectively test the adequacy of cathodic protection operating on the metallic
piping.
5.2 Impressed Current Systems
Anyone who is a MDEQ certified UST installer may install and/or repair an impressed current
cathodic protection system. However, the design of an impressed current system must be
accomplished by a corrosion expert. If the repair of an impressed current cathodic protection
system results in the reconfiguration of any of the components of the system, then the
reconfiguration must also be designed by a corrosion expert.
If the repair only involves the replacement of existing components, a corrosion expert does not
need to "sign-off on such work. However, after any repair/alteration of the impressed current
system is made, an evaluation of the cathodic protection survey must be conducted within six
months of the repair. If the repair/alteration results in any of the conditions found in Section 7.2
of this document being met, the cathodic protection survey must be conducted/evaluated by a
corrosion expert.
5.2.1 Rectifier Adjustment
Anyone who is considered qualified as a cathodic protection tester may adjust the rectifier
output/voltage of an impressed current cathodic protection system. An evaluation of the cathodic
protection system must be conducted whenever an adjustment to the rectifier is made. Before
making any adjustments to the rectifier, the power must be turned off. Open both the AC and the
DC circuit breakers.
It should be recognized that increasing the rectifier output could cause an increase in the
potential for stray current to be generated that may have a detrimental effect on other buried
metallic structures at the facility. Excessive rectifier output can also significantly shorten the life
of the anode ground bed since the anodes will be consumed more quickly than necessary. In
addition, care should also be taken to ensure that components of the rectifier do not become
overheated (causing a potential fire hazard) as a result of increasing the output.
When evaluating the operation and output of a rectifier, it is important to make all measurements
with a good quality multimeter. Do not rely on the output indicated by the voltmeter and/or
ammeter that may be installed on the rectifier. Most rectifier gauges are adjustable and you
should make any adjustment that may be indicated by measurement with the portable multimeter.
The gauges that are commonly built into rectifiers are usually not accurate and may even be
frozen in a fixed position. If the indicator needle is frozen on the rectifier voltmeter/ammeter and
cannot be freed, you should replace the gauge. If replacement is not accomplished, you should
note that the gauge is not functioning so that an observer will be able to discern that the gauge is
inoperable.
For the reasons given above and other considerations, a person qualified as a corrosion expert
should be consulted whenever the output is adjusted or repairs are made to the rectifier.
SECTION 6 - CATHODIC PROTECTION TESTING
6.1 Equipment
Although the equipment required to test cathodic protection systems is relatively simple, it is
very important that the equipment be maintained in good working order and is free of corrosion
and contamination. The basic equipment includes a voltmeter/ammeter (multimeter), reference
electrode, wires, clips and test probes.
It may also be necessary to have a current interrupter for impressed current systems when the
power cannot be easily cut on and off at the rectifier. A clamp-on type ammeter can be useful
when troubleshooting impressed current systems. Wire locators can help determine the location
of buried anode lead wires and header cables. Hand tools to clean corrosion or dielectric coatings
from the surface of the structure you are testing at the point of contact with lead wires/probes
may also be necessary.
6.1.1 Voltmeter/Ammeter
A good quality voltmeter/ammeter (multimeter) that has an adequate degree of accuracy is
essential for testing cathodic protection due to the low voltage/current involved. Most "low end"
voltmeters/ammeters are not capable of achieving results accurate enough to ensure reliable
results and should therefore not be used.
All testing of cathodic protection systems must be accomplished with a high internal resistance
(impedance of 10 meg-ohms or greater) voltmeter that is properly maintained and periodically
calibrated in accordance with the manufacturer's recommendations. The voltmeter should be
calibrated at least on an annual basis. It is important that the voltmeter has a high internal
resistance in order to avoid introducing a large error when measuring structure-to-soil potentials.
The voltmeter must have a high degree of sensitivity and must be placed in as low a scale as
possible (normally the 2 volt DC scale works well) in order to accurately measure the small
voltages associated with cathodic protection systems. All voltage measurements obtained should
be recorded as millivolts (mV). For example, a reading of-1.23 volts should be recorded as -
1230 mV; a reading of-.85 volts should be recorded as -850 mV.
Voltmeters that have a variable input resistance can be utilized to ensure that contact resistance
between the reference electrode and the electrolyte has been evaluated as a source of error
(voltage drop) in the observed structure-to-soil potential. This is accomplished by changing the
input resistance and noting whether or not the voltage observed changes significantly. If no
voltage change is observed when the input resistance is changed, it can be assumed that contact
resistance is not causing an error in the structure-to-soil potential measurement.
An ammeter that has a very low internal resistance is necessary when testing impressed current
systems in order to accurately determine the current output of the rectifier and/or individual
circuits in the system. Generally, amperage should only be measured where calibrated
measurement shunts are present. Alternatively, a "clamp-on" type ammeter may be utilized in
those cases where shunts are not present.
The batteries in the portable multimeter must also be in good condition. Batteries that are in poor
condition can cause unintended errors. If there is any question about the condition of the batteries
in the multimeter, they must be replaced.
6.1.2 Reference Electrode
A standard copper/copper sulfate reference electrode (also known as a half cell or reference cell)
must be utilized in order to obtain structure-to-soil potentials. The reference electrode must be
maintained in good working condition and must be placed in the soil in a vertical position when
conducting a test.
On those sti-Ps® tanks that have a PP4® test station, a reference electrode is permanently buried
in the tank pit. Since it is generally not possible to determine where the permanent reference
electrode was installed on these types of systems, it is also necessary to conduct structure-to-soil
potential measurements in the conventional manner (i.e. with a portable reference electrode in
the soil directly over the tank and at a remote placement). A tank may not be passed on the basis
of a structure-to-soil potential obtained with a PP4® test station. Both the local and the remote
potential obtained in the conventional manner must indicate that adequate cathodic protection
has been provided regardless of what the PP4® test station indicates.
Maintenance of the reference electrode is important for accurate results and includes:
a.
The copper-sulfate solution inside the reference electrode should be clear. If the solution
appears cloudy, this may indicate that the solution has become contaminated and the
reference electrode should be compared with the known standard as described in
paragraph e below. Should it be necessary to replace the solution, only distilled water and
new copper-sulfate crystals should be used. Excess copper-sulfate crystals must be
present in order to assure a saturated solution. Under average conditions, it is usually a
good idea to empty and replace the solution every 2 or 3 months.
b.
The porous ceramic tip must be maintained moist at all times. If the tip is allowed to dry
out, it may lose its porosity and a good low resistivity contact with the soil will not be
possible. Periodic replacement of the tip may be necessary.
c.
The copper rod inside the reference electrode should periodically be cleaned with non-
metallic sandpaper. Do not use black metal oxide sandpaper, steel wool or any other
metallic abrasive as this can cause the copper rod to become contaminated. If the copper
rod becomes contaminated, it is best to replace the reference electrode.
d.
The copper-sulfate solution must be free of contamination or errors will be introduced in
the readings you observe. If the reference electrode is submerged in water or placed in
moist soils that are contaminated, it is likely that the solution will become contaminated.
e.
The reference electrode that is used in the field must be periodically calibrated. How
often the reference electrode needs to be calibrated depends upon several different
factors. Among the more important factors that should be considered are the frequency of
use and the exposure of the reference electrode to contaminants. As a general rule,
calibration should be checked once every week if the reference electrode is used daily. If
the reference electrode is only periodically used, calibration should be checked prior to
each use.
Calibration of the reference electrode is accomplished by comparing it with another reference
electrode that has never been used. The unused reference electrode that is to act as the
calibration standard should be properly set up (ready for use) and must not have ever been used
in the field so that no chance of contamination exists.
To calibrate the field electrode:
1.
Place the voltmeter on the 2 volt DC scale (or lower) and connect the leads to the
reference electrodes as shown in the illustration below.
2.
Place both the field electrode and the standard electrode in a shallow nonmetallic
container that has one to two inches of tap water in the bottom of it. Do not use
distilled water. The reference electrodes must be placed vertically in the container
with the ceramic tip of each submerged in the water.
3.
Observe the potential measurement displayed on the voltmeter. If more than 10
mV potential exists between the two reference electrodes, the field reference
electrode should be properly cleaned and refilled with new solution until the
potential difference is 10 mV or less. If you are unable to achieve a 10 mV or less
potential difference after cleaning/reconditioning, the field electrode must be
replaced.
4.
In order to lessen the chance of cross contaminating the calibration electrode, you
should leave the calibration electrode in the water for the shortest time necessary
to complete the test.
6.1.3 Lead Wires/Test Probes/Miscellaneous
You should ensure that the insulation material of any lead wires is in good condition. Any clips
or probes used to make contact with the structure to be tested must be clean and free of
corrosion. A spool of suitable wire of sufficient length is necessary to conduct continuity and/or
"remote earth" testing. It is usually necessary to have a probe that can be attached to the end of a
tank gauging stick in order to contact the tank bottom since it is not uncommon for the test lead
on sti-P3 tanks to either be missing or discontinuous with the tank shell. A pair of locking pliers
can sometimes be useful when attempting to get a solid connection.
6.2 Test Criteria
There are three test criteria that can be utilized to indicate if adequate cathodic protection is
being provided to the structure being evaluated:
850 On - A structure-to-soil potential of-850 mV or more negative with the protective current
applied. This is commonly referred to as "850 on" or the "on potential". This criterion is
normally the only one available for galvanic systems since the protective current usually cannot
be interrupted.
Voltage drops (see Section 6.3) other than those across the structure to electrolyte boundary must
be taken into consideration whenever this criterion is applied. Voltage drops may have a
significant impact on the potentials observed when testing impressed current systems with the
protective current applied. Therefore, the 850 on criterion is not applicable to impressed current
systems.
850 Off- A structure-to-soil potential of-850 mV or more negative with the protective current
temporarily interrupted. This is referred to variously as "850 off', "polarized potential" or
"instant off potential". This criterion is applicable to impressed current and galvanic systems
where the protective current can be interrupted. Caution must be exercised when testing
impressed current systems to ensure that no active sacrificial anodes are also installed near the
protected structure. If there are active anodes influencing the observed potential, the 850 off
criterion is not applicable.
The instant off potential is the 2nd value that is observed on a digital voltmeter the instant the
power is interrupted. The first number that appears immediately after power interruption must be
disregarded. After the second number appears, a rapid decay (depolarization) of the structure will
normally occur. In order to obtain instant off potentials, a current interrupter or a 2nd person is
necessary. If a current interrupter is not available, have the second person throw the power
switch at the rectifier off for 3 seconds and then back on for 15 seconds. Repeat this procedure
until you are sure an accurate instant off reading has been obtained.
This criterion is considered by most to be the best indicator that adequate cathodic protection has
been provided. Therefore, consideration should be given to adjusting the rectifier output upward
until the 850 off criterion has been met if this is feasible.
100 mV Polarization - A polarization voltage shift of at least 100 mV. Commonly referred to as
"100 mV polarization" or "100 mV shift". This criterion is applicable to galvanic and
impressed current systems where the protective current can be temporarily interrupted. Either
the formation or the decay of at least 100 mV polarization may be used to evaluate adequate
cathodic protection.
The "true" polarized potential may take a considerable length of time to effectively form on a
structure that has had cathodic protection newly applied. If the protective current is interrupted
on a metallic structure that has been under cathodic protection, the polarization will begin to
decay nearly instantaneously. For this reason, it is important that the protective current not be
interrupted for any significant length of time. Generally, not more than 24 hours should be
allowed for the 100 mV depolarization to occur. On a well-coated structure complete
depolarization may take as long as 60-90 days. Complete depolarization of uncoated structures
will usually occur within 48 hours although it could take as long as 30 days.
The base reading from which to begin the measurement of the voltage shift is the instant off
potential. For example, a structure exhibits an on voltage of-835 mV. The instant off voltage is -
720mV. In order to meet the 100 mV polarization criteria, the structure-to-soil potential must
decay to at least -620 mV (final voltage).
The use of native potentials to demonstrate the formation of 100 mV polarization is generally
only applicable when a system is initially energized or is re-energized after a complete
depolarization has occurred. This is because it is necessary to leave the reference electrode
undisturbed (or returned to the exact position) between the time the native and the final voltage
are obtained.
It is only necessary to conduct a 100 mV polarization test on that component of the UST system
where the lowest (most positive) instant off structure-to-soil potential exists in order to
demonstrate that the UST system meets this criterion. If the criterion is met at the test point
where the potential is most positive, it can be assumed that it will be met at all other test
locations.
6.3 Voltage (IR) Drops
The effect voltage drops have must be considered whenever structure-to-soil potentials are
obtained during the survey of a cathodic protection system. The concept of voltage drops is a
difficult and controversial subject and a full discussion is beyond the scope of this document.
However, stated in the simplest terms, a voltage drop may be thought of as any component of the
total voltage measurement (potential) that causes an error.
The term IR drop is sometimes used and it is equivalent to voltage drop. IR drop is derived from
Ohm's Law which states that V = I R. In this equation, V stands for voltage, I represents current
(amperage) and R stands for resistance. Because the observed voltage is equal to the amperage
(I) multiplied by the resistance (R) a voltage drop is commonly referred to as an IR drop. There
are various sources of voltage drops and two of the more common are discussed below.
Current Flow - Whenever a current flows through a resistance, a voltage drop is necessarily
created and will be included whenever a measurement of the electrical circuit is conducted. In
order to effectively eliminate this voltage drop when testing impressed current systems, it is
necessary to interrupt the protective current. The magnitude of the voltage drop obtained on
impressed current systems is evaluated by conducting both on and instant off potential
measurements.
To illustrate how this type of voltage drop contributes to the potential observed when measuring
impressed current systems consider the following example. A potential of-950 mV is observed
when the rectifier is on. A potential of -700mV is observed when the power is interrupted.
Taking the absolute values (negative is dropped), the voltage drop component of the on potential
is 250 mV (950 - 700 = 250). Figure 2 is a graphical representation of this voltage drop and also
shows how the instant off potential will degrade over time until the native potential is reached.
Raised Earth - All active anodes will have a voltage gradient present in the soil around them
producing a "raised earth effect". An abnormally high (more negative) potential will be
observed if the reference electrode is within the voltage gradient of an active anode. The
magnitude or area of influence of the voltage gradient is dependent predominantly on the voltage
output of the anode and the resistance of the soil. Unfortunately, there is no "rule of thumb"
guidance that can be given to determine how far away you must be from an anode in order to be
outside the voltage gradient. If you suspect the potential you obtain may be affected by raised
earth, you should take a remote reading and compare the two.
Because of the raised earth effect, it is necessary to place the reference electrode as far away
from any active anode (and still be directly over the structure) when obtaining local potentials on
galvanic systems. Since the protective current can not typically be interrupted in galvanic
systems, any effect this type of voltage drop may have is evaluated by placing the reference
electrode remote. Placement of the reference electrode remote ensures that the reference
electrode is not within the voltage gradient of an active anode. Since it is desirable to eliminate
any effect voltage drops may have, it is necessary to obtain both local and remote structure-to-
soil potentials on galvanic systems. Any effect raised earth may have when testing impressed
current systems is eliminated by temporarily interrupting the power.
6.4 Stray Current
An unintended current that is affecting the structure you are trying to protect is referred to as a
stray current. Stray currents can cause rapid corrosion failure of a buried metallic structure and
are caused by an electric current flowing through the earth in an unintended path. If the metallic
object you are trying to cathodically protect is buried near the path of the stray current, the
current may "jump-on" the protected structure because it offers a lower resistance path for the
current to flow. The affected structure will be cathodic where the stray current enters but will be
highly anodic where the stray current returns to the earth. At the point where the current
discharges, rapid corrosion of the structure intended to be protected will occur.
Although stray currents are relatively rare on UST systems, common sources include: a) Railroad
crossing signals (powered by batteries); b) Traffic signals that have induction type sensors buried
in the pavement; c) Portable or fixed emergency power generators; d) Electrical railway systems
such as streetcars or subways in urban areas; e) DC welding operations and other types of
industrial machinery or processes that utilize DC power.
If unsteady readings are observed on the protected structure and you have determined that it is
not because of a bad electrical connection, you should suspect that stray current is affecting the
protected structure. In some cases, a pattern can be seen in the potential whereby it alternates
between two relatively stable readings. These patterns can sometimes help to identify the source
of the stray current. If you suspect that stray current may be affecting the UST system, a
thorough investigation must be conducted as soon as possible by a qualified corrosion expert
since stray current can cause a rapid failure of the affected structure.
Cathodic Interference - When the impressed current cathodic protection system operating on
the structure you are trying to protect causes an unintended current on some other nearby
structure, this type of stray current is referred to as "cathodic interference". Cathodic interference
can cause a rapid failure of the water lines and other buried metallic structures at the facility
where the cathodic protection system is operating. If you observe what you believe to be an
abnormally high (more negative) potential on a buried metallic structure, you should suspect that
the impressed current system operating on the UST system is causing cathodic interference.
Instances where cathodic interference may be present include: a) copper water lines that are not
bonded to the impressed current system and have a polarized potential of greater than -200 mV;
b) metallic flex connectors associated with fiberglass reinforced plastic piping that have
abnormally high (more negative) potentials and are not bonded to the impressed current system;
c) sti-P3® tanks are buried at a facility where there is an impressed current system operating and
are not bonded to the negative circuit. When the sti-P3® tanks have zinc anodes and a potential
more negative than -1100 mV (more negative than -1600 mV in the case of magnesium anodes)
is observed, it is likely that cathodic interference is occurring. Because of the potential for stray
current to impact sti-P3® tanks, it is normally necessary to bond them into the impressed current
system. A corrosion expert must be consulted whenever cathodic interference is suspected in
order to properly investigate and make any repairs/modifications that may be necessary.
6.5 Dissimilar Metals/Bimetallic Couples
The effect bimetallic couples may have must also be considered whenever structure-to-soil
potentials are obtained during the survey of a cathodic protection system. The concept of
dissimilar metals/bimetallic couples and the impact they can have on the proper evaluation of
cathodic protection systems is a difficult and controversial subject and a full discussion is beyond
the scope of this document. However, you should be aware that bimetallic couples may
substantially influence the structure-to-soil potentials of a tank system to the extent that the 100
mV polarization criterion is not applicable. Because the validity of the 100 mV criterion may be
suspect, consideration should be given to only utilizing the -850 mV instant off criterion when
evaluating impressed current systems. A brief discussion follows.
Caution must be exercised when evaluating steel UST systems that have metals of lower
electrochemical potential electrically connected to them. Typically, bimetallic couples are only
of concern on impressed current systems since those steel components protected by galvanic
systems are electrically isolated from other metallic structures. Copper is the metal of lower
potential that is commonly of concern. Sources of copper at UST facilities include the water
service lines and the grounding system of the electrical power grid. Since the AC power supply
to the submersible turbine pump should be continuous with the electrical service grounding
system, which may in turn be continuous with the water lines, a significant amount of copper
may be coupled to the steel UST system.
The effect this type of bimetallic couple has on the impressed current system can sometimes be
clearly seen on those UST systems that store fuel for emergency power generators. Commonly
these generator tank systems are installed with copper supply and return lines. When these tanks
were retrofitted with an impressed current system, the copper lines were bonded into the cathodic
protection system. In these instances, it is not uncommon to observe native structure-to-soil
potentials on the UST system of-450 mV or more positive.
If the native structure-to-soil potential of the UST system is substantially lower than what you
would normally expect, it is likely that a significant amount of copper is electrically bonded to
the UST system. Typically, the expected native potential of a steel UST system should not be
more positive than -500 mV.
To illustrate the effect of the copper-steel couple, consider the following example: A steel UST
system that is coupled to copper has a native structure-to-soil potential of -300 mV with the
bimetallic couple intact. If the copper couple is broken the UST system native potential is -600
mV. With the copper couple intact, the polarized (off) potential of the UST system -450 mV.
Although the voltage shift satisfies the 100 mV polarization criterion (from -300 mV to -450
mV), it is likely that the steel UST system is not adequately protected. This is because the UST
system is not polarized at least 100 mV beyond the native potential of the steel. Since the true
native potential of the steel UST system in this example is -600 mV, you would need to reach a
polarized (instant off) potential of-700 mV or more negative.
Because the unaffected native potential of steel UST systems is generally not known, the
application of the 100 mV polarization criterion would be inappropriate when there is a
significant amount of copper (or other more noble metal) electrically continuous. For this reason,
it is always desirable to demonstrate that the UST system satisfies the 850 off criterion when
evaluating a cathodic protection system.
6.6 Other Test Considerations
Various other factors can affect the accuracy of structure-to-soil potentials. Listed below are
some of the more common factors that you should keep in mind:
Contact Resistance - In order to obtain an accurate structure-to-soil potential, a good (low
resistivity) contact between the reference electrode and the soil must be made. Sometimes, the
soil at the surface is too dry and water needs to be added in order to lower the resistance between
the reference electrode and the soil. In addition, if the porous ceramic tip of the reference
electrode becomes clogged or contaminated it should be replaced since this in itself can cause a
high contact resistance.
Contaminated Soil - You should ensure that the soil the reference electrode is placed in is free
of contamination. Hydrocarbon contamination can cause a high resistance between the reference
electrode and the soil.
Current Requirement Testing - When a current requirement test is conducted on galvanically
protected tanks (refer to STI R972-01 for a description of this test), the affected structure can
exhibit an elevated (more negative) structure-to-soil potential during the test and for a period of
time after the test is completed. This is due to a temporary polarization of the tested structure
which will dissipate over a period of time ranging from a few minutes to perhaps a few days
depending on several different factors. Therefore, time sufficient for the temporary polarization
of the affected structure to "drain-off after a current requirement test is conducted must be
allowed before an accurate structure-to-soil potential can be obtained. In addition, any potential
measured with the battery connected should be disregarded as this measurement contains a large
voltage drop. Only instant off voltages are meaningful when the battery is connected.
Drought Conditions - On occasion, it has been observed that structure-to-soil potentials can be
improved by running water into the backfill material of the tank bed when extended periods of
no rain have occurred. This is commonly done by placing a water hose in one of the tank bed
monitoring wells (or other access points) and allowing the water to run for a period of a few
hours. This practice serves to lower the resistance of the backfill material. However, you should
keep in mind that the resistivity of the soil is not appreciably lowered if the moisture content is
20% or higher.
Electrical Shorts - When a substandard reading is observed on a galvanically protected system,
it is common to find that some other metallic object is electrically connected to the protected
structure. For instance, on sti-P3® tanks, the nylon bushings installed in the tank bungs were
sometimes removed when the various risers and other tank system components were installed or
an electrical conduit was buried in contact with the tank shell.
Electromagnetic Interference - Overhead high voltage power lines, railroad crossing signals,
airport radar systems and radio frequency transmitters (CB radios, cellular phones, etc.) can all
cause an interference that will result in an inaccurate voltage reading.
Galvanized Metals - Buried metals that have a high electrochemical potential can also influence
the voltage observed if the reference electrode is placed in close proximity to such metals. For
instance, the steel of some of the man ways that are installed to provide access to the tank
appurtenances may be galvanized. If the reference electrode is placed in the soil of such a
manway, an artificially high (more negative) potential may be observed. This is actually a raised
earth effect although the galvanized metal is not acting to cathodically protect the buried
structure of concern.
Parallel Circuits - Care should be taken to ensure that the person conducting the structure-to-
soil testing does not allow their person to come into contact with the electrical components of the
testing equipment. If the person touches the electrical connections, an error may be introduced
due to the creation of a parallel circuit.
Pea Gravel - Because pea gravel or crushed stone typically has a very high electrical resistivity,
it is necessary to ensure that it is saturated with water when attempting to measure structure-to-
soil potentials with the reference electrode placed in the pea gravel. Evaluate any effect high
contact resistance may have by changing the input resistance of the voltmeter as described in
Section 6.1.1. As an alternative way to evaluate the effect contact resistance may have, place the
reference electrode remotely. If the remote reading is substantially more negative than the local,
high resistance is indicated. Placement of a saturated sponge on the surface of the pea gravel may
help overcome high contact resistance.
Photovoltaic Effect - It is known that sunlight striking the viewing window of a reference
electrode can have an effect (as much as 50 mV) on the voltages observed when conducting
testing. You should ensure that the viewing window of the reference electrode is kept out of
direct sunlight. As an alternative, the viewing window can be covered with black electrical tape
in order to prevent any sunlight from reaching the copper-copper sulfate solution.
Poor Connection - If the observed structure-to-soil potentials are unsteady and the voltmeter
will not stabilize, you should suspect a bad connection somewhere. Ensure that all electrical
connections are clean and tight and good contact is made between the test lead and the structure.
Shielding - Sometimes, a buried metallic structure that is between the reference electrode and
the structure you are attempting to test will cause the reference electrode to be unable to "see"
the structure you are testing. Shielding is commonly cited when low potentials are observed with
the reference electrode placed locally over sti-Pj tanks due to the various tank risers, pump
heads, piping, electrical conduits and metallic manways that are typically located over the tank.
Temperature - The temperature of the reference electrode affects the voltages that are observed
when conducting cathodic protection testing. You may need to make a correction to the observed
potential in some extreme and/or marginal cases. The "standard" temperature is considered to be
77° F. For every degree less than 77 add 0.5 mV from the observed voltage. For every degree
above 77 subtract 0.5 mV from the observed voltage. To illustrate this, consider the following (in
order to simplify the calculation, the negative sign is dropped from the structure-to-soil
potential): A voltage of 845 mV is observed when the temperature is 57° F. In this case the
corrected voltage would then be 855 mV (20° X 0.5 mV = 10 mV. Therefore: 845 mV + 10 mV
= 855 mV).
6.7 Continuity Testing
When conducting an evaluation of a cathodic protection system, it is normally necessary to
establish that the cathodically protected components of a UST system are either electrically
isolated or electrically continuous depending on the type of cathodic protection system.
Ohmmeters (continuity testers) such as those utilized to test automotive wiring circuits are not
acceptable for use on buried metallic structures and should never be used for testing continuity of
UST system components. The "fixed cell-moving ground" method and the "point-to-point"
method are the two commonly utilized ways to test continuity and are discussed in more detail
below.
Fixed Cell - Moving Ground Method - The most commonly accepted method of conducting a
continuity survey is referred to as fixed cell - moving ground. In this method, the reference
electrode is placed at a location remote from any of the cathodically protected structures.
Potentials of all the metallic structures present at the site are then measured without moving the
reference electrode (refer to Appendix E for a more complete description). Because the
conditions found at the reference electrode/electrolyte interface can change over a short period of
time (causing the observed potential to change), it is important to conduct this type of testing as
quickly as possible.
When determining whether electrical continuity or isolation is provided, the following guidelines
are generally accepted for fixed cell - moving ground surveys:
> If two or more structures exhibit potentials that vary by 2 m V or less, the structures
are considered to be electrically continuous.
> If two or more structures exhibit potentials that vary by 10 mV or greater, the
structures are considered to be electrically isolated.
> If two or more structures exhibit potentials that vary by more than 2 mV but less than
10 mV, the result is inconclusive and further testing (point-to-point) is necessary.
Point-to-Point Method - An easier and usually more accurate way to test continuity is the
"point-to-point" method. With this method, a reference electrode is not utilized. The two
structures that are to be tested are simply touched with each lead of the voltmeter and the voltage
difference (if any) is observed. For example, if you are trying to establish that electrical isolation
exists between a tank and the fill riser associated with that tank, you would simply touch the fill
riser with one of the voltmeter leads and the tank shell with the other voltmeter lead and observe
the voltage difference.
When conducting point-to-point testing, any current that is flowing through the UST components
can cause an inaccurate test result. Impressed current systems must be turned off.
When determining whether electrical continuity or isolation is provided, the following guidelines
are generally accepted for point-to-point surveys:
> If the voltage difference observed between the two structures is 1 mV or less, the two
structures are considered to be electrically continuous with each other.
> If the voltage difference observed between the two structures is 10 mV or greater, the
two structures are considered to be electrically isolated from each other.
> If the voltage difference observed between the two structures is greater than 1 mV but
less than 10 mV, the result is inconclusive and further testing beyond the scope of this
document is necessary.
6.7.1
Continuity Testing of Galvanic Systems
In order for sacrificial anodes to function efficiently, the protected component must be
electrically isolated from any other metallic structures that may be connected to or in contact
with the protected structure. This is generally accomplished through the use of dielectric
bushings and unions and by making sure that no additional metallic structures come into contact
with the protected structure.
On those systems where adequate cathodic protection has not been achieved, it is common to
find that some unintended metallic structure is electrically continuous with the protected
structure. Frequently, an electrical conduit is in contact with a sti-P3® tank or the tank bung nylon
bushings are missing or damaged. If metallic tank hold down straps were improperly installed,
they will wear through the epoxy coating on the tank over time and cause premature anode
failure. With metallic piping, the shear valve anchoring bracket usually provides an electrical
bond with the dispenser cabinet and all of the other metal connected to it. When this is the case,
the anodes are trying to protect much more metal than intended and the life of the anodes is
shortened.
6.7.2 Continuity Testing of Impressed Current Systems
All protected components of the UST system must be electrically continuous in an impressed
current cathodic protection system. Various bonds may be required in order to ensure that
continuity has been provided. Failure to establish continuity in an impressed current system can
result in accelerated corrosion of the electrically isolated components.
Carefully check all bonds when evaluating an impressed current system as these are of critical
importance. Commonly, tanks are bonded into the negative circuit by attachment to the tank vent
lines above ground. Because of this, it is easy for the integrity of the bonds to be compromised. It
is equally important to ensure that the positive lead wire(s) have continuity. Any break in the
insulation or dielectric coating of the positive circuit will allow current to discharge from the
break and cause rapid corrosion failure of the wire. This is why it is absolutely critical that all
buried positive circuit splices are properly coated and insulated.
6.8
Reference Electrode Placement
6.8.1 General
Where you place the reference electrode when taking structure-to-soil potential measurements is
of critical importance. It is also essential that the exact location of the reference electrode
placement is documented so that anyone could come back at a later date and reasonably
duplicate the test. Reference electrode placement must be indicated by both written description
and visually shown on a drawing of the tank system. The forms in Appendix K and L of this
guidance document provide for both written and visual description of reference electrode
placement.
6.8.2 Local Placement
Placement of the reference electrode is considered local when it is in the soil directly over the
structure that is being tested. As discussed in Section 6.3, consideration of any effect active
anodes have (raised earth) must be considered when selecting the appropriate location for local
placement.
In addition, shielding of the reference electrode by other buried metallic components may also
need to be considered. For instance, it is necessary to ensure that the tip of the reference
electrode is below the metallic skirting found on most man ways. If the tip of the reference
electrode is not below the metal skirt, it may be shielded from "seeing" the cathodic protection
current.
Ideally, the tip of the reference electrode should be as close to the structure-to-soil interface as is
practical in order to minimize the voltage drop present in the soil due to resistivity. In practice,
about 6 inches of soil between the tip of the reference electrode and the structure being tested
works well.
6.8.3 Remote Placement
The remote potential represents the average potential of the entire surface of the protected
structure. The purpose of remote placement is to eliminate any effect that raised earth may be
contributing to the measurement of the structure-to-soil potential and to overcome any effects
shielding may have.
Placement of the reference electrode is considered remote when it is placed in the soil a certain
distance away from the structure that is being tested. There are several different factors that
determine the distance necessary in order to reach remote earth and a full discussion is beyond
the scope of this document. However, a remote condition can normally be achieved when the
reference electrode is placed between 25 and 100 feet away from any protected structure.
Depending on the conditions specific to the particular location where the cathodically
protected structure is, the minimum distance to remote earth may be considerably more than
25 feet. Therefore, it is important that you establish that the reference electrode is truly
remote when obtaining a structure-to-soil potential. In order to ensure that remote earth has
been achieved, place the reference electrode at least 25 feet away from the protected structure
and observe the potential. Move the reference electrode out away from the protected structure
another 10 feet or so and observe the potential. If there is no significant difference in the two
potentials, it can be assumed that remote earth has been achieved. If there is a significant
difference, continue moving the reference electrode out away from the protected structure
until no significant difference is observed.
When selecting a location to place the reference electrode to establish remote earth, it is
essential that there are no other cathodically protected structures (e.g. natural gas lines) in
proximity to the reference electrode. Foreign cathodically protected structures can cause an
abnormally high (more negative) potential that is not indicative of the remote potential of the
structure you are measuring. It is also important that there are no other buried metallic
structures in the vicinity of the reference electrode. Any metallic structure that is buried near
the reference electrode could possible affect the structure-to-soil potential that is observed on
the protected structure. In addition to the above considerations, you should attempt to select
the remote placement such that the reference electrode can "see" the structure you are testing.
This means that there should not be any buried metallic structure between the remote
reference electrode placement and the protected structure. If you suspect that shielding may
be affecting the observed potential, place the reference electrode away from the protected
structure in a different direction.
6.8.4 Galvanic Placement
All galvanic cathodic protection systems must be tested with the reference electrode placed
both local and remote. In order to pass the structure-to-soil survey, both the local and the
remote potentials must indicate that adequate cathodic protection has been provided. If
neither the local or the remote potential satisfies one of the cathodic protection criteria, the
structure fails the test. If one of the potentials indicates adequate cathodic protection but the
other does not, the result of the test is inconclusive. If the test result is inconclusive, repairs
must be made or a corrosion expert must evaluate the data and/or conduct further testing to
declare either pass or fail.
6.8.5 Impressed Current Placement
Impressed current cathodic protection systems are only required to be tested with the
reference electrode placed locally. In order to pass the survey, the potential obtained with the
reference electrode placed locally must satisfy either the 850 off or the 100 mV polarization
criteria. While only one test point is required, the tester should obtain structure to soil
potentials from as manysoil access points along the structure as is practical. If any of the
potentials indicate that adequate cathodic protection has not been provided, the structure
should be failed. Although not required by this guidance, it may be useful to place the
reference electrode remotely when testing an impressed current system. The remote potential
may provide additional information by which to evaluate the cathodic protection system.
However, the structure may not be passed based on the remote potential itself. In all
circumstances, the potential obtained with the reference electrode placed locally must indicate
that adequate cathodic protection has been provided.
Additionally, special circumstances may require that a remote potential be obtained when
testing impressed current systems. For instance, if there are active sacrificial anodes buried in
close proximity to the structure being tested, the local potential may be influenced by raised
earth. The voltage drop caused by the sacrificial anodes would preclude the accurate
measurement of the local structure-to-soil potential. If it is known that sacrificial anodes are
impacting the potentials obtained locally, remote potentials must be obtained.
The remote potential obtained under these special circumstances must meet either the 850 off
or the 100 mV polarization criteria in order for the tested structure to pass the survey. An
explanation must be given in the "comments" of Section XVI of the MDEQ impressed current
cathodic protection evaluation form as to why the remote potential must be considered. The
remote potentials should be indicated on the form by designating remote in the location code
column of Section XVI.
6.9
Soil Access
All structure-to-soil potentials that are intended to satisfy one of the three acceptable criteria
found in Section 6.2 must be obtained with the reference electrode placed in the soil.
Therefore, the person conducting the evaluation must either confirm that soil access is
available or make prior arrangements with the owner of the UST system to secure access.
Under no circumstances is it allowable to place the reference electrode on concrete, asphalt,
or any other paving material to achieve satisfactory structure-to-soil potentials. Likewise, the
practice of placing the reference electrode on a crack or expansion joint of a concrete or
asphalt paving is not recognized as an acceptable method of obtaining satisfactory structure-
to-soil potentials.
Placement of the reference electrode in an observation (monitoring) well to obtain a passing
reading is also not allowed. While it may be useful to obtain data by placing the reference
electrode on a crack in the pavement or in an observation well, the structure-to-soil potentials
obtained by such placement are not in themselves acceptable to demonstrate adequate
cathodic protection.
Access may be provided by drilling holes through the pavement or the installation of proper
cathodic protection test stations. A practical way to provide soil access is to drill a V-i inch
diameter hole in the pavement so that a "pencil" type reference electrode (3/8 inch diameter)
can be inserted through the pavement and into the soil. Upon completion of the survey, the
hole
should be filled with a fuel resistant caulking material so that easy access can be provided at a
later date. As an alternative, a two inch hole could be drilled to allow use of a standard
reference electrode. A short length of PVC pipe could be epoxied in the hole and plugged
with a threaded cap. Various cathodic protection test stations/man ways are available for
installation. Whenever, a new tank system is installed or the pavement is reworked around an
existing system, provisions for access to the soil must be made so that adequate cathodic
protection testing may be accomplished.
6.10 Cathodic Protection Test Locations
Because there are many different possible tank and cathodic protection system configurations
that may occur, it is not feasible to attempt to illustrate every situation that may exist and the
examples given in the following sections are offered as representative of some typical
scenarios to illustrate the general principles. It may sometimes be necessary for you to utilize
judgement to apply the intent of this guidance document when circumstances arise that are
not specifically addressed in this guidance document.
All galvanic cathodic protection systems must be tested with the reference electrode placed
both locally and remotely. Impressed current systems are only required to be tested with the
reference electrode placed locally.
6.10.1 Galvanically Protected (sti-P3*) Tanks
The measurement of both local and remote structure-to-soil potentials is necessary when
evaluating sti-P3® tanks. The appropriate location to place the reference electrode locally
would be in the soil at the middle of the tank (see Figure 3). However, if access to the soil is
not available at the middle of the tank, the reference electrode may be placed at any point
along the centerline of the tank but not directly over the anodes at each end of the tank.
Caution should be exercised to ensure that there are no sacrificial anodes installed in the soil
around the submersible pump manway to protect any steel piping that may be associated with
the tank. If anodes are installed at the pump manway, the reference electrode must be placed
in the soil near the opposite end of the tank.
In addition to the local potential described above, a remote potential must also be obtained.
Remote generally means the reference electrode is placed in the soil at least 25 feet away and not
more than 100 feet away from the tank you are measuring (See Figure 4). Refer to Section 6.8.3
for a more complete discussion of remote reference electrode placement. Care must be taken that
the remote location is not in proximity to any other cathodically protected structure (e.g.
natural gas lines) or directly over any other kind of buried metallic structure. The remote
placement should be such that the reference electrode is aligned with the longitudinal axis of the
tanks and can "see" the anodes. This orientation is desirable in order to prevent shielding.
6.10.2 Galvanically Protected Metallic Piping
Both local and remote potentials are required on all galvanically protected metallic piping.
When metallic piping is protected by sacrificial anodes, several different possibilities exist as
to where would be the appropriate location to place the reference electrode to obtain local
potentials. Knowing where the anodes that are protecting the piping are installed is of critical
importance. When obtaining local potentials, the reference electrode must be placed in the
soil directly over the pipe to be evaluated at a point that is the most distant from any anode
that may be along the pipe.
Because it is a common practice to bury piping anodes at the submersible pump manway of a
tank, the appropriate location to place the reference electrode to obtain local potentials is at
the dispensers (See Figure 5). Remote placement of the reference electrode is also necessary.
When the piping anodes are installed at the dispensers, the appropriate local reference
electrode placement would be at the piping nearest the tanks (usually the submersible turbine
pump manway) as shown in Figure 6. Remote placement of the reference electrode is also
necessary.
When the piping anodes are located at both the tanks and the dispensers, the reference
electrode must be placed at the approximate center of the piping run to obtain local potentials
(See Figure 7). Remote placement of the reference electrode is also necessary.
When the anodes are installed at the center of the piping, or it is not known where the anodes
are installed, the reference electrode must be placed at both the tank and the dispenser end of
the piping to obtain local potentials (See Figure 8). Remote placement of the reference electrode
is also necessary.
6.10.3 Tanks Protected by Impressed Current
With impressed current cathodic protection systems, tank potentials are required to be
measured with the reference electrode placed locally. Where the location of the anodes is known
and they are relatively evenly distributed about the tank bed, the appropriate location to place
the reference electrode would be in the soil at the middle of the tank (See Figure 9). However, if
access to the soil is not available at the middle of the tank, the reference electrode may be
placed in the soil at any point along the centerline of the tank similar to that described in
Section 6.10.1.
As with the evaluation of any cathodic protection system, the location of the anodes in
relation to reference electrode placement can be of critical importance. When selecting the
appropriate local placement, it is necessary to place the reference electrode at the point over the
structure that is the most distant from any active anode due to the effects of attenuation.
Attenuation of the cathodic protection current may occur whereby effective protection is not
achieved at some point along a UST system. For instance, if all of the active anodes are along
one side of a tank bed, current distribution and attenuation may prevent sufficient protective
current from reaching the side of the tanks away from the anodes. The preferred placement of
the reference electrode would be along the centerline of the tanks at the end opposite to that
where the anodes are installed (See Figure 10).
If it is not known where the anodes are installed, at least one measurement is required along
the centerline of the tank. Testing should be conducted at as many locations along the centerline
of the tank as are available. If soil access is available at each end of the tank and in the middle,
all three structure-to-soil potentials should be recorded. If any one of the measured potentials
does not meet one of the acceptable criteria, the structure should be failed.
In addition, if it is possible to measure the individual circuits in an impressed current system,
a determination can be made as to which anodes are functional and how the current is
distributed throughout the groundbed. How the current is distributed should be considered
when choosing reference electrode placement when conducting a structure-to-soil potential
survey. If for instance it is known that the majority of the rectifier output current is directed to
only those anodes along one end of a tank bed, the reference electrode should be placed at the
opposite end of the tank bed.
6.10.4 Piping Protected by Impressed Current
With impressed current cathodic protection systems, pipe potentials are required to be
measured with the reference electrode placed locally. Just as with any other type of cathodic
protection system, knowing where the anodes that are protecting the piping are installed is of
critical importance. Due to the high degree of variability that exists in anode placement and
piping configurations, structure-to-soil potentials must be obtained by placing the reference
electrode at both the tank and dispenser end of any piping that is protected by impressed
current (See Figure 11).
6.10.5 "100 Foot Rule" for Piping
For both galvanic and impressed current systems, if more than 100 feet of piping exists
between any two anodes, the reference electrode must also be placed at the midpoint between
the two anodes that are separated by more than 100 feet (see Figure 12). In addition, if it is not
known where the piping anodes are located, there can be no more than 100 feet of piping
between any two test points. This midpoint placement is in addition to any other reference
electrode placement that may be required as noted above in Sections 6.10.1 through 6.10.
SECTION 7 -
DOCUMENTATION OF EVALUATION
7.1 Documentation
As with any kind of testing or work that is being performed at a UST facility, it is critical that
proper documentation be made of all activities and test procedures. Without proper
documentation, the evaluation of a cathodic protection system through the application of a
structure-to-soil potential survey is of little value.
Although it has been previously stated, the exact location where the reference electrode was
placed in order to obtain a passing structure-to-soil potential is of critical importance and cannot
be overemphasized. For this reason, an exact description of where the reference electrode was
placed for each structure-to-soil potential obtained during the survey is an absolute necessity.
Failure to properly document reference electrode placement will result in the survey being
deemed invalid.
Additionally, in order to effectively evaluate the survey of a cathodic protection system it is
essential to be able to clearly understand how the survey was conducted. Likewise, when a re-
survey of an existing system is being conducted it is important that the tester understands how
the previous survey was conducted. Various forms of documentation may be necessary in order
to clearly convey the procedures and survey results. In the sections that follow, some of the more
critical aspects of documentation are discussed in more detail.
7.1.1
As Built Drawings
If any modification to the construction of the cathodic protection system is made (e.g.
supplemental anodes) it is necessary to show the modification on the "as built" drawings. If no as
built drawing is available, you must indicate the location of any anode addition on the site
drawing that is constructed as part of the evaluation. As built drawings are required whenever a
cathodic protection system is installed or substantially modified. The drawings should include: a)
how many anodes were installed; b) what type of anodes were installed; c) where were the
anodes installed; d) how deep were the anodes installed; e) what type of wire was used; 0 how
were the wires bonded, etc.
7.1.2
Site Drawing
Whenever a cathodic protection survey is conducted, a site drawing depicting the UST system,
the cathodic protection system and any related features of the facility must be constructed. In
addition, you must indicate on the drawing where the reference electrode was placed for each of
the structure-to-soil potentials utilized to obtain a pass. Figure 13 is an example of a site drawing
that shows the type of information that is necessary to properly complete the evaluation.
While it is understood that you will not always know where all of the pertinent components of
the cathodic protection system may be buried, all that is known must be indicated. It is very
important to show where the anodes are located on the site drawing. If you do not know where
the anodes are buried, voltage gradients in the soil may help you determine the approximate
location as described in the raised earth discussion of Section 6.3.
Should any modifications to the cathodic protection system be made, it is very important that
such modifications be both visually indicated on the site drawing and a written narrative made
that describes the work conducted. If as built drawings are available, it is acceptable to utilize
these drawings for the purposes of meeting the requirements of this rule. Any modifications or
changes to the UST and/or cathodic protection systems that have been made since the
construction of the as built drawings must be included.
7.1.3 MDEQ UST Cathodic Protection Evaluation Forms
Whenever a cathodic protection survey is conducted in the State of Mississippi, the appropriate
form (s) prescribed by the MDEQ (Appendix K and/or L) must be utilized to document the
survey. However, use of the prescribed form(s) is not intended to limit other kinds of
documentation that may be desirable in order to complete the evaluation. For instance, it may be
necessary to provide a written narrative describing various aspects of the evaluation or a
repair/modification that are not captured by completion of the form(s) them selves.
7.1.4 Pass/Fail/Inconclusive
In order to assure uniformity in the manner in which cathodic protection evaluations are
documented, it is necessary to "make a call" as prescribed in the MDEQ cathodic protection
evaluation form found in Appendix K and L of this document. The terms "pass", "fail" and
"inconclusive" are utilized for this purpose. Therefore, it is necessary to clarify what these terms
mean and their applicability as related to the evaluation of cathodic protection systems utilizing
the MDEQ forms. An evaluation conducted by an individual who is only qualified as a cathodic
protection tester must result in one of three conclusions, pass, fail or inconclusive. If the person
conducting the evaluation is qualified as a corrosion expert, the evaluation must result in either
pass or fail.
Pass - The term "pass" as related to Section VI and Vll (tester's/corrosion expert's evaluation)
of the MDEQ galvanic/impressed current cathodic protection system evaluation forms is taken to
mean that the structure-to-soil potential survey indicates all of the protected structures at a
facility meet at least one of the three accepted criteria. Pass as related to Section XIV and XVI
(potential survey) of the respective MDEQ galvanic/impressed current cathodic protection
system evaluation forms means that the individual structure that is being tested meets at least one
of the accepted criteria.
Fail - The term "fail" as related to Section VI and VII (tester's/corrosion expert's evaluation) of
the MDEQ galvanic/impressed current cathodic protection system evaluation forms means that
the structure-to-soil potential survey indicates that there are one or more protected structures at a
facility that do not meet any of the accepted criteria. Fail as related to Section XIV and XVI
(potential survey) of the respective MDEQ galvanic/impressed current cathodic protection
system evaluation forms means that the individual structure that is being tested does not meet
any of the accepted criteria.
Inconclusive - The term "inconclusive" as related to Section VI (tester's evaluation) of the
MDEQ galvanic/impressed current cathodic protection system evaluation forms means that a
person qualified only as a tester is unable to conclusively evaluate the cathodic protection system
and a corrosion expert must "make the call". A cathodic protection tester must indicate
inconclusive whenever one or more of the conditions listed in Section 7.2 of this document are
applicable.
Inconclusive as related to Section XII and XV (continuity testing) of the respective MDEQ
galvanic/impressed current cathodic protection system evaluation forms means that it cannot be
determined if the individual structure that is being tested is either electrically isolated in the case
of galvanic systems or is electrically continuous in the case of impressed current systems.
Inconclusive as related to Section XIV of the MDEQ galvanic cathodic protection system
evaluation form is utilized when both the local and the remote potential measurements do not
result in the same conclusion. If for instance the local potential was -900 mV but the remote was -
700 mV an inconclusive would result since the local indicates that adequate cathodic protection
is provided but the remote does not.
7.2 Corrosion Expert's Evaluation
Because the MDEQ has allowed those individuals who may only have minimal training in the
principles of cathodic protection to conduct testing of such systems, it must be recognized that
there will be instances where the expertise of someone who is more qualified and better
understands the principles involved will be necessary.
Some of the more obvious scenarios where a person with a level of expertise equivalent to a
"corrosion expert" {as defined in Section 2.1 (280.12) of this document} are necessary are given
below. If any of the conditions given below are met, a corrosion expert must evaluate the survey
results obtained by a tester and/or conduct further testing and complete Section VII of the
MDEQ cathodic protection system evaluation form(s). If the structure-to-soil potential survey is
conducted by a person who is qualified as a corrosion expert, completion of Section VII of the
MDEQ form(s) is all that is necessary.
A corrosion expert is required to evaluate and/or conduct the survey when:
1.
Supplemental anodes are added to a galvanic cathodic protection system and an accepted
industry standard is not followed and/or properly documented.
2.
Supplemental anodes or other changes in the construction of an impressed current system
are made.
3.
It is known or suspected that stray current may be affecting the protected structure.
4.
The repair and/or addition of supplemental anodes to bare steel/galvanized piping that is
galvanically protected (see Section 5.1.3).
5.
An inconclusive was declared when testing a galvanically protected structure because
both the local and the remote potentials did not indicate the same result (one indicated
pass but the other indicated fail).
Although not specifically listed above, it should be recognized that there might be additional
circumstances that may arise that will require evaluation, and/or design by a corrosion expert.
7.3 What if the Evaluation Result is Fail?
It is important to properly notify the tank owner if an evaluation of the cathodic protection
system fails. Necessary repairs should be accomplished within 90 days of receipt of the "failed"
evaluation. The tank owner is responsible for ensuring that the cathodic protection system is
maintained in a manner that will provide adequate corrosion protection to the UST system.
As it is recognized that many factors may cause a lower than desired voltage to be obtained
during a structure-to-soil survey, there may be several different courses of action appropriate to
resolve the "fail". For instance, it is not uncommon to simply retest a sti-P3® tank that has failed
a cathodic protection survey at a later date and achieve a passing result.
Therefore, a 90-day re-testing period is allowed whenever a fail is obtained during which no
action is necessary to repair or modify the cathodic protection system. This applies only to those
galvanic and impressed current systems that appear to be in good working condition. If there are
obvious problems with a system or you are unable to achieve a pass within the 90-day window,
the tank owner must make any repairs and/or modifications that are necessary to achieve a pass.
Repairs and/or modifications must be completed as soon as practical but no more than 90 days
should be allowed after expiration of the "90 day window".
APPENDIX A - INDUSTRY CODES/STANDARDS, REFERENCES and REGULATIONS
INDUSTRY CODES/STANDARDS
American Petroleum Institute (API) RP1632 3rd Edition "Cathodic Protection of Underground
Petroleum Storage Tanks and Piping Systems".
American Petroleum Institute (API) RP1615 5lh Edition "Installation of Underground Petroleum
Storage Systems".
National Association of Corrosion Engineers (NACE International) RPO 169-96 "Control of
External Corrosion on Underground or Submerged Metallic Piping Systems".
National Association of Corrosion Engineers (NACE International) TM0101-2001
"Measurement Techniques Related to Criteria for Cathodic Protection on Underground or
Submerged Metallic Tank Systems".
National Association of Corrosion Engineers (NACE International) RP0285-2002 "Corrosion
Control of Underground Storage Tank Systems by Cathodic Protection".
Petroleum Equipment Institute (PEI) RP 100-2000 "Recommended Practices for Installation of
Underground Liquid Storage Systems".
Steel Tank Institute (STI) R892-91 "Recommended Practice for Corrosion Protection of
Underground Piping Networks Associated with Liquid Storage and Dispensing Systems".
Steel Tank Institute (STI) R972-01 "Recommended Practice for the Installation of Supplemental
Anodes for sti-P3® UST's".
REFERENCES
Department of Defense MIL-HDBK-1136 "Maintenance and Operation of Cathodic Protection
Systems".
Department of Defense MIL-HDBK-1136/1 "Cathodic Protection Field Testing".
REGULATIONS
Subtitle I of the Resource Conservation and Recovery Act published in the Code of Federal
Regulations Chapter 40 Part 280 "Technical Standards and Corrective Action Requirements for
Owners and Operators of Underground Storage Tank Systems".
APPENDIX B - GLOSSARY
100 mV POLARIZATION - One of the three criteria that are commonly accepted as indicating
adequate cathodic protection has been achieved. It is typically measured by interrupting the
protective current on an impressed current system. When the current is interrupted, an "instant
off" potential is recorded and the structure under cathodic protection is then allowed to
depolarize until a change of at least 100 mV in potential is observed. Not more than 24 hours
should be allowed for the depolarization to occur when conducting this test.
850 ON - One of the three criteria that are commonly accepted as indicating adequate cathodic
protection has been achieved. It is measured with the protective current applied and is typically
the only measurement possible with galvanic systems since the anodes cannot be disconnected.
This criterion is not applicable to impressed current systems since a large portion of the "on"
measurement can be comprised of a voltage drop when the protective current is applied.
850 OFF - One of the three criteria that are commonly accepted as indicating adequate cathodic
protection has been achieved. It is measured with the protective current interrupted (either the
power is cut off to the rectifier or the sacrificial anodes are disconnected). This criterion is
considered by most to be the best indicator that adequate cathodic protection has been provided.
ANODE - The electrode of an electrochemical cell where oxidation (corrosion) occurs. With
respect to cathodic protection, it can be thought of as the place where electrons leave the surface
of a metal. Common galvanic anodes are zinc and magnesium.
AMPERE (AMP) - The basic unit of current flow in an electric circuit. Amperage can be
thought of as "gallons per minute" in a water system.
AS BUILT DRAWINGS - Drawings that show how a system was actually installed in the field.
Sometimes, unforeseen factors prevent the installation of a system as it was intended in the
design drawings and this is why it is important to have detailed and accurate "as built" drawings.
ATTENUATION - The protective effects of cathodic protection current diminish as you move
away from the source of the protective current. To illustrate this, on an impressed current system
where the ground bed is installed only on one side of the tank bed, the end of the tanks away
from the ground bed will receive less protective current than the side of the tanks closest to the
anodes. Attenuation of protective current applies to galvanic systems as well.
CATHODE - The electrode of an electrochemical cell where reduction (and no corrosion)
occurs. With respect to cathodic protection, it can be thought of as the place where current enters
the surface of a metal.
CATHODIC PROTECTION - The technique of causing the entire surface of a metallic
structure to become a cathode with respect to its external environment (soil). This is
accomplished by supplying an electric current sufficient to overcome the tendency of naturally
occurring electrical currents to leave the metallic structure.
CATHODIC PROTECTION EVALUATION - The interpretation of whether or not a
cathodic protection system is providing sufficient corrosion protection. An evaluation
incorporates all cathodic protection testing, surveys, rectifier operation/output measurements,
consideration of voltage drops, condition of dielectric coatings, continuity, bond integrity, circuit
integrity and any other factors or site specific conditions that may have an influence on the
operation and effectiveness of a cathodic protection system.
CATHODIC PROTECTION SURVEY - Refers to the process whereby all of the structure-to-
soil measurements necessary to contribute to the final evaluation of a system are obtained.
CATHODIC PROTECTION TEST- Refers to the process whereby only a single structure-to-
soil measurement is obtained.
CONTINUITY - As related to cathodic protection, continuity means that two metallic
structures are electrically continuous. With impressed current systems all protected structures
must be continuous and this is normally accomplished through the use of wires referred to as
continuity bonds.
CORROSION - The deterioration of a material (usually a metal) caused by an electro-chemical
reaction with its environment. Corrosion of metals involves the flow of electrons (current)
between an anode and a cathode. Corrosion will occur where the electrons leave the surface of a
metal.
CURRENT TEST -A method of temporarily creating an impressed current cathodic protection
system on a galvanically protected structure so that it can be determined how much protective
current is necessary in order to achieve adequate cathodic protection. This is normally done by
connecting a 12-volt battery to the structure to be tested and to a temporary anode.
DIELECTRIC MATERIAL - A coating that does not conduct electricity. Various coatings are
utilized and some examples are the "fusion-bonded epoxy" found on factory coated steel piping
and coal tar epoxies commonly found on sti-P3® tanks.
DISTRIBUTED GROUND BED - Used to describe an anode configuration in which the
anodes are more or less equally distributed around the metallic structure that is intended to be
protected.
ELECTROLYTE - As related to UST cathodic protection systems, electrolyte refers to the soil
and/or water surrounding the metallic structure that is under cathodic protection.
ELECTROMAGNETIC INTERFERENCE - As related to corrosion protection, it is an
external electrical current that causes an error in a voltmeter measurement. Sources are
commonly associated with high voltage AC power lines, radio frequency transmitters and airport
radar systems.
FAIL-See Section 7.1.4.
FIELD INSTALLED - Refers to any impressed current system or sacrificial anode cathodic
protection system that is installed at a pre-existing UST location or when sacrificial anodes are
installed on new metallic pipe in the field. Any cathodic protection system except for those
associated with unmodified sti-Pj® tanks may be thought of as "field installed".
FINAL POTENTIAL (VOLTAGE) - The voltage that is observed at the end of the
depolarization period associated with the measurement of "100 mV polarization". The final
voltage must be at least 100 mV less than the "instant off' voltage in order to meet the 100 mV
polarization criterion for adequate cathodic protection.
"FIXED CELL - MOVING GROUND" - A technique for measuring continuity in a UST
system whereby the reference electrode is placed in the soil at a location remote from the UST
system and is left undisturbed (fixed cell) while potentials are measured on various parts of the
UST system (moving ground).
GALVANIC (SACRIFICIAL) ANODE - A metal of high electro-potential (see Appendix J)
that is used to protect another metal. Zinc and magnesium are two metals that are commonly
utilized in the protection of UST systems.
GALVANIC CATHODIC PROTECTION - A cathodic protection system that utilizes
sacrificial anodes to provide the protective current. The anode will corrode (sacrifice itself)
instead of the metal it is intended to protect. The anode provides a protective current (reverses
the electron flow) because it has a higher electrochemical potential than the metal it is intended
to protect. Galvanic systems are normally limited to the protection of well coated structures
because they have a very low driving potential.
IMPRESSED CURRENT ANODE - A metal that is utilized to deliver the current from a
rectifier to the soil in order to protect the intended metallic structure. Impressed current anodes
are commonly made of graphite, high silicon cast iron and "mixed-metal oxides" because the
metal must be highly resistant to corrosion in order to have an acceptably long life span.
IMPRESSED CURRENT CATHODIC PROTECTION - A cathodic protection system in
which the protective current is supplied by an external source (rectifier). The level of protective
current that is delivered to the structure is adjustable and is much higher than that associated with
galvanic anodes. For this reason, impressed current systems are utilized on those UST systems
that are uncoated or require a high amount of protective current.
INCONCLUSIVE - See Section 7.1.4.
INSTANT OFF POTENTIAL (VOLTAGE) - The voltage that is observed momentarily after
the power to an impressed current cathodic protection system is interrupted. It is used as the base
line from which to begin calculating a "100 mV polarization". The second number that appears
after the current is interrupted is considered the proper value to represent the instant off potential.
ISOLATION - As related to cathodic protection, isolation means that two metallic structures
are electrically discontinuous. With galvanic systems a protected structure must be electrically
isolated and this is normally accomplished through the use of nylon bushings and dielectric
unions.
LOCAL POTENTIAL (VOLTAGE) - The structure-to-soil potential of a metallic structure
that is measured with the reference electrode placed in the soil immediately over the protected
structure.
NACE INTERNATIONAL - Acronym for National Association of Corrosion Engineers
International.
NATIVE POTENTIAL (VOLTAGE) - The structure-to-soil potential exhibited before any
cathodic protection is applied.
ON POTENTIAL (VOLTAGE) - The structure-to-soil potential that is measured with the
protective current applied.
PARALLEL CIRCUIT - Can be caused by the person conducting the test making contact with
a metallic part of the test leads, or reference electrode when conducting structure-to-soil potential
measurements. The creation of parallel paths must be avoided since inadvertent errors can be
introduced.
PASS-See Section 7.1.4
PASSIVATION - When a metal undergoes passivation, an oxidation layer forms on the surface
of the metal due to corrosion and can be defined as the loss of chemical reactivity. The oxidation
layer acts as a coating and prevents or slows further corrosion of the metallic object since oxygen
is prevented from reaching the underlying metal.
PHOTOVOLTAIC EFFECT - Sunlight striking the electrolyte solution in a copper-copper
sulfate reference electrode can cause an error in the observed structure-to-soil potential and must
be avoided.
"POINT-TO-POINT" - A technique for measuring continuity in a UST system whereby each
lead of a voltmeter is connected to the two metallic structures of interest (negative lead to one
structure and positive to the other). The voltage difference (if any) measured with the voltmeter
connected in this manner indicates if continuity is present or not.
POLARIZATION - The change in the structure-to-soil potential of a metallic structure due to
the application of a protective current. In this guidance document, polarization is considered to
mean cathodic polarization - that is, the potential of the metal is shifted in the negative direction.
POLARIZED POTENTIAL - The structure-to-soil potential of a metallic structure that is
observed after the protective current is applied and sufficient time has elapsed for the structure to
completely polarize.
RAISED EARTH - Term used to describe the high voltage gradient found in the soil around an
active impressed current or sacrificial anode. Placement of the reference electrode in proximity
to an active anode will cause an abnormally high (more negative) structure-to-soil potential than
would be present if the anode were not in close proximity.
RECTIFIER - A device utilized in impressed current systems that changes AC power to DC
power.
REFERENCE ELECTRODE - Also referred to as a reference cell or a half-cell. A device
whose electrochemical potential is constant that is used to measure the structure-to-soil potential
of buried metallic structures. The potential that is observed on the buried metallic structure is
relative to the potential of the reference electrode. The potential of a buried metallic structure
would be zero if it were of the exact same composition as the reference electrode if all sources of
measurement error were eliminated.
RESISTANCE - A measurement of the tendency of a substance to inhibit the flow of electrical
current. Resistance in UST cathodic protection systems is generally meant to refer to the
electrical properties of the backfill materials (soil).
REMOTE EARTH - The structure-to-soil potential of a metallic structure that is measured
with the reference electrode placed in the soil at a point well away (remote) from the protected
structure. Remote earth is generally thought of as at least 25 feet and not more than 100 feet
away. Remote earth is established when the observed structure-to-soil potential does not
significantly change no matter how far away the reference electrode is from the protected
structure.
SACRIFICIAL ANODE - See Galvanic Anode.
SHIELDING - A structure that prevents or diverts an electrical current from reaching the
desired location. Normally thought of as something that stops a reference electrode from being
able to "see" the metallic structure that you trying to measure.
sti-P3® TANK - A steel tank manufactured to the standard created by the Steel Tank Institute
that comes from the factory with a "pre-engineered" cathodic protection system. The "P3" means
that the steel tank is protected in three ways: 1) A protective dielectric coating is factory applied;
2) Sacrificial anodes (normally zinc) are factory installed on the tanks and 3) dielectric bushings
are installed to facilitate electrical isolation of the tank.
STRAY CURRENT - An electrical current that travels along an unintended path. Normally
thought of as a current from some external source that enters a protected metallic structure at one
point that then exits at another point. The point where the stray current exits the protected
structure can be subject to intense corrosion and failure may rapidly occur.
STRUCTURE-TO-SOIL POTENTIAL - Also known as "pipe-to-soil potential' or "structure-
to-electrolyte potential" - The difference in the potential of the surface of a buried metallic
structure and the electrolyte (soil) that surrounds it with respect to a reference electrode in
contact with the electrolyte (soil). Can be thought of as the voltage difference between a buried
metallic structure and the soil that it is buried in.
VOLTAGE - The basic unit of force in an electric circuit. Voltage is equivalent to pounds per
square inch in a water system.
VOLTAGE (IR) DROP - With respect to UST cathodic protection systems, voltage drops may
be thought of as any voltage that causes an error in the observed structure-to-soil potential.
Whenever a current is flowing through a resistance, a voltage drop is present and is part of the
voltage measurement obtained.
GENERALIZED
INTERPRETATION
OF
STRUCTURE-TO-SOIL
POTENTIAL
MEASUREMENTS
(VOLTAGES) OBTAINED ON GALVANIC CATHODIC PROTECTION SYSTEMS
Listed in this table are some generalized observations that can be applied to the interpretation of structure-to-soil potentials.
Depending on the specific site conditions and other factors, differing interpretations are possible.
VOLTAGE (mV)
“ON”
GENERALIZED INTERPRETATION
POSITIVE
Test leads are reversed (negative should be connected to the reference electrode and the positive
should contact the structure you are testing in order to observe negative voltages). Could indicate
that stray current is affecting the structure (consult with a corrosion expert).
0 to -100
Usually occurs when you are attempting to measure a structure that has a test lead that is not
continuous with the tank. Because you are measuring the potential of a copper wire with reference
to the copper-copper sulfate half-cell, the potential is zero or very near it. Disregard test lead and
make direct contact with the protected structure.
-101 to -399
Try again – A reading in this range is not normally seen on an underground steel structure. Could
indicate that steel structure is electrically connected to a significant amount of a more noble metal
(e.g. copper). Very corroded low carbon steel may also be indicated.
-400 to -599
Steel structure does not meet regulatory requirements. Usually means that the steel structure has no
cathodic protection. Existing sacrificial anodes could be completely “burned-out” or were never
there to begin with.
-600 to -849
Steel structure does not meet regulatory requirements. Usually means that the steel structure has
anodes but for whatever reason, something is causing a low reading that may indicate adequate
cathodic protection has not been provided. The anodes may be trying to protect a structure that
requires more current than they can produce. The protected steel structure may not be electrically
isolated from all other metallic structures (conduct continuity testing). The environmental
conditions may not be favorable at the time you are attempting to obtain the reading. Retest during
the next 90 days to see if an acceptable reading can be obtained.
-850 to -1100
Steel structure protected by zinc anodes meets regulatory requirements and cathodic protection is
judged to be adequate. Readings in this range are what you would expect on most sti-P3® tanks that
have not been modified and are reading “good” since nearly all come from the manufacturer with
zinc anodes.
-850 to -1600
Steel structure protected by magnesium anodes meets regulatory requirements and cathodic
protection is judged to be adequate. Readings in this range are what you would typically expect on
steel piping that is reading “good” since magnesium anodes are generally installed on piping. You
may also find readings up to -1600 mV on a sti-P3® tank that has been retrofitted or was supplied at
the factory with magnesium anodes.
MORE NEGATIVE
THAN -1100 WITH
ZINC ANODES
ONLY
Voltages more negative than -1100 mV are theoretically not possible if there are only zinc anodes
installed. If you have a reading more negative than -1100 mV and you are sure magnesium anodes
are not present, you should suspect that stray current may be affecting the cathodically protected
structure. A corrosion expert should be contacted immediately since stray current can cause a
corrosion failure in a relatively short period of time.
MORE NEGATIVE
THAN -1600
Voltages more negative than -1600 mV are theoretically not possible with any sacrificial anode
cathodic protection system. If you have a reading more negative than -1600 mV on any galvanic
cathodic protection system, you should suspect that stray current may be affecting the cathodically
protected structure. A corrosion expert should be contacted immediately since stray current can
cause a corrosion failure in a relatively short period of time.
VARIABLE
If the voltmeter readings vary you should suspect that stray current may be affecting the
cathodically protected structure. Sometimes, the stray current can cause a pattern to develop that is
recognizable. An example would be the on/off pattern of a nearby DC powered welding operation.
A corrosion expert should be contacted immediately since stray current can cause a corrosion
failure in a relatively short period of time.
RAPIDLY
FLUCTUATING
If the voltmeter will not stabilize, it usually means that there is a high electrical resistance
somewhere. Check all lead wires and connections and make sure that you are making a solid and
clean metal to metal connection. Soil where the reference electrode is placed could be too dry. Add
water to the soil or wait until a heavy rain occurs and try again. Petroleum contaminated soils may
cause a high contact resistance. The tip of the reference electrode may need to be cleaned or
replaced.
APPENDIX C
GENERALIZED
INTERPRETATION
OF
STRUCTURE-TO-SOIL
POTENTIAL
MEASUREMENTS
(VOLTAGES) OBTAINED ON IMPRESSED CURRENT CATHODIC PROTECTION SYSTEMS
Listed in this table are some generalized observations that can be applied to the interpretation of structure-to-soil potentials.
Depending on the specific site conditions and other factors, differing interpretations are possible.
VOLTAGE (mV)
GENERALIZED INTERPRETATION
ANY POSITIVE
VOLTAGE OR
0 TO -100 “ON”
or “OFF”
Can indicate that the structure you are attempting to measure is not bonded to the impressed current
system (conduct continuity testing). Stray current could be affecting the protected structure (consult a
corrosion expert). Positive and negative wires could be reversed (negative must be to protected
structure and positive to anode). Test leads are reversed (positive lead should contact structure and
negative lead should be connected to reference electrode). Could indicate that you are measuring the
potential of a copper wire.
-101 to -399 “ON”
or “OFF”
Try again – A reading in this range is not normally seen on an underground steel structure. Could
indicate that steel structure is electrically connected to a significant amount of a more noble metal (e.g.
copper). Very corroded low carbon steel may also be indicated.
-400 to -599 “ON”
or “OFF”
Usually means that the steel structure has no cathodic protection. Existing impressed current anodes
could be completely “burned-out”. Continuity of anode lead wires (positive circuit) could be broken.
Negative bonds on the protected structures may be broken or non-existent.
-600 to -849 “ON”
or “OFF”
Usually means that the steel structure has some protection but for whatever reason, something is
causing a low reading that may indicate adequate cathodic protection has not been provided. The
impressed current system may be trying to protect a structure that requires more current than it can
produce (rectifier output too small). The impressed current system may not be capable of effectively
distributing the required current to all parts of the structure you are trying to protect (not enough
anodes, anodes improperly installed, soil resistivity too high). The steel structure that is intended to be
protected may not be electrically continuous with the other metallic structures under protection
(conduct continuity testing). The environmental conditions may not be favorable at the time you are
attempting to obtain the reading. Retest during the next 90 days.
-850 or MORE
NEGATIVE “ON”
Steel structure may or may not be adequately protected. Usually indicates that the impressed current
system is providing current to the structure although the reading normally includes a large voltage (IR)
drop. Because the flow of current through the soil causes a voltage drop, the on potential cannot be
used to indicate that adequate cathodic protection has been provided. Instant off potentials must be
utilized to demonstrate cathodic protection.
-850 or MORE
NEGATIVE
“OFF”
Steel structure protected by impressed current system meets regulatory requirements and cathodic
protection is judged to be adequate. A potential measurement of -850 mV or more negative with the
protective current temporarily interrupted (850 off) is considered to be the best indicator that adequate
cathodic protection has been provided.
MORE
NEGATIVE
THAN -1220 mV
“OFF”
Instant off potentials more negative than -1220 mV are theoretically not possible. If you observe an
instant off potential more negative than -1220 mV, you should suspect stray current is affecting the
protected structure. Consult a corrosion expert immediately since stray current can cause a rapid
corrosion failure of the protected structure.
MORE
NEGATIVE
THAN -2000
“ON”
Usually means that a high resistance exists in the ground bed that is causing a large voltage drop. This
condition is normally evident by checking the rectifier output since the voltage is very high but the
amperage is relatively low. However, you should be cautious when abnormally high voltages are
observed since this can have a detrimental effect on cathodically protected structures or the anodes
may be rapidly depleted. Stray current may also be generated that can adversely affect other buried
metallic structures such as water lines and other utilities. Consult a corrosion expert whenever it is
suspected that too much voltage is being generated.
VARIABLE
“ON” or “OFF”
If the voltmeter readings vary, you should suspect that stray current may be affecting the cathodically
protected structure. Sometimes, the stray current can cause a pattern to develop that is recognizable.
An example would be the on/off pattern of a nearby DC powered welding operation. A corrosion
expert should be contacted immediately since stray current can cause a corrosion failure in a relatively
short period of time.
RAPIDLY
FLUCTUATING
“ON” or “OFF”
If the voltmeter will not stabilize, it usually means that there is a high electrical resistance somewhere.
Check all lead wires and connections and make sure that you are making a solid and clean metal to
metal connection. Soil where the reference electrode is placed could be too dry. Add water to the soil
or wait until a heavy rain occurs and try again. Petroleum contaminated soils may cause a high contact
resistance. The tip of the reference electrode may need to be cleaned or replaced.
APPENDIX D
CONTINUITY TESTING PROCEDURE FOR GALVANIC/IMPRESSED CURRENT CATHODIC PROTECTION
SYSTEMS
Fixed Cell – Moving Ground Continuity Test Procedure
1.
Place reference electrode in contact with the soil at a location remote (25 – 100 feet) from all cathodically
protected structures. You must ensure that the remote reference electrode placement is not in proximity to any
other cathodic protection systems (e.g. natural gas pipelines) or directly over any buried metallic structure in
order to minimize the chances of unwanted interference.
2.
Be sure that reference electrode is firmly placed in moist soil and is not in contact with any vegetation.
3.
Connect reference electrode to the negative terminal of voltmeter using a long spool of suitable wire.
4.
Connect positive lead wire to voltmeter. This lead wire should have a sharp test prod (scratch awl or similar) in
order to assure good contact with the metallic structures under test.
5.
Place voltmeter on 2 volt DC scale.
6.
Contact each buried metallic structure with the positive test lead without moving the reference electrode.
Typical items that would be tested during a continuity survey include: all tanks, tank risers, submersible pump
heads, piping, flex connectors/swing joints, vent lines, electrical conduits, dispensers, utilities, etc.
7.
Obtain voltage for each component and record on MDEQ continuity testing form.
8.
Voltages for each component that is tested must be obtained as quickly as possible since the observed
potential can change over time. This is because the conditions in the soil where the reference electrode is
placed can change over a relatively short period of time.
Fixed Cell – Moving Ground Data Interpretation
If two or more structures exhibit potentials that vary by 2 mV or less, the structures are considered to be electrically
continuous.
If two or more structures exhibit potentials that vary by 10 mV or greater, the structures are considered to be
electrically isolated.
If two or more structures exhibit potentials that vary by more than 2 mV but less than 10 mV, the result is
inconclusive and further testing (point-to-point) is necessary.
Point-to-Point Continuity Test Procedure
1.
Turn off power to rectifier if testing an impressed current system. This is necessary to obtain accurate results.
2.
Connect test leads to voltmeter. Both test leads should have a sharp test prod or suitable clip lead in order to
make good contact with tested structures.
3.
Place voltmeter on 2 volt (or lower) DC scale.
4.
Connect one voltmeter test lead to one of the structures for which continuity is being tested and connect the
other voltmeter test lead to the other structure that is being tested.
5.
Record voltages observed on each of the two structures that are being compared and record on MDEQ
continuity testing form.
Note:
Testing with this method does not require a reference electrode. The two structures of interest are simply
connected in parallel with the voltmeter and a determination made as to whether or not any potential
difference exists between them.
Point-to-Point Data Interpretation
If the voltage difference observed between the two structures is 1 mV or less, this indicates that the two structures
are considered to be electrically continuous with each other.
If the voltage difference observed between the two structures is 10 mV or greater, this indicates that the two
structures are considered to be electrically isolated from each other.
If the voltage difference observed between the two structures is greater than 1mV but less than 10 mV, the result is
inconclusive and further testing beyond the scope of this document is necessary.
APPENDIX E
STRUCTURE-TO-SOIL TEST PROCEDURE FOR GALVANIC CATHODIC PROTECTION SYSTEMS
1.
Place voltmeter on 2 volt DC scale.
2.
Connect voltmeter negative lead to reference electrode.
3.
Place reference electrode in clean soil directly over the structure that is being tested to obtain local
potential. At least one local potential is required for each tank - the preferred test point is at the
approximate midpoint along the centerline of the tank. Piping may require measurement at each end of
the pipe and at the middle depending upon anode configuration (see Section 6.10.2 of MDEQ guidance
document).
The reference electrode may not be placed on concrete or other paving materials.
Ensure that the reference electrode is placed in a vertical position (tip down).
Ensure that the soil where the reference electrode is placed is moist – add tap water if necessary.
Ensure that the soil where the reference electrode is placed is not contaminated with hydrocarbons.
Ensure that the reference electrode window is not exposed to direct sunlight.
4.
Connect voltmeter positive lead to structure that is to be tested.
If a test lead wire is utilized to make contact with the tested structure you must ensure that
continuity exists between the test lead wire and the structure. This may be accomplished by
conducting a point-to-point continuity test as described in Appendix E.
Ensure that good metal-to-metal contact is made between the test lead clip/probe and the structure.
Ensure that no corrosion exists where the test lead makes contact with the structure.
Ensure that your body does not come into contact with the electrical connections.
Ensure that test leads are not submerged in any standing water.
Ensure that test lead insulation is in good condition.
sti-P3 tanks
If the test lead wire is not continuous or is not present, contact with the inside bottom of the
tank is necessary. This may be accomplished by connecting the voltmeter lead wire to a test
prod mounted onto the bottom of a wooden gauging stick and lowering the stick into the tank fill
riser. Be sure that firm contact is made with the tank bottom. Care should be taken to ensure
that any drop tube that may be installed in the tank does not prohibit contact with the tank
bottom. If a metallic probe bar is utilized to contact the tank bottom, ensure that the probe bar
does not contact the fill riser or any other metallic component of the UST system.
If a sti-P3 tank is equipped with a PP4 test station, the PP4 test station is disregarded and
potentials must be obtained with a portable reference electrode placed in the soil (both local
and remote) as described in Section 6.10.1 of the MDEQ guidance document.
5.
Obtain voltage and record in the local column on the MDEQ galvanic survey form.
6.
Place reference electrode in clean soil remote from the protected structure. (Refer to Section 6.10.3 for
a discussion of remote reference electrode placement.)
7.
Obtain voltage and record in the remote column on the MDEQ galvanic cathodic protection form. (Note:
if the fixed cell-moving ground method was used to conduct continuity survey, the potential obtained
during the continuity survey for each corresponding structure may be transposed to the appropriate
column.)
Data Interpretation (for a more complete discussion refer to Appendix C of this guidance document)
If both the local and the remote potential are –850 mV or more negative, the 850 on criterion is satisfied and
it is judged that adequate cathodic protection has been provided.
If either the local or the remote potential is more positive than –850 mV the test result is inconclusive and
further testing and/or repairs are necessary. Alternatively, a person qualified as a corrosion expert could
evaluate/conduct the survey and declare a pass or fail based on their interpretation and professional
judgement.
APPENDIX F
STRUCTURE-TO-SOIL TEST PROCEDURE FOR IMPRESSED CURRENT CATHODIC PROTECTION
SYSTEMS
1.
Inspect rectifier for proper operation and document necessary information. This includes measurement of output
voltage/amperage with a multimeter (do not rely on rectifier gauges) and measurement of individual anode circuits (if
installation allows such). Record all necessary information under Section XI and XII of MDEQ impressed current form.
2.
Place voltmeter on 2 volt DC scale.
3.
Connect voltmeter negative lead to reference electrode.
4.
Place reference electrode in clean soil directly over the structure that is being tested. At least one measurement must be
taken for each tank - the preferred test point is usually the center of the tank. Piping normally requires measurement at
each end of the pipe (see Section 6.10.3 and 6.10.4 of MDEQ guidance document for further explanation).
The reference electrode may not be placed on concrete or other paving materials.
Ensure that the reference electrode is placed in a vertical position (tip down).
Ensure that the soil where the reference electrode is placed is moist – add tap water if necessary.
Ensure that the soil where the reference electrode is placed is not contaminated with hydrocarbons.
Ensure that the reference electrode window is not exposed to direct sunlight.
5.
Connect voltmeter positive lead to structure that is to be tested.
Ensure that good metal-to-metal contact is made between the test lead clip/probe and the structure.
Ensure that no corrosion exists where the test lead makes contact with the structure.
Ensure that your body does not come into contact with the electrical connections.
Ensure that test leads are not submerged in any standing water.
Ensure that test lead insulation is in good condition.
6.
Obtain voltage potential with the protective current applied and record in the on column on the MDEQ impressed current
cathodic protection evaluation form.
7.
Without moving reference electrode from the position it was in during step 6 above, obtain voltage potential with the
protective current temporarily interrupted and record in the instant off column on the MDEQ impressed current cathodic
protection form.
The instant off potential is the 2nd value that is observed on a digital voltmeter the instant the power is interrupted.
The first number that appears immediately after power interruption must be disregarded. After the second number
appears, a rapid decay (depolarization) of the structure will normally occur.
In order to obtain instant off potentials, a current interrupter or a 2nd person is necessary. If a current interrupter is not
available, have the second person throw the power switch at the rectifier off for 3 seconds and then back on for 15
seconds. Repeat this procedure until you are sure an accurate instant off reading has been obtained.
8.
Conduct 100 mV polarization decay if you are unable to obtain an instant off potential of -850 mV or more negative in step
7 above. (Note: While not a requirement of this guidance document, consideration should be given to adjusting the rectifier
output until an instant off potential of -850 mV is achieved or the maximum safe output is reached.) It is only necessary to
conduct 100 mV polarization where the lowest (most positive) instant off potential is observed on the UST system.
100 mV of polarization is determined by leaving the power interrupted on the structure until a change of at least 100
mV in the structure-to-soil potential is observed. In calculating the 100 mV decay, the instant off potential obtained in
Step 7 above is utilized as the starting point (e.g. if instant off = -800 mV, power must be left off until decayed to -700
mV).
Calculate voltage change by subtracting final (or ending) voltage from the instant off voltage and record these values
in the appropriate columns on the MDEQ impressed current cathodic protection evaluation form.
Data Interpretation (for a more complete discussion refer to Appendix D of this guidance document)
If the instant off potential is -850 mV or more negative, the 850 off criterion is satisfied and it is judged that adequate
cathodic protection has been provided.
If the instant off potential is more positive than -850 mV, the tank may or may not be adequately protected and a 100 mV
polarization test is necessary.
If the structure exhibits more than 100 mV polarization, the 100 mV polarization criterion is met and it is judged that
adequate cathodic protection has been provided.
If you are unable to meet either the 850 instant off or the 100 mV polarization criteria, it is judged that adequate cathodic
protection has not been provided and repairs/modification are indicated. Alternatively, a person qualified as a corrosion
expert could evaluate/conduct the survey and determine that cathodic protection is adequate based on their interpretation.
APPENDIX G
CHECKLIST FOR GALVANIC CATHODIC PROTECTION SYSTEM SURVEY
Identified UST owner, UST facility, CP tester, tester’s qualifications and reason for survey (complete
Sections I – V of MDEQ galvanic cathodic protection form).
Described UST and cathodic protection system (complete Section X of MDEQ galvanic cathodic
protection form).
Constructed site drawing depicting all pertinent components of the UST and cathodic protection systems
at the facility (complete Section XII of MDEQ galvanic cathodic protection form).
Reviewed any previous cathodic protection design/repair/testing data that may be available.
Ensured soil access was available directly over each cathodically protected component at the facility
(see Section 6.9.2 of MDEQ cathodic protection guidance document for discussion).
Conducted continuity testing of all pertinent metallic components at the UST facility by the fixed remote
– moving ground and/or the point-to-point method (complete Section XII of MDEQ galvanic cathodic
protection form).
Obtained local structure-to-soil potentials on every cathodically protected structure with the reference
electrode placed in the soil directly over the structure under test (complete Section XIV of MDEQ
galvanic cathodic protection form).
Obtained remote potentials or transposed remote potentials obtained during continuity testing for every
cathodically protected structure to appropriate column in Section XIV of MDEQ galvanic cathodic
protection form.
Indicated location (by code or other means) of reference electrode placement on site drawing for each
structure-to-soil potential that was obtained during the survey.
Described any repairs and/or modifications that were made to the cathodic protection system (complete
Section XI of MDEQ galvanic cathodic protection form).
Indicated whether or not each protected structure met the –850mV on criteria for both the local and
remote reference electrode placement by indicating pass/fail/inconclusive in the appropriate column in
Section XVI of the MDEQ galvanic cathodic protection form.
If only qualified as a tester - indicated the results of the evaluation by marking either pass, fail or
inconclusive in Section VI of MDEQ galvanic cathodic protection form.
If only qualified as a tester - marked inconclusive if any of the conditions found in Section 7.2 of MDEQ
cathodic protection guidance document were applicable to survey.
If tester indicated inconclusive, either repairs were conducted or a corrosion expert evaluated/conducted
the survey and completed Section VII of MDEQ galvanic cathodic protection form.
If a corrosion expert conducted and/or evaluated the survey – indicated the results by marking either
pass or fail in Section VII of MDEQ galvanic cathodic protection form.
Indicated criteria that were applied to the evaluation by completion of Section VIII of the MDEQ galvanic
cathodic protection form.
Indicated action required as a result of the survey by marking either none, retest or repair & retest in
Section IX of MDEQ galvanic cathodic protection form.
Provided UST owner with any other type(s) of documentation that may be necessary in order to
adequately describe the cathodic protection evaluation including the operating status and any repairs or
recommendations and attached same to the MDEQ galvanic cathodic protection form.
APPENDIX H
CHECKLIST FOR IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM SURVEY
Identified UST owner, UST facility, CP tester, tester’s qualifications and reason for survey (complete
Sections I – V of MDEQ impressed current cathodic protection form).
Described UST system and type of cathodic protection (complete Section X of MDEQ impressed current cathodic
protection form).
Constructed site drawing depicting all pertinent components of the UST and cathodic protection systems at the
facility (complete Section XIV of MDEQ impressed current cathodic protection form).
Reviewed any previous cathodic protection design/repair/testing data that may be available.
Checked rectifier for proper operation and measured output voltage/amperage with portable multimeter and
indicated all other pertinent information (complete Section XI of MDEQ impressed current form).
Measured current output of all positive and negative circuits if the system was designed to allow for such
(complete Section XII of the MDEQ impressed current cathodic protection form).
Ensured soil access was available directly over each cathodically protected component at the facility.
Conducted continuity testing of all pertinent metallic components at the UST facility by the fixed remote – moving
ground and/or point-to-point method (complete Section XV of MDEQ impressed current form).
Recorded native structure-to-soil potentials in appropriate column in Section XVI of MDEQ impressed current
cathodic protection form if this data was available or the system had been down long enough for complete
depolarization to occur.
Obtained structure-to-soil potential on every cathodically protected structure with the reference electrode placed
in the soil directly over the structure under test with the protective current applied (on) and 0recorded voltages in
appropriate column in Section XVI of MDEQ impressed current cathodic protection form.
Obtained structure-to-soil potential on every cathodically protected structure without moving reference electrode
from placement utilized to obtain on potential with the protective current temporarily interrupted (instant off) and
recorded voltages in appropriate column in Section XVI of MDEQ impressed current form).
Conducted 100 mV polarization test if all protected structures did not meet the -850 instant off criterion. Obtaining
a 100 mV decay is only required on that component of the UST system that displays the lowest (most positive)
instant off potential in order to demonstrate the criterion has been satisfied.
Indicated location (by code or other means) of reference electrode placement on site drawing for each structure-
to-soil potential that was obtained.
Described any repairs and/or modifications that were made to the cathodic protection system (complete Section
XIII of MDEQ impressed current cathodic protection form).
Indicated whether or not each protected structure met the –850mV instant off criteria and/or the 100 mV
polarization criteria by indicating pass/fail in the appropriate column in Section XVI of the
MDEQ form.
If only qualified as a tester - indicated the results of the evaluation by marking either pass, fail or
inconclusive in Section VI of MDEQ impressed current cathodic protection form.
If only qualified as a tester - marked inconclusive if any of the conditions found in Section 7.2 of MDEQ cathodic
protection guidance document were applicable to survey.
If it was necessary for the tester to indicate inconclusive, a corrosion expert evaluated the data obtained by a
tester and/or conducted his own testing and completed Section VII of MDEQ impressed current form.
If a corrosion expert conducted evaluation – indicated the results by marking either pass or fail in Section VII of
MDEQ impressed current cathodic protection form.
Indicated criteria that were applied to the evaluation by completion of Section VIII of the MDEQ form.
Indicated action required as a result of the survey by marking either none, retest or repair & retest in Section IX of
MDEQ impressed current cathodic protection form.
Provided UST owner with any other type(s) of documentation that may be necessary in order to adequately
describe the cathodic protection evaluation including the operating status and any repairs or recommendations
and attached same to the MDEQ impressed current cathodic protection form.
APPENDIX I
APPENDIX J
TYPICAL POTENTIAL OF SELECTED METALS
The table below lists some common metals and their observed electrical potentials as measured with
respect to a copper/copper sulfate reference electrode.
METAL
VOLTAGE (mV)
Magnesium (commercially pure)
-1750
Magnesium (alloy found in typical cathodic protection anode)
-1600
Zinc (nearly 100% pure - as found in typical cathodic protection anode)
-1100
Aluminum (5% zinc alloy)
-1050
Aluminum (pure)
-800
Low Carbon Steel (new – clean & shiny)
-600 to -750
Low Carbon Steel (old – rusty)
-500 to -600
Stainless Steel (active - unpassivated)
-450 to -600
Cast Iron (not graphitized)
-500
Lead
-500
Low Carbon Steel in Concrete
-200
Brass, Bronze
-200
Stainless Steel (passivated)
50 to -250
Copper
0 to -200
High Silicone Cast Iron
-200
Carbon, Graphite
+300
Silver
+500
Platinum
+900
Gold
+1200
APPENDIX K
STATE OF MISSISSIPPI
GALVANIC CATHODIC
PROTECTION SYSTEM
EVALUATION
APPENDIX L
STATE OF MISSISSIPPI
IMPRESSED CURRENT CATHODIC
PROTECTION SYSTEM
EVALUATION
APPENDIX M
STATE OF MISSISSIPPI
IMPRESSED CURRENT
CATHODIC PROTECTION
SYSTEM
60 DAY RECORD OF OPERATION
STATE OF MISSISSIPPI
GALVANIC (SACRIFICIAL ANODE) CATHODIC PROTECTION SYSTEM EVALUATION
This form must be utilized to evaluate underground storage tank (UST) cathodic protection systems in the State of Mississippi.
Access to the soil directly over the cathodically protected structure that is being evaluated must be provided.
A site drawing depicting the UST cathodic protection system and all reference electrode placements must be completed.
I. UST OWNER
II. UST FACILITY
NAME:
NAME:
ID #
ADDRESS:
ADDRESS:
CITY:
STATE:
CITY:
COUNTY:
III. CP TESTER
IV. CP TESTER’S QUALIFICATIONS
TESTER’S NAME:
NACE INTERNATIONAL CERTIFICATION NUMBER:
COMPANY NAME:
MDEQ UST INSTALLER CERTIFICATION NUMBER:
ADDRESS:
OTHER (EXPLAIN):__________________________________________________________
CITY:
STATE:
__________________________________________________________________________
V. REASON SURVEY WAS CONDUCTED (mark only one)
Routine - 3 year Routine – within 6 months of installation 90-day re-survey after fail Re-survey after repair/modification
Date next cathodic protection survey must be conducted by _____________________ (required within 6 months of installation/repair & every 3 years thereafter).
VI. CATHODIC PROTECTION TESTER’S EVALUATION (mark only one)
All protected structures at this facility pass the cathodic protection survey and it is judged that adequate cathodic protection has
been provided to the UST system (indicate all criteria applicable by completion of Section VIII).
One or more protected structures at this facility fail the cathodic protection survey and it is judged that adequate cathodic protection has not been
tection has not been provided to the UST system (complete Section IX).
If the remote and the local do not both indicate the same test result on all protected structures (both pass or both fail), inconclusive
is indi inconclusive is indicated and the survey must be evaluated and/or conducted by a corrosion expert (complete Section VII).
CP TESTER’S SIGNATURE:
DATE CP SURVEY PERFORMED:
VII. CORROSION EXPERT’S EVALUATION (mark only one)
The survey must be conducted and/or evaluated by a corrosion expert when: a) an inconclusive is indicated for any protected structure since both the local and the remote structure-to-soil
potentials do not result in the same outcome (both pass or both fail); b) repairs to galvanized or uncoated steel piping are conducted or c) supplemental anodes are added to the tanks
and/or piping without following an accepted industry code.
All protected structures at this facility pass the cathodic protection survey and it is judged that adequate cathodic protection has
been provided to the UST system (indicate all criteria applicable by completion of Section VIII).
One or more protected structures at this facility fail the cathodic protection survey and it is judged that adequate cathodic
protection has not been provided to the UST system (indicate what action is necessary by completion of Section IX).
CORROSION EXPERT’S NAME:
COMPANY NAME:
NACE INTERNATIONAL CERTIFICATION:
NACE INTERNATIONAL CERTIFICATION NUMBER:
CORROSION EXPERT’S SIGNATURE:
DATE:
VIII. CRITERIA APPLICABLE TO EVALUATION (mark all that apply)
Structure-to-soil potential more negative than –850 mV with respect to a Cu/CuSO4 reference electrode with the protective current applied
current applied ( ( (This criterion is applicable to any galvanically protected structure).
Structure-to-soil potential more negative than –850 mV with respect to a Cu/CuSO4 reference electrode with protective current temporarily interrupted
interrupted (This criterion is applicable only to those galvanic systems where the anodes can be disconnected).
Structure tested exhibits at least 100 mV of cathodic polarization (This criterion is applicable to galvanic systems where the anodes can be temporarily disconnected.)
.
IX. ACTION REQUIRED AS A RESULT OF THIS EVALUATION (mark only one)
NONE Cathodic protection is adequate. No further action is necessary at this time. Test again by no later than (see Section V).
RETEST Cathodic protection may not be adequate. Retest during the next 90 days to determine if passing results can be achieved.
REPAIR & RETEST Cathodic protection is not adequate. Repair/modification is necessary as soon as practical but within the next 90 days.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
INCONCLUSIVE
PASS
FAIL
PASS
FAIL
100 mV POLARIZATION
850 OFF
850 ON
X. DESCRIPTION OF UST SYSTEM
TANK
PRODUCT
CAPACITY
TANKS
PIPING
FLEX CONNECTORS
XI. DESCRIPTION OF CATHODIC PROTECTION SYSTEM REPAIRS AND/OR MODIFICATION
Complete if any repairs or modifications to the cathodic protection system are made or are necessary. Certain repairs/modifications as explained in the text of the MDEQ
cathodic protection guidance document are required to be designed and/or evaluated by a corrosion expert (completion of Section VII required).
Supplemental anodes for a sti-P3® tank (attach corrosion expert’s design or documention industry standard was followed).
Supplemental anodes for metallic pipe (attach corrosion expert’s design or documention industry standard was followed).
Galvanically protected tanks/piping not electrically isolated (explain in “Remarks/Other” below).
Remarks/Other: ____________________________________________________________________________________________________________
_________________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________________
XII. UST FACILITY SITE DRAWING
Attach detailed drawing or use the space provided to draw a sketch of the UST and cathodic protection systems. Sufficient detail must be given in order to clearly indicate
where the reference electrode was placed for each structure-to-soil potential that is recorded on the survey forms. Any pertinent data must also be included. At a minimum you
should indicate the following: All tanks, piping and dispensers; All buildings and streets; All anodes and wires; Location of CP test stations; Each reference electrode
placement must be indicated by a code (1,2, T-1,) corresponding with the appropriate line number in Section XIV of this form.
AN EVALUATION OF THE CATHODIC PROTECTION SYSTEM IS NOT COMPLETE WITHOUT AN ACCEPTABLE SITE
DRAWING.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
XIII. GALVANIC (SACRIFICIAL ANODE) CATHODIC PROTECTION SYSTEM CONTINUITY SURVEY
This section may be utilized to conduct measurements of continuity on underground storage tank systems that are protected by cathodic protection systems.
When conducting a fixed cell - moving ground survey, the reference electrode must be placed in the soil at a remote location and left undisturbed.
Conduct point-to-point test between any two structures for which the fixed cell-moving ground survey is inconclusive or indicates possible continuity.
For galvanic systems, the structure that is to be protected must be isolated from any other metallic structure in order to pass the continuity survey.
FACILITY NAME:
NOTE: The survey is not complete unless all applicable parts of Sections I-XIV are also completed
DESCRIBE LOCATION OF “FIXED REMOTE” REFERENCE ELECTRODE PLACEMENT:
STRUCTURE “A” 1
STRUCTURE “B” 2
STRUCTURE “A” 3
FIXED REMOTE
VOLTAGE
STRUCTURE “B” 4
FIXED REMOTE
VOLTAGE
POINT-TO-POINT
5 VOLTAGE
DIFFERENCE
ISOLATED/ 6
CONTINUOUS/
INCONCLUSIVE
(example)
PREMIUM TANK BOTTOM
(example)
PREMIUM TANK FILL RISER
(example)
-921 mV
(example)
-915 mV
(example)
INCONCLUSIVE
(example)
PREMIUM TANK BOTTOM
(example)
PREMIUM TANK FILL RISER
(example)
17 mV
(example)
ISOLATED
COMMENTS:
1 Describe the cathodically protected structure that you are attempting to demonstrate is isolated from unprotected structures (e.g. prem. tank).
2 Describe the unprotected structure that you are attempting to demonstrate is isolated from the protected structure (e.g. premium tank fill riser).
3 Record the measured structure-to-soil potential of the cathodically protected structure {“A”} in millivolts (e.g. –921 mV).
4 Record the measured structure-to-soil potential of the unprotected structure {“B”} in millivolts (e.g. –915 mV).
5 Record the voltage observed between the protected and the unprotected structures when conducting point-to-point testing (e.g. 17 mV).
6 Document whether the test (fixed cell and/or point to point) indicated the protected structure was isolated, continuous or inconclusive.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
XIV. GALVANIC (SACRIFICIAL ANODE) CATHODIC PROTECTION SYSTEM SURVEY
This section may be utilized to conduct a survey of a galvanic cathodic protection system by obtaining structure-to-soil potential measurements.
The reference electrode must be placed in the soil directly over the tested structure (local) and 25-100 feet away from the structure (remote).
Both the local and the remote voltage must be –850 mV or more negative, in order for the structure to pass.
Inconclusive is indicated when both the local and the remote structure-to-soil potentials do not result in the same outcome (both pass or both fail).
FACILITY NAME:
NOTE: The survey is not complete unless all applicable parts of sections I – XIV are also completed
DESCRIBE LOCATION OF REMOTE REFERENCE ELECTRODE PLACEMENT:
LOCATION
1 CODE
STRUCTURE 2
CONTACT POINT 3
LOCAL REFERENCE CELL PLACEMENT
LOCAL
VOLTAGE5
REMOTE
VOLTAGE
PASS/FAIL/ 7
INCONCLUSIV
E
(example)
(example)
PLUS TANK
(example)
TANK BOTTOM
(example)
PLUS TANK STP MANWAY
(example)
-928
(example)
-810
(example)
INCONCLUSIVE
(example)
(example)
PLUS PIPING
(example)
DISPENSER 5/6
(example)
UNDER DISPENSER 5/6
(example)
-890
(example)
-885
(example)
PASS
COMMENTS:
1 Designate numerically or by code on the site drawing each “local” reference electrode placement (e.g. 1,2,3… T-1, T-2, P-1, P-2…etc.).
2 Describe the structure that is being tested (e.g. plus tank; premium piping; diesel submersible pump flex connector; etc.).
3 Describe where contact with the structure that is being tested is made (e.g. plus tank @ test lead; diesel piping @ dispenser 5/6; tank test lead; pp4, etc).
4 Describe the exact location where reference electrode is placed for each “local” measurement (e.g. soil @ plus tank STP; soil @ dispenser 5/6; etc.)
5 Record the structure-to-soil potential measured with the reference electrode placed “local” in millivolts (e.g. –865 mV, -920 mV, etc.).
6 Record the structure-to-soil potential measured with the reference electrode placed “remote” (copy voltage that was obtained during continuity survey).
7 Indicate whether the tested structure passed or failed the –850 mV “on” criterion based on your interpretation of the test data.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
STATE OF MISSISSIPPI
IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM EVALUATION
This form must be utilized to evaluate underground storage tank (UST) cathodic protection systems in the State of Mississippi.
Access to the soil directly over the cathodically protected structure that is being evaluated must be provided.
A site drawing depicting the UST cathodic protection system and all reference electrode placements must be completed.
I. UST OWNER
II. UST FACILITY
NAME:
NAME:
ID #
ADDRESS:
ADDRESS:
CITY:
STATE:
CITY:
COUNTY:
III. CP TESTER
IV. CP TESTER’S QUALIFICATIONS
TESTER’S NAME:
NACE INTERNATIONAL CERTIFICATION NUMBER:
COMPANY NAME:
MDEQ UST INSTALLER CERTIFICATION NUMBER:
ADDRESS:
OTHER
CITY:
STATE:
V. REASON SURVEY WAS CONDUCTED (mark only one)
Routine - 3 year Routine – within 6 months of installation 90-day re-survey after fail Re-survey after
Date next cathodic protection survey must be conducted
(required within 6 months of installation/repair & every 3 years thereafter).
VI. CATHODIC PROTECTION TESTER’S EVALUATION (mark only one)
All protected structures at this facility pass the cathodic protection survey and it is judged that adequate cathodic protection has
been provided to the UST system (indicate all criteria applicable by completion of Section VIII).
One or more protected structures at this facility fail the cathodic protection survey and it is judged that adequate cathodic
protection has not been provided to the UST system (complete Section IX).
The cathodic protection survey of an impressed current system must be evaluated by a corrosion expert because one or more of
the conditions listed in Section 7.1.5 of the MDEQ cathodic protection guidance document are applicable (complete Section VII).
CP TESTER’S SIGNATURE:
DATE CP SURVEY PERFORMED:
VII. CORROSION EXPERT’S EVALUATION (mark only one)
The survey must be conducted and/or evaluated by a corrosion expert when: a) supplemental anodes or other changes in the construction of the impressed current
system are made; b) stray current may be affecting buried metallic structures or c) an inconclusive result was indicated in Section VI.
All protected structures at this facility pass the cathodic protection survey and it is judged that adequate cathodic protection has
been provided to the UST system (indicate all criteria applicable by completion of Section VIII).
One or more protected structures at this facility fail the cathodic protection survey and it is judged that adequate cathodic
protection has not been provided to the UST system (indicate what action is necessary by completion of Section IX).
CORROSION EXPERT’S NAME:
COMPANY NAME:
NACE INTERNATIONAL CERTIFICATION:
NACE INTERNATIONAL CERTIFICATION NUMBER:
CORROSION EXPERT’S SIGNATURE:
DATE:
VIII. CRITERIA APPLICABLE TO EVALUATION (mark all that apply)
Structure-to-soil potential more negative than –850 mV with respect to a Cu/CuSO4 reference electrode with protective
current temporarily interrupted current temporarily interrupted (instant-off).
Structure(s) exhibit at least 100 m V of cathodic protection.
IX. ACTION REQUIRED AS A RESULT OF THIS EVALUATION (mark only one)
NONE Cathodic protection is adequate. No further action is necessary at this time. Test again by no later than (see Section V).
RETEST Cathodic protection may not be adequate. Retest during the next 90 days to determine if passing results can be achieved.
REPAIR & RETEST Cathodic protection is not adequate. Repair/modification is necessary as soon as practical but within the next 90 days.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
INCONCLUSIVE
PASS
FAIL
PASS
FAIL
850 OFF
100 mV POLARIZATION
X. DESCRIPTION OF UST SYSTEM
TANK
PRODUCT
CAPACITY
TANK MATERIAL
PIPING MATERIAL
FLEX
XI. IMPRESSED CURRENT RECTIFIER DATA (complete all applicable)
In order to conduct an effective evaluation of the cathodic protection system, a complete evaluation of rectifier operation is necessary.
RECTIFIER MANUFACTURER:
RATED DC
OUTPUT:
____________ VOLTS ____________ AMPS
RECTIFIER MODEL:
RECTIFIER SERIAL NUMBER:
RECTIFIER OUTPUT AS INITIALLY DESIGNED OR LASTLY RECOMMENDED (if available): __________ VOLTS __________ AMPS
EVENT
DATE
COARSE
FINE
VOLTS
AMPS
HOUR
METER
COMMENTS
“AS FOUND”
“AS LEFT”
XII. IMPRESSED CURRENT POSITIVE & NEGATIVE CIRCUIT MEASUREMENTS
Complete if the system is designed to allow such measurements (i.e. individual lead wires for each anode are installed and measurement shunts are present).
CIRCUIT
TOTAL
ANODE (+)
TANK (-)
XIII. DESCRIPTION OF CATHODIC PROTECTION SYSTEM REPAIRS AND/OR MODIFICATION
Complete if any repairs or modifications to the cathodic protection system are made OR are necessary. Certain repairs/modifications as explained in the text of
the MDEQ cathodic protection guidance document are required to be designed and/or evaluated by a corrosion expert (completion of Section VII required).
Additional anodes for an impressed current system (attach corrosion expert’s design).
Repairs or replacement of rectifer (explain in “Remarks/Other” below).
Anode header cables repaired and/or replaced(explain in “Remarks/Other” below).
Impressed current protected tanks/piping not electrically continuous (explain in “Remarks/Other” below).
Remarks/Other: _____________________________________________________________________________________________________
__________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________
XIV. UST FACILITY SITE DRAWING
Attach detailed drawing of the UST and cathodic protection systems. Sufficient detail must be given in order to clearly indicate where the reference electrode was placed for each structure-to-soil
potential that is recorded on the survey forms. Any pertinent data must also be included. At a minimum you should indicate the following: All tanks, piping and dispensers; All buildings and streets;
All anodes and wires; Location of CP test stations; Each reference electrode placement must be indicated by a code (1,2,3 R-1, R-2, R-3…etc.) corresponding with the appropriate line number in
Section XVI of this form.
AN EVALUATION OF THE CATHODIC PROTECTION SYSTEM IS NOT COMPLETE WITHOUT AN ACCEPTABLE SITE DRAWING.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
TAP SETTINGS
DC OUTPUT
XV. IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM CONTINUITY
This section may be utilized to conduct measurements of continuity on underground storage tank systems that are protected by cathodic protection systems.
When conducting a fixed cell - moving ground survey, the reference electrode must be placed in the soil at a remote location and left undisturbed.
Conduct point-to-point test between any two structures for which the fixed cell - moving ground survey is inconclusive or indicates possible isolation.
For impressed current systems, the protected structure must be continuous with all other protected structures in order to pass the continuity survey.
FACILITY NAME:
NOTE: The survey is not complete unless all applicable parts of sections I-XIV are also completed
DESCRIBE LOCATION OF “FIXED REMOTE” REFERENCE ELECTRODE PLACEMENT:
STRUCTURE “A” 1
STRUCTURE “B” 2
STRUCTURE “A”
3 FIXED REMOTE
INSTANT OFF
VOLTAGE
STRUCTURE “B”
4 FIXED REMOTE
INSTANT OFF
VOLTAGE
POINT-TO-
POINT5
VOLTAGE
DIFFERENCE
ISOLATED/ 6
CONTINUOUS/
INCONCLUSIVE
(example)
PLUS TANK BOTTOM
(example)
PLUS STEEL PRODUCT LINE @ STP
(example)
-915 mV
(example)
-908 mV
(example)
INCONCLUSIVE
(example)
PLUS TANK BOTTOM
(example)
PLUS STEEL PRODUCT LINE @ STP
(example)
1 mV
(example)
CONTINUOUS
1 Describe the protected structure {“A”} that you are attempting to demonstrate is continuous (e.g. plus tank bottom).
2 Describe the “other” protected structure {“B”} that you are attempting to demonstrate is continuous (e.g. plus steel product line @ STP).
3 Record the fixed remote instant off structure-to-soil potential of the protected structure {“A”} in millivolts (e.g. –915 mV).
4 Record the fixed remote instant off structure-to-soil potential of the “other” protected structure {“B”} in millivolts (e.g. –908 mV).
5 Record the voltage difference observed between structure “A” and structure “B” when conducting “point-to-point” testing (e.g. 1mV).
6 Document whether the test (fixed cell and/or point to point) indicated the protected structure was isolated, continuous or inconclusive.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
XVI. IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM SURVEY
This section may be utilized to conduct a survey of an impressed current cathodic protection system by obtaining structure-to-soil potential measurements.
The reference electrode must be placed in the soil directly above the structure that is being tested and as far away from any active anode as practical to obtain a valid
structure-to-soil potential (refer to the MDEQ cathodic protection evaluation guidance document for detailed discussion of electrode placement).
Both on and instant off potentials must be measured for each structure that is intended to be under cathodic protection.
The instant off potential must be -850 mV or more negative or the 100 mV polarization criterion must be satisfied in order to pass.
FACILITY NAME:
NOTE: This survey is not complete unless all applicable parts of sections I – XIV are also completed
LOCATION
1 CODE
STRUCTURE 2
CONTACT
POINT3
REFERENCE CELL PLACEMENT 4
ON 5
VOLTAGE
INSTANT
6 OFF
VOLTAGE
ENDING7
VOLTAGE
VOLTAGE
8 CHANGE
PASS/
FAIL 9
(example)
(example)
PLUS TANK
(example)
TANK BOTTOM
(example)
SOIL @ REG. TANK STP MANWAY
(example)
-1070mV
(example)
-875 mV
(example)
PASS
(example)
(example)
DIESEL PIPE
(example)
DISPENSER 7/8
(example)
SOIL @ DIESEL TANK STP MANWAY
(example)
-810 mV
(example)
-680 mV
(example)
-575 mV
(example)
105 mV
(example)
PASS
COMMENTS:
1 Designate numerically or by code on the site drawing each local reference electrode placement (e.g. 1,2,3… T-1, T-2, P-1, P-2…etc.).
2 Describe the structure that is being tested (e.g. plus tank; diesel piping; flex connector, etc.).
3 Describe where the structure being tested is contacted by the test lead (e.g. plus tank bottom; diesel piping @ dispenser 7/8; etc.).
4 Describe the exact location where the reference electrode is placed for each measurement (e.g. soil @ regular tank STP manway; soil @ dispenser 2, etc.)
5 {Applies to all tests} Record the structure-to-soil potential (voltage) observed with the current applied (e.g. –1070 mV).
6 {Applies to all tests} Record the structure to soil potential (voltage) observed when the current is interrupted (e.g. 680 mV).
7 {Applies to 100 mV polarization test only} Record the voltage observed at the end of the test period (e.g. 575 mV).
8 {Applies to 100 mV polarization test only} Subtract the final voltage from the instant off voltage (e.g. 680 mV – 575 mV = 105 mV).
9 Indicate if the tested structure passed or failed one of the two acceptable criteria (850 instant off or 100 mV polarization) based on your interpretation of data.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
100 mV POLARIZATION
STATE OF MISSISSIPPI
IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM
60-DAY RECORD OF RECTIFER OPERATION
This form may be utilized to document that the cathodic protection system rectifier is checked for operation at least once every 60 days.
Checked for operation is taken to mean that it was confirmed the rectifier was receiving power and is “turned-on”.
If your rectifier is so equipped, you should also record the output voltage, amperage and the number of hours indicated on the meter.
Any significant variance should be reported to your corrosion professional so that any repairs and/or adjustments necessary can be made.
UST OWNER
UST FACILITY
NAME:
NAME:
ID #
ADDRESS:
ADDRESS:
CITY:
STATE:
CITY:
COUNTY:
IMPRESSED CURRENT RECTIFIER DATA
Rectifier Manufacturer:
Rated DC Output: ____________ VOLTS ___________AMPS
Rectifier Model:
Rectifier Serial Number:
What is the ‘as designed’ or lastly recommended rectifier output? ____________ VOLTS ___________AMPS
60-DAY LOG OF RECTIFIER OPERATION
DATE
INSPECTED
RECTIFIER
TURNED ON?
COARSE
FINE
VOLTS
AMPS
HOUR
METER
INSPECTOR
INITIALS
COMMENTS
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
TAP SETTINGS
DC OUTPUT
APPENDIX 280.2
STATE OF MISSISSIPPI
SELF CERTIFICATION OF UST SYSTEM RETURN TO DELIVERY ELIGIBILITY
UST OWNER
UST FACILITY
Owner Name
Facility Name
Owner Address
Facility Physical Street Address
City
State
City
State
MS
Phone
County
Tank Owner Contact Person
MDEQ UST Facility I.D. Number
I CERTIFY UNDER PENALTY OF LAW THAT:
1.
The underground storage tank facility referenced above has completed the repairs/modifications necessary to establish
compliance and is eligible to receive product deliveries.
2.
I have personally examined and am familiar with the information contained in this submittal and any accompanying
documents. This information, to the best of my knowledge, is true, accurate and complete.
3.
I am aware that there are significant penalties for knowingly submitting false information.
UST OWNER
MDEQ CERTIFIED UST INSTALLER
Printed Name of Owner or Authorized Representative
Printed Name of Certified UST Installer
Owner’s Signature
Installer’s Signature
Date
Date
MDEQ Certification Number
This form must be signed by both the UST owner and a MDEQ certified UST installer.
MDEQ reserves the right to make the final determination of whether or not the UST facility has satisfactorily
returned to compliance.
PRODUCED BY THE MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY, OFFICE OF POLLUTION CONTROL, UST BRANCH
PO BOX 2261, JACKSON, MS 39225 PHONE (601) 961-5171 FACSIMILE (601) 961-5093 www.deq.state.ms.us 7/08
APPENDIX 280.3 [Reserved]
APPENDIX 280.4 - GUIDELINES FOR THE
PERMANENT CLOSURE OF PETROLEUM
UNDERGROUND STORAGE TANK SYSTEMS
CONTENTS
SECTION 1 -GENERAL
1.1 Introduction .................................................................................................
SECTION 2 - PAPERWORK AND REPORTING REQUIREMENTS
2.1 Tank Registration ........................................................................................
2.2 Notice of Intent to Permanently Close UST System(s) .................................
2.3 Underground Storage Tank System Closure Report ...................................
2.4 Sample Chain-of-Custody .............................................................................
SECTION 3 - SAMPLING PROCEDURES
3.1 General Sampling Requirements .................................................................
3.2 Soil Versus Groundwater Samples ..............................................................
3.3 Soil Sample Collection Procedures ..............................................................
3.4 Groundwater Sample Collection Procedures .............................................
SECTION 4 - SAMPLING LOCATIONS FOR TANKS
4.1 General Requirements ................................................................................
4.2 Removal of a Single Tank ...........................................................................
4.3 Removal of Two or More Tanks Within a Common Excavation ..............
4.4 Tank Closure in Place or Change in Service ..............................................
SECTION 5 - SAMPLING LOCATIONS FOR PIPING
5.1 General Requirements................................................................................
5.2 Dispenser Islands ........................................................................................
5.3 Piping Trenches .........................................................................................
SECTION 6 - BACKFILL SAMPLING
6.1 General Requirements ..............................................................................
6.2 Backfill Handling Options .........................................................................
SECTION 7 - DEVIATIONS FROM MINIMUM SAMPLING
REQUIREMENTS
7.1 Hazards or Obstructions ...........................................................................
7.2 Waiver of Sampling Requirements ............................................................
SECTION 8 - SAMPLE ANALYSIS
8.1 Tanks ..........................................................................................................
8.2 Dispenser Islands & Piping ........................................................................
APPENDICES
Appendix A - "The Closure Cycle ....................................................................
Appendix B - Permitted Solid Waste Landfills ................................................
Appendix C - "Notice of Intent to Permanently Close UST System(s)" .........
Appendix D - "UST System Closure Report" ..................................................
Appendix E - Chain-of-Custody Record ...........................................................
Appendix F - Industry Codes and Standards ...................................................
Appendix G - Boring Log for UST System Closure in Place...........................
Appendix H - Definitions ................................................................................
SECTION 1 - GENERAL
1.1 Introduction
The purpose of this document is to provide guidance that explains what the policies
of the Underground Storage Tank (UST) Branch are regarding the permanent
closure of petroleum UST systems. If you are permanently closing a UST system
that has contained a regulated substance other than petroleum, you must contact the
UST Branch in order to determine what sampling requirements must be met.
Any tank that was in use on or after December 22,1988, must be permanently
closed if taken out of use for more than a 12-month period unless the tank meets the
corrosion protection requirements. If a tank was taken out of use prior to December
22, 1988, and was closed in accordance with acceptable industry standards at that
time, it is not required to be permanently closed in accordance with the present UST
rules and regulations. Generally, the acceptable industry practice prior to December
22, 1988, was to simply empty the UST of product and in some instances, fill the
tank with water. However, if a release is discovered at a tank that was closed prior
to December 22, 1988, the release must be reported to the UST Branch and
remediated just as if the release had occurred today.
The UST regulations require that when a UST is permanently closed, the site must be
sampled for the presence of a release where contamination is most likely to be
present. Therefore, the sampling requirements in this guide are only the minimum
necessary and are not intended to substitute for the specific conditions that may
apply to an individual site. Additional sampling may be justified whenever obvious
areas of contamination are found.
No closure report will be accepted as complete without the minimum sampling data
that is described herein. However, an allowance will be made where certain
circumstances prohibit the collection of the minimum sampling points necessary
such as when a tank is to be closed in place but one end of the tank is underneath a
building. If it is necessary to deviate from the minimum sampling procedure, the
tank owner must submit to the UST Branch an alternative sampling plan thirty (30)
days prior to the closure to gain approval.
A Mississippi Department of Environmental Quality (MDEQ) certified contractor
must supervise the permanent closure of any UST system that was in use on or after
December 22, 1988. The certified contractor must ensure that all UST regulations
and industry codes/practices (see Appendix F) relating to the closure are followed.
To obtain a current listing of MDEQ certified contractors, contact the UST Branch
at(601) 961-5171.
The state Fire Marshall's office and/or local fire department may need to be
contacted prior to performing UST closure. You may also be required to obtain city
or local demolition permits.
All underground utilities must be identified and clearly marked prior to any
excavation or drilling. Contact Mississippi One-Call System, Inc. at 1-601-362-4374
in order to have all underground utilities marked.
Certain terms used in this document are defined in Appendix H for your reference.
SECTION 2 - PAPERWORK AND REPORTING REQUIREMENTS
2.1 Tank Registration
Prior to performing a UST closure, the owner is to verify that the USTs are properly
registered with the UST Branch. Any UST system that was in use on or after
January 1,1974, must be registered. If it is determined that a UST system is not
registered, the permanent closure will not be approved until the tanks are registered
and any applicable annual tank regulatory fees are paid in full. Tanks may be
registered by submittal of a "Notification for Underground Storage Tanks" form
which may be obtained by contacting the UST Branch or may be downloaded from
the Internet at www.deq.state.ms.us.
2.2.Notice of Intent to Permanently Close Underground Storage Tank
System (s)
The owner of the UST system or his representative must submit the "Notice of
Intent to Permanently Close Underground Storage Tank System(s)" form (Appendix
C) at least 30 days prior to the closure. This form becomes invalid if the closure is
not initiated within 120 days after submission. Any form submitted that does not
have the owner's signature and the name of the certified contractor is not considered
to be valid. Note that an owner may be subject to penalty if a Notice of Intent to
Permanently Close UST System(s)" form is not filed with the UST Branch prior to
performing a tank closure.
2.3 Underground Storage Tank System Closure Report
The owner of the UST system or his representative must submit the "Underground
Storage Tank System Closure Report" form (Appendix D) and all supporting
documentation within 60 days of completing the UST closure. The form must be
signed by the owner and the certified contractor to be valid. Supporting
documentation that must be included with the submittal of the UST Closure Report
form includes; a) copies of all analytical results of any and all samples; b) valid
sample chain-of-custody; and c) site drawing. In addition, if the closure involves the
disposal of contaminated soils and/or groundwater, a copy of the waste manifests
must be included in the submittal. Failure to submit all of the documentation
necessary to complete the closure will result in the return of the UST Closure Report
form to the tank owner.
The site drawing must contain the following:
general site layout showing tank locations and the
substance(s) stored
dispenser locations
depth to groundwater (if encountered)
dimensions of the excavation
sample locations (sample identification on the drawing
must match the labeling on each of the sample
containers)
depth at which each sample was collected.
2.4 Sample Chain-of-Custody
A chain-of-custody record (Appendix E) shall accompany the sample from the time
of sample collection to delivery to the lab. The possession or custody of samples
must be traceable from the time they are collected until the time the sample is
submitted to the laboratory for analysis.
If chain-of-custody procedures are not followed, the integrity of the samples is
compromised and the analysis is invalidated. A chain-of-custody record must be
completed for all samples that will be analyzed by the laboratory. This record must
be completed in the field at the time of sampling. Correct chain-of-custody must
continue when the samples are transferred to the laboratory or to the person
responsible for the delivery of the samples to the laboratory. Upon transfer of the
samples, each person handling the samples must sign, date, and note the time each
person received the samples.
Completed chain-of-custody records must be submitted for all samples and included
with the UST System Closure Report. A sample chain-of-custody form can be found
at Appendix E or may be obtained from the laboratory.
SECTION 3 - SAMPLING PROCEDURES
3.1 General Sampling Requirements
Soil and/or groundwater samples must be collected to determine if a release has
occurred. The importance of good sampling procedures is critical to the assessment
of a site at a UST closure. Since gasoline and some other petroleum products consist
largely of volatile organic compounds, special care in collecting samples is required.
Special precautions must be taken to be certain that samples collected from each site
are representative of the soil and/or groundwater at that location and that the sample
is neither altered nor contaminated by the sampling and handling procedure.
When collecting samples for Benzene, Toluene, Ethylbenzene and Xylenes (BTEX)
analysis, new disposable latex or nitrile gloves must be worn at each sample
collection location. When collecting samples for Polynuclear Aromatic
Hydrocarbons (PAH) analysis, new disposable vinyl or nitrile gloves must be worn at
each sample collection location. Latex is not a suitable glove material when
collecting samples for PAH analysis since PAH's have an affinity for latex.
The minimum number of sample containers (i.e. aliquots) that are stated in this
document are only intended to be guidance. Always contact your laboratory to
determine the sample size and aliquots that are required for a particular laboratory.
All samples must be placed in proper containers immediately upon collection,
properly packaged and labeled with the following minimum information:
1. facility name
2.
sample location (e.g. NW corner of tank bed, Sample #1, etc.)
3.
date and time samples were collected
4.
depth samples were collected
5.
person collecting samples
6.
analytical test(s) required
All samples must be placed on ice immediately after collection and shipped to the
laboratory within 24 hours of collection.
3.2 Soil Versus Groundwater Samples
Soil samples must be collected whenever evidence of soil contamination exists.
However, if water is encountered, pump it out in accordance with all regulatory
requirements and determine if the water in the tank excavation or borehole returns
within 24 hours. If the water returns, assume that the water is true groundwater. If
groundwater is present, water sample(s) must be collected. If groundwater is
sampled, no soil sampling is required unless soil contamination is evident. If soil
contamination is evident at either the tank excavation or the piping trench/dispenser
island, soil samples must be collected in accordance with Sections 5-7 of this
document in addition to any water samples.
3.3 Soil Sample Collection Procedures
3.3.1 Collecting Soil Samples for Gasoline (BTEX) Analysis
For BTEX analysis, collect at least one 4-oz sample from each sampling point. The
sampling procedure is as follows:
1.
Use a stainless steel spoon, spatula or some other appropriate sampling
device. NOTE: Sampling device must be decontaminated between each
sampling location.
2.
Soil samples should be tightly packed into the sample container using the
stainless steel spoon or appropriate sampling device.
3.
Completely fill sample container (4-oz widemouth amber glass container
with a Teflon liner) so that no headspace is present.
4.
Immediately store samples on ice and ship to the laboratory within 24 hours
of collection.
3.3.2 Collecting Soil Samples for Diesel, Oil, Etc. (PAH) Analysis
For PAH analysis, collect at least one 8-oz sample from each sampling point. The
sampling procedure is as follows:
1. Use a stainless steel spoon, spatula or some other appropriate sampling
device. NOTE: Sampling device must be decontaminated between each
sampling location.
2.
Soil samples should be tightly packed into the sample container using the
stainless steel spoon or appropriate sampling device.
3.
Completely fill sample container (8-oz widemouth amber glass container
with a Teflon liner) so that no headspace is present.
4.
Immediately store samples on ice and ship to the laboratory within 24 hours
of col lection.
3.4 Groundwater Sample Collection Procedures
3.4.1.Collecting Groundwater Samples for Gasoline (BTEX) Analysis
For BTEX groundwater analysis, collect at least three (3) 40-ml samples from each
sampling point.
1.
Sampling containers should be pre-labeled before any sample collection
begins.
2.
Decontaminate bailer and use clean new string/line.
NOTE: In general, use a disposable bailer and not one that must be
decontaminated between borings or wells in order to lessen the chance of
cross-contamination.
3.
Slowly lower the bailer into the water. Do not allow the bailer to free-fall.
4.
Allow the bailer to go into the water as far as possible without touching the
bottom of the boring and/or tank hole.
5.
Remove the bailer from the water before it is completely immersed under the water.
6.
Collect three aliquots:
a. transfer the sample from the bailer to amber 40-ml glass vials with
Teflon-lined septum cap, leaving no head space;
b. each sample should be carefully poured down the inside of the vial to
minimize turbulence;
c. verify no headspace by inverting the vial and tapping it gently to check
for trapped air bubbles. If any are present, a new sample must be
collected;
d. as a rule of thumb, it is best to gently pour the last few drops into the vial
so that surface tension holds the water in a "convex meniscus". The cap
is then placed on the vial and some overflow is lost, but air space in the
bottle is eliminated;
e. Immediately store samples on ice and ship to the laboratory within 24
hours of collection.
3.4.2.Collecting Groundwater Samples for Diesel, Oil, Etc. (PAH) Analysis
For PAH analysis collect one water sample (1 liter) from each sampling point.
1.
Sampling containers should be pre-labeled before any sample collection
begins.
2.
Transfer the sample from the bailer to a one liter widemouth glass sampling
container with a Teflon liner. Completely fill container to the top.
3. Immediately store the samples on ice and ship to the laboratory within 24
hours of collection.
BTEX and PAH Sample Handling Requirements for Soil/Groundwater Samples
Parameter
Media
Container
BTEX (Gasoline)
Soil
One 4-oz (120-ml) amber glass
with Teflon liner
PAH (Diesel, Oil, etc.)
Soil
One 8-oz (250-ml) amber
widemouth glass with Teflon
liner
BTEX (Gasoline)
Water
Three 40-ml amber
vials with septum caps
PAH (Diesel, Oil, etc.)
Water
One 1 liter widemouth glass
with Teflon liner
SECTION 4 - SAMPLING LOCATIONS FOR TANKS
4.1 General Requirements
The goal of sampling a tank excavation at closure is to represent the contamination
which may exist in a manner that is as accurate as possible while at the same time
minimizing the number of samples that are necessary to achieve the stated purpose.
Although the sampling locations described in this document are the minimum
necessary, they are not intended to substitute for the conditions which may exist at a
particular location. Therefore, a certain amount of professional judgement is
necessary in order to evaluate and properly assess the site conditions at a tank
closure.
When conducting sampling at a tank removal, all backfill materials must be removed
from the excavation prior to sampling. Whether sampling the sidewalls or the floor
of an excavation, all samples must be collected from a depth of at least one foot into
the native soil. Soil samples shall be collected immediately after the removal of all
backfill material. When closing tanks in place, the soil borings must be conducted in
the native soil immediately surrounding the tank bed excavation. Soil samples shall
be collected immediately after completion of the soil boring.
No compositing of samples (including sampling of the backfill) is allowed and each
sample that is collected must be analyzed separately.
If "true" groundwater (refer to Section 3.2) is encountered during excavation
activities, a groundwater sample must be collected from the excavation. No soil
sampling is required if a groundwater sample is collected unless soil contamination
is evident. Any soils that appear to be contaminated must be sampled in addition to
sampling of the groundwater. Follow the soil sampling requirements as described in
Sections 5-7 of this document when soil sampling is necessary.
4.2 Removal of a Single Tank
Prior to beginning any sampling activity, all backfill materials must be removed
from the excavation. Sampling of the tank excavation may occur from the floor of
the excavation only or from both the sidewalls and the floor, depending on the site
conditions. A discussion of where to sample the excavation and the minimum
number of samples that are necessary to satisfy the requirements of the UST Branch
follows:
4.2.1 Removal of a Single Tank - No Sidewall Contamination Apparent
If no contamination is apparent in the sidewalls, only floor sampling is required.
Two samples must be collected from the floor of the excavation at a depth of one
foot into the native soil. The samples must be collected from the areas of the floor
that appear to be the most contaminated. However, you should also take into
consideration the entire area of the excavation so that both of the floor samples are
not collected from the same general area. If no area of the floor appears to be
obviously contaminated, or the floor appears to be uniformly contaminated, the
samples must be collected from each end of the excavation as shown in Figure 1.
4.2.2 Removal of a Single Tank - Sidewall Contamination Apparent
If any of the sidewalls appear to be contaminated, sidewall samples must be
collected. As shown in Figure 2 below, a minimum of three samples are required to
assess the excavation when the sidewalls are contaminated. Two samples must be
collected from the sidewalls and one from the floor of the excavation.
The first sidewall sample must be collected from the sidewall of the excavation that
appears to be the most contaminated. The second sample must be collected from one
of the three remaining sidewalls that appears to have the greatest remaining
contamination. If no other sidewall appears to be contaminated, the second sample
must be collected from the wall opposite of the sidewall which appears to be the
most contaminated. The third sample to be collected must come from the floor of
the excavation. The floor sample must be collected from the area of the floor that
appears to be the most contaminated. If no area of the floor appears contaminated or
if it appears uniformly contaminated the sample must be collected from the center of
the excavation.
4.3 Removal of Two or More Tanks Within a Common Excavation
Prior to beginning any sampling activities, all backfill materials must be removed
from the tank excavation. As will be discussed, sampling of the tank excavation may
occur from the floor of the excavation only or from both the sidewalls and the floor,
depending on the site conditions.
4.3.1 Removal of Two or More Tanks - No Sidewall Contamination Apparent
If no contamination is apparent in the sidewalls, only floor sampling is required.
When the excavation is 50 feet or less in all dimensions, four samples must be
collected from the floor of the excavation at a depth of one foot into the native soil.
The samples must be collected from the areas of the floor that appear to be the most
contaminated. However, you should also take into consideration the entire area of
the excavation so that no two of the samples are collected from the same general
area. If no area of the floor appears to be obviously contaminated, or the floor
appears to be uniformly contaminated, the samples must be collected from each
corner of the excavation as shown in Figure 3.
However, if the excavation is greater than 50 feet in any dimension, additional
samples must be collected along each dimension of the excavation that is greater
than 50 feet in length. The additional sample must be collected from the center of
that dimension of the excavation as shown in Figure 4. Soil sampling must also be
conducted in such a manner that no more than 50 feet exists between any two
sampling points as measured along each dimension (side) of the excavation.
4.3.2 Removal of Two of More Tanks - Sidewall Contamination Apparent
If any of the sidewalls appear to be contaminated, all of the sidewalls must be
sampled. As shown in Figure 5 below, a minimum of five samples are required to
assess the excavation when the sidewalls are contaminated. One sample must be
collected from each of the four sidewalls and one from the floor of the excavation.
The sidewall samples must be collected from the area of each sidewall that appears to
be the most contaminated. If a wall appears to be clean, the sample for that
uncontaminated wall must be collected from the same depth where the highest level
of contamination appears in the most contaminated wall of the excavation.
The fifth sample must come from the floor of the excavation. The floor sample must
be collected from the area of the floor that appears to be the most contaminated. If
no area of the floor appears contaminated or if it appears uniformly contaminated,
the sample must be collected from the center of the excavation.
Soil sampling must also be conducted in such a manner that no more than 50 feet
exists between any two sampling locations along each wall of the excavation.
4.4 Tank Closure in Place or Change in Service
Since potentially contaminated soils cannot be seen during closure in place activities
as when removing tank systems, the sampling requirements for closure in place are
more conservative. You must follow the exact guidelines given in this document
unless special circumstances do not allow such. Any alternative sampling plan must
be submitted to the UST Branch for approval at the same time the "Notice of Intent
to Permanently Close UST System(s)" form is submitted.
If "true" groundwater (refer to Section 3.2) is encountered during soil boring
activities, groundwater samples must be collected from each boring that contains
groundwater and each sample must be analyzed separately. Soil sampling must be
conducted from those borings that do not have groundwater. In addition, regardless
of whatever soil and/or groundwater sampling that is conducted, one soil sample
must be collected from the boring that exhibited the highest level of petroleum
contamination during the field screening process (see Section 4.4.4).
Tanks closed in place must be cleaned and filled with an inert solid material such as
sand, concrete, virgin drilling mud or a "foam" material approved for such purposes.
If virgin drilling mud is used, the mixture must consist of 25-30 pounds of bentonite
per 42 gallon barrel of water and the pH must be between 6.5 and 8. All tank
sludges removed during the cleaning process must be properly disposed of in
accordance with all regulatory requirements.
4.4.1 Change in Service
A change in service is when the contents of the tank are changed from a regulated
substance (e.g. gasoline) to an unregulated substance (e.g. water). In order to
accomplish a change in service, the same notification and sampling requirements for
the permanent closure of a UST system must be followed. Sampling must be
conducted in the same manner as tank closure in place and the interior of the tank
properly cleaned. In addition, you must notify the UST Branch of the change in
service by submittal of a "Notification for Underground Storage Tanks" form which
indicates what unregulated substance is presently stored in the tank.
4.4.2 Closure in Place of a Single Tank Less Than or Equal to 25 Feet in
Length
Four borings are required when closing in place a single tank less than or equal to
25 feet in length. One borehole at each corner the tank bed must be advanced to a
depth of at least one foot below the bottom of the tank and into the native soil as
shown in Figure 6. In order to determine the appropriate sampling depth and number
of samples to collect, conduct field screening of the soil column following the
guidance Section 4.4.4.
4.4.3 Closure in Place of Two or More Tanks Within a Common Tank Bed
For closure in place of two or more tanks within a common tank bed or a single tank
that is greater than 25 feet in length, soil borings must be conducted at intervals of
every 25 feet along the perimeter of the tank bed as shown in Figure 7. In order to
determine the appropriate sampling depth and number of samples to collect, conduct
field screening of the soil column following the guidance in Section 4.4.4.
4.4.4 Field Screening of Soils
In order to properly evaluate the appropriate depths to collect soil samples, conduct
field screening in two foot intervals of the soil column in each boring. Field
screening involves placing the soil in a container (normally a zipper-type plastic bag)
and evaluating the headspace with a suitable hydrocarbon meter.
Because soils must be relatively undisturbed to obtain accurate field screening
results, any boring that is conducted during sample collection/screening must be
accomplished in a manner that will produce a "core" of the soil column. Cuttings
produced from rotary drilling equipment are not acceptable for either field screening
or sample collection.
In order for the field screening to be evaluated by UST staff, a boring log must be
submitted along with the analytical results of sampling. The boring log must show
the type of soil encountered throughout the length of the boring. The boring log
must also show hydrocarbon vapor levels in parts per million as determined by the
field screening process for every two feet of the boring. Please refer to Appendix G
for an example of an acceptable boring log.
Soil samples must be conducted at the depth at which the highest levels of
hydrocarbon vapors were detected during the field screening process. If no
significant variations are found during field screening, samples must be collected
from a depth of at least one foot below the bottom of the tanks into the native soil. If
the field screening process reveals that all samples should be collected at less than
maximum depths, at least one additional sample must be collected from the borehole
that had the highest level of vapors found during the field screening process. This
additional sample must be collected from a depth of one foot below the bottom of
the tanks and into the native soil.
SECTION 5 - SAMPLING LOCATIONS FOR DISPENSER ISLANDS & PIPING 5.1
General Requirements
When performing a UST system closure, all piping must be removed from the
ground or properly closed in place. However, if new underground tanks are installed
to replace the tanks being closed, the existing piping may be utilized provided it is
constructed of non-corrodible materials or coated and cathodically protected steel. If
aboveground tanks are being installed, the existing piping may be utilized if it meets
the corrosion protection requirements and all soil/groundwater sampling required for
a piping closure in place is accomplished.
When closing piping in place, the goal is to render the piping unusable. Therefore,
provided the piping is no longer usable, filling of all voids in the piping is not
necessary. Pump a concrete slurry or other suitable inert solid material in the piping as
full as practical and cap each end of the piping.
Below are several procedure examples to follow when you are only replacing
piping or abandoning a dispenser island.
I am only abandoning an island - the facility will remain
operating as a UST facility. In this case, you must submit
the "Notice of Intent to Permanently Close a UST System"
and indicate on the form that only piping is being closed.
The section of piping that supplied the abandoned dispenser
island must also be closed in accordance with the
requirements of this document.
I am only replacing the piping - the facility will remain
operating as a UST facility and all of the new piping will
utilize the existing trenches/dispenser islands. In this case,
you must submit the "Notice of Intent to Permanently Close
a UST System" and indicate on the form that only piping is
being removed. All dispenser
islands/piping trenches must be closed in accordance with
the requirements of this document.
I am only replacing the tanks - the existing piping will
be utilized. In this case, you must submit the "Notice of
Intent to Permanently Close a UST System" and indicate on
the form that only tanks are being closed. The tanks must be
closed in accordance with the requirements of this
document.
I am only repairing the piping (please refer to Appendix
H for the definition of "repair"). Repairs of piping are not
subject to any of the UST closure requirements. However,
if you discover contaminated soils and/or groundwater while
conducting the repairs you must collect the appropriate soil
and/or groundwater samples for laboratory analysis.
5.2 Dispenser Islands
Sampling is required whenever a dispenser island is taken out of service or the
piping associated with the island is closed or replaced. However, small changes to
the piping system such as installation of new flex connectors or pipe nipples in order
to set new dispensers are not subject to the sampling requirements. An island is
considered to be any dispenser or series of dispensers that are oriented in a straight
line. Therefore, several different dispense arrangements may exist that could be
considered as one island. You should use your professional judgement to determine
the most appropriate sampling scheme.
If the dispensers are located directly above the tanks and the tanks are also being
permanently closed, no discreet dispenser island samples are necessary provided all
of the dispensers are located within the perimeter of the tank bed.
5.2.1 Removal of Dispenser Islands - No Sidewall Contamination Apparent
Prior to beginning any sampling activity, all backfill materials must be removed
from the excavation. If no contamination of the sidewalls is apparent, one soil
sample must be collected from the floor of the excavation. The sample must be
collected at a depth of one foot below the piping trench and into the native soil. The
sample must be collected from the area of the floor that appears to be the most
contaminated. If no area of the floor appears to be contaminated, the sample must be
collected from the center of the excavation when the dispenser island is less than or
equal to 50 feet in length as shown if Figure 8.
Two soil samples must be taken below each dispenser island if the island is more
than 50 feet in length. The samples must be collected from beneath the piping trench
at least one foot into the native soil. The samples must be collected from the areas of
the floor that appears to be contaminated although no more than 50 feet may exist
between any two sample locations. If no area of the floor appears contaminated, the
sample locations must be spaced equally along the length of the island and such that
no more than 50 feet exists between any two sampling locations as shown in Figure
8.
5.2.2 Removal of Dispenser Islands - Sidewall Contamination Apparent
If any of the sidewalls of the excavation appear to be contaminated, the sidewalls
must be sampled. At least two samples are required for dispenser islands less than 50
feet in length when sidewall sampling is necessary. One sample must be collected
from the area of the sidewall that appears to be the most contaminated. The second
sample must be collected from the floor of the excavation where the most
contamination appears to be present. The second sample must be collected from the
floor of the piping trench and at least one foot into the native soil. If no area of the
floor appears contaminated or it appears uniformly contaminated, the sample must
be collected as shown in Figure 8.
If the dispenser island is greater than 50 feet in length and sidewall sampling is
necessary, at least three samples are required. One of the samples must be collected
from the area of the sidewall that appears to be the most contaminated. The other
two samples must be collected from the floor of the excavation where the most
contamination appears to be present. However, you should also take into
consideration the entire area of the excavation so that both of the floor samples are
not collected from the same general area. If no area of the floor appears
contaminated or if it appears uniformly contaminated, collected floor samples as
shown in Figure 8.
5.2.3 Dispenser Island Closure in Place
Since potentially contaminated soils cannot be seen during closure in place activities
as when excavating, the sampling requirements for closure in place are more
conservative. You must follow the exact guidelines given in this document unless
special circumstances do not allow such. Any alternative sampling plan must be
submitted to the UST Branch for approval at the same time the "Notice of Intent to
Permanently Close UST System(s)" form is submitted.
Soil borings must be conducted at each end of the dispenser island and along the
length of the island such that no more than 25 feet exists between any two borings as
shown in Figure 9. The borings must extend to a depth of at least one foot below the
bottom of the piping trench and into the native soil. Samples must be collected from
each boring following the field screening practices as described in Section 4.4.4.
If "true" groundwater (refer to Section 3.2) is encountered during soil boring
activities, groundwater samples must be collected from each boring that contains
groundwater and each sample must be analyzed separately. Soil sampling must be
conducted from those borings that do not have groundwater. In addition, regardless
of whatever soil and/or groundwater sampling that is conducted, one soil sample
must be collected from the boring that exhibited the highest level of petroleum
contamination during the field screening process.
5.3 Piping Trenches
Sampling is required whenever a piping trench is taken out of service or piping is
replaced. However, repairs (see definition in Appendix H) or small changes to the
piping system such as installation of new flex connectors or unions are not subject to
the sampling requirements.
When both the tanks and piping are being removed and 50 feet or less of piping
trench exists between the dispenser island sampling point and the nearest tank
excavation sampling point, no additional sampling is required along the piping
trench unless soil contamination along the piping trench is evident as shown in
Figure 10.
5.3.1 Removal of Piping - No Sidewall Contamination Apparent
Prior to beginning any sampling activity, all backfill materials must be removed
from the piping trench excavation. If no contamination of the sidewalls is apparent,
soil samples must be collected from the floor of the excavation. The samples must
be collected from the floor of the piping trench at least one foot into the native soil.
The samples must be collected from the areas of the floor that appears to be the
most contaminated although no more than 50 feet may exist between any two
sampling locations. If no area of the floor appears contaminated or if it is uniformly
contaminated, the samples must be collected along the length of the piping trench
such that no more than 50 feet exists between any two sampling locations as shown
in Figure 11.
5.3.2 Removal of Piping - Sidewall Contamination Apparent
If any of the sidewalls of the piping trench excavation appear to be contaminated, the sidewalls
must be sampled. Samples must be collected from the areas of the sidewalls that appear to be
the most contaminated. However, sampling must be conducted so that no more than 50 feet
exists between any two sampling points.
If the site conditions are such that the sidewalls are the appropriate locations for all samples,
at least one of the samples must be collected from the floor of the piping trench excavation
where the most contamination appears to be present. The sample must be collected at a depth
of at least one foot below the piping trench and into the native soil. If no area of the floor
appears contaminated or it appears uniformly contaminated, the sample must be collected at
the midpoint of the piping trench.
5.3.3 Closure in Place of Piping
Since potentially contaminated soils cannot be seen during closure in place activities as when
excavating, the sampling requirements for closure in place are more conservative. All
sampling schemes must follow the exact guidelines given in this document unless special
circumstances do not allow such. Any alternative sampling plan must be submitted to the
UST Branch for approval.
When piping is to be closed in place, sampling along the piping trench is not required if the
location of the dispenser island sample is within 25 feet of the nearest tank excavation
sample. The 25 foot distance is measured in a straight line as depicted in Figure 12.
If you are conducting a piping closure in place but the tanks are remaining active, the 25 foot
distance referenced above has no significance. Under these circumstances, a sample must be
collected from the dispenser island and from the end of the piping trench where it enters the
tank bed. If there is more than 25 feet of piping trench located between these two sampling
points, additional samples must be collected such than no more than 25 feet exists between
any two sample points.
If the distance between the dispenser island sample and the nearest tank bed sample is greater
than 25 feet, soil samples must be collected along the piping trench such that no more than 25
feet of piping exists between any two sampling points as shown in Figure 13. This means that
some excavation is required in order to locate the piping trench since sampling must occur
underneath or immediately adjacent to the trench. All soil borings must extend to a depth of at
least one foot below the bottom of the piping trench and into the native soil. Samples must be
collected from each boring following the field screening practices as described in Section
4.4.4.
If "true" groundwater (refer to Section 3.2) is encountered during soil boring activities,
groundwater samples must be collected from each boring that contains groundwater and each
sample must be analyzed separately. Soil sampling must be conducted from those borings that
do not have groundwater. In addition, regardless of whatever soil and/or groundwater
sampling that is conducted, one soil sample must be collected from the boring that exhibited
the highest level of petroleum contamination during the field screening process.
SECTION 6 - BACKFILL SAMPLING
6.1 General Requirements
All excavated backfill material must be sampled unless it is disposed of in an approved
sanitary landfill. This is because the soil samples collected from the native soil of the tank
excavation may not be representative of the contamination levels of the backfill materials.
A minimum of one soil sample is required to be collected for each 100 cubic yards of
material. Sample the backfill material as soon as possible after stockpiling. The samples
must be collected at a point at least one foot into the stockpile following the same sample
collection procedures as for any other soil sampling. The backfill samples must be analyzed
for the same constituents as the tank excavation samples.
6.2 Backfill Handling Options
Typically, all backfill material is contaminated and should be handled as such until laboratory
analysis proves otherwise. The following are the options allowed for handling the backfill
material:
a.
Dispose of in an approved landfill (Appendix B).
Conduct any sampling that may be required by the landfill and receive
permission from the landfill you wish to utilize.
b.
Stockpile on site and await the lab results of sampling.
All backfill material should be placed on and covered with an impervious material
(plastic sheeting). If the analytical results of the backfill material are below the action
levels of the UST Branch, the backfill material may be placed back into the
excavation. If the results are above our limits, your options are as described in
paragraphs a, d or e of this rule.
c.
Sample the backfill material and return it to the excavation.
The backfill material may be returned to the excavation before the analytical
results are obtained with the understanding that the backfill material may have
to be re-excavated if the analytical results arc above the action levels of the UST
Branch. If the results are above the action levels of the UST Branch, your options
are as described in paragraphs a, d or e of this rule.
d.
Aerate the backfill material on site.
If the analytical results indicate concentrations above the action levels of the UST Branch
and the owner does not want to dispose of the backfill material in an approved sanitary
landfill, the backfill material may be aerated on site. To aerate the backfill material, place
the backfill material on an impervious material (plastic sheeting), spread the backfill material
approximately one foot thick. Build a berm around the soil that will retain any rainwater and
prevent any contamination from spreading. Cover the soil on rainy days; uncover the soil on
sunny days. Disc or till the soil weekly. Contact a UST Branch Project Manager for
instructions before initiating the aeration process.
e.
Stockpile the backfill material at a different location.
Before this is done, approval must be obtained from the MDEQ
Groundwater Division-Special Waste Section.
SECTION 7 - DEVIATIONS FROM MINIMUM SAMPLING REQUIREMENTS
7.1 Hazards or Obstructions
When circumstances do not allow the collection of samples from the locations required in this
document, the owner must contact the UST Branch and receive prior approval of any
alternative sampling plan. Draw a sketch of the facility that shows the tank system in relation
to any obstacles and show the proposed sampling locations.
7.2 Waiver of Sampling Requirements
While not generally a recommended practice, sampling requirements may be waived if the
facility has monitoring wells as the method of leak detection and no evidence of a release has
been noted. The UST Branch generally will only consider groundwater monitoring to grant a
waiver. In order to request a waiver, submit the previous twelve months of monitoring well
records at the same time the "Notice of Intent to Permanently Close UST System(s)" form is
submitted and indicate you wish to have the sampling requirements waived.
However, if evidence of petroleum contaminated soil and/or groundwater is found during
closure activities, samples must then be collected from the appropriate locations and
analyzed as described in this guidance document.
SECTION 8 -SAMPLE ANALYSIS 8.1
Tanks
The samples must be analyzed for the product last stored in the UST (refer to the table
below). However, if evidence of a leak from a previously stored product is found or it is
known that the tank stored a different substance at one time, the samples must be
analyzed for that substance also. For example, all of the tanks have stored gasoline for
the past several years but it is known that one of the tanks was once used to store diesel
fuel. Therefore, all samples collected from the tank excavation would have to be
analyzed for both PAH and BTEX.
In addition, if an excavation contained tanks that stored substances that require both
BTEX and PAH analysis (i.e. gasoline and diesel fuel), all samples collected from the
excavation must be analyzed for both BTEX and PAH.
8.2 Dispenser Islands and Piping
Samples must be analyzed for the products last transferred in the piping. However, if
evidence of a leak from a previously stored product is found or it is known that the
piping transferred a different substance at one time, the samples must be analyzed for
that substance also.
In addition, if both diesel fuel and gasoline piping are in the same trench/dispenser
island, all samples collected from the piping trench/dispenser island must be analyzed
for both BTEX and PAH.
REQUIRED SAMPLE ANALYSIS (TANKS & PIPING)
Product Stored
Sample Media
Analysis
Gasoline
Soil/Water
BTEX*
Diesel Fuel, Used Oil
Kerosene, Jet Fuel
Soil/ Water
PAH**
Hazardous or Other
Substances
Soil/Water
***
* BTEX = The analysis for Benzene, Toluene, Ethylbcnzcne and Xylenes
802IB, 8260B
EPA Methods
** PAH = The analysis for poly nuclear aromatic hydrocarbons (EPA Methods 8100, 8270C or 8310)
*** Analyze by approved method for the substance stored or contact the UST Branch for required analysis
APPENDIX A
“The Closure Cycle”
UST OWNER
Decides to Close UST and
Verifies USTs are Registered*
UST OWNER
Selects Certified Contractor and
Submits Notice of Intent to Close
UST REMOVAL
UST CLOSURE-IN-PLACE
UST BRANCH
UST OWNER
Collects Soil Samples and Submits
Reviews Intent and Sends
Lab Results and Intent to Close
Owner Approval Letter**
Form to UST Branch
UST OWNER
UST BRANCH
Performs Closure in Accordance
Reviews Lab Results and Sends
with UST Branch Requirements
Owner Approval Letter***
UST OWNER
UST OWNER
Submits Closure Report and
Performs Closure in Accordance
Supporting Documentation****
with UST Branch Requirements
UST BRANCH
UST OWNER
Reviews Report and Sends
Submits Closure Report and
Owner No Further Action
Supporting Documentation****
Letter*****
*
If the tanks are not registered, the Owner must submit a
UST BRANCH
Notification for Underground Storage Tanks.
Reviews Report and Sends
** If the Notice of Intent to Permanently Close form is not
Owner No Further Action
completed satisfactorily, the form will not be accepted.
Letter*****
***
The lab results must normally be below the limits established by the UST Branch in order for the
Closure-in-Place to be approved.
****
Supporting documentation: a) lab results of any sampling; b) chain-of-custody; c) manifests for the
disposal of any contaminated soils, waters, or tank sludges; d) site drawing.
*****
If lab results are above UST Branch limits, Owner is notified of contamination and works with UST
Branch to clean up site.
APPENDIX B
Adams County
Plantation Oaks Landfill
Operator – Waste Management, Inc.
(601) 445-8459
Chickasaw County
Prairie Bluff Landfill
Operator – Waste Management, Inc.
(662) 456-9560
Clay County
Golden Triangle Regional Landfill
Operator – Golden Triangle SW Mgt. Auth.
(662) 324-7566
Harrison County
Pecan Grove Landfill
Operator – Waste Management, Inc.
(228) 255-5553
Jefferson County
Jefferson County Landfill
Operator – Southern Landfill Mgt., Inc.
(601) 786-9997
Kemper County
Kemper County Landfill
Operator - Kemper Co. Landfill
Company, L.L.C.
(601) 656-5411
Lauderdale County
Pine Ridge Landfill
Operator – Waste Management, Inc.
(601) 483-0715
Leflore County
Leflore County Sanitary Landfill
Operator – County & Santek Envir. of MS
(601) 453-8550
Madison County
City of Canton Sanitary Landfill
Operator – City of Canton
(601) 859-3245
Madison County
Little Dixie Landfill
Operator – BFI Waste Systems
(601) 982-9488
Pearl River County
Central Landfill
Operator – Transamerican Waste
(601) 795-2500
Perry County
Pine Belt Regional Landfill
Operator – Pine Belt SW Auth.
(601) 545-6676
Pontotoc County
Three Rivers Regional Landfill
Operator – Three Rivers SW Authority/
Santek Envir. of MS
(662) 488-0444
Scott County
Clearview Environmental Control
Operator – Chambers/USA Waste
(800) 832-2937
Tippah County
Northeast Mississippi Regional Landfill
Operator – Northeast Authority/
Waste Services, Inc.
(662)223-5445
Tunica County
Tunica County Landfill
Operator – Trashhunters, Inc.
(662) 363-2282
Washington County
Big River Landfill
Operator – BFI Waste Systems
(662) 335-1014
Winston County
City of Louisville Landfill
Operator – City of Louisville
(662) 773-9201
APPENDIX C
Notice of Intent to Permanently Close Underground Storage Tank System(s)
Return
Completed
Form
To
Mississippi Department of Environmental Quality
Office of Pollution Control
P. O. Box 2261
Jackson, MS 39225-2261
Facility I. D. Number:
Date Received by MDEQ:
Complete and return this form within thirty (30) days prior to permanently closing tank system
I. Location of Tank System
II. Ownership of Tank System
Name:
Address:
City:
County:
Name:
Address:
City:
State:
ZIP:
III. Date of Scheduled Tank System Closure
Month: _____________________
Day: ________________________
Year: _______________________
IV. Type of Permanent Closure
Tank & Piping Removal
Tank Removal Only
Piping Removal Only
Tank & Piping Closure in Place
Tank Closure in Place Only
Piping Closure in Place Only
Sand
Concrete
Virgin Drilling Mud
Approved "foam"
Will any new underground Tanks
Piping
be installed at this facility?
V. Underground Storage Tank System Information
Tank
Date of Installation
Tank Capacity
Substance stored
throughout history
of the tank (check
all that apply)
gasoline
diesel
used oil
kerosene
other
VI. Contractor Information
Name of Company Performing Closure:
Name of Individual Certified by MDEQ to Permanently Close USTs:
Mississippi DEQ UST Certification Number: Expiration Date:
VII. Sampling Requirements
All sampling must be performed in accordance with the Mississippi Department of Environmental Quality's Underground
Storage Tank Guidelines for the Permanent Closure of Petroleum Underground Storage Tanks.
Product Stored in Tank
Media
Analysis to be Performed
Gasoline
Waste Oil, Diesel, Kerosene
Other than above
Soil or Groundwater
Soil or Groundwater
Soil or Groundwater
BTEX (EPA Methods 8021B, 8260B)
PAH (EPA Methods 8100, 8270C, 8310)
Contact Office of Pollution Control
VIII. Owner Agreement
Oath: I certify that the information listed above is true and correct to the best of by belief and knowledge.
Owner's Name
Owner's Signature
Date Signed
Produced by the Mississippi Department of Environmental Quality, Office of Pollution Control, UST Branch
P. O. Box 2261, Jackson, MS 39225-2261 601.961.5171 /fax 601.961.5093 / www.deq.state.ms.us
Type of fill material to be used for
Closure in Place
4/08
APPENDIX D
UNDERGROUND STORAGE TANK SYSTEM CLOSURE REPORT
Return Department of Environmental Quality
Completed Office of Pollution Control
Form PO Box 2261
To Jackson MS 39225-2261
Location of Tank System Ownership of Tank System
Name ________________________________________ Name _________________________________________
Address ______________________________________ Address ______________________________________
City _____________________ County ______________ City ___________________State ____ ZIP
____________
Tank and piping removal _____ Tank and piping closure in place _____ Were any new tanks installed? _____
Tank removal only _____ Tank closure in place only _____ Was any new piping installed? _____
Piping removal only _____ Piping closure in place only _____ Number of active tanks remaining _____
Description of Underground Storage Tanks (Complete for each closed tank at this location.)
I. Tank Information
Tank
No.
Tank
No.
Tank
No.
Tank
No.
Tank
No.
Tank
No.
Estimated age of tank in years.
Estimated total capacity in gallons.
Substance stored in tank.
II. Tank Closure Information
Date product was removed from tank/piping (mm/dd/yy).
Date tank/piping was permanently closed (mm/dd/yy).
If closed in place, list the inert material used (sand,
concrete, drilling mud approved foam material).
Disposition of excavated backfill material .
Disposed of in landfill _______
Returned to excavation _______
Stockpiled on site _______
Aerating on site _______
Aerating off site _______
III. Site Assessment Information
Date samples were collected. (mm/dd/yy) ____________ Was groundwater encountered (yes/no) ____________
Was there any soil staining apparent? ____________ Depth to groundwater (feet) ____________
Was there any free product noted? ____________ Were visible holes in tanks/piping? _____________
To be completed by the tank owner: (Please print or type all but signature)
Date:
Oath: I certify that the information concerning closure is true to the best of my belief and knowledge.
Owner’s Name:
Owner’s Signature:
To be completed by person certified by MDEQ to Permanently Close:
Date:
Name of person certified by MDEQ to close/remove:
MDEQ Certified Contractor’s Signature:
MDEQ Certified Contractor’s Company:
MDEQ Certification No.:
Produced by the Mississippi Department of Environmental Quality, Office of Pollution Control, UST Branch
P O Box 2261, Jackson, MS 39225-2261 (601) 961-5171 Fax (601) 961-5093 www.deq.state.ms.us
4/08
Facility I.D. No. __________________________
Date Received by MDEQ __________________
Note: All backfill materials must
be handled in accordance with
the Mississippi Department of
Environmental Quality’s (MDEQ)
Guidelines for the Permanent
Closure of UST Systems.
TYPE OF UNDERGROUND STORAGE TANK SYSTEM CLOSURE
Submit the following supporting
documentation with this Closure Report:
1. Lab analytical results of sampling
2. Sample Chain-of-Custody
3. Site Drawing
4. Waste manifests if tank sludges, water or
backfill materials are disposed.
APPENDIX E
CHAIN OF CUSTODY RECORD
Company Name:
Address:
Location Name:
Address:
UST Facility I.D. Number::
Sampler Name:
Sampler Signature:
Number of coolers:
Required Due Date (mm-dd-yy):
Collection
Analysis
Required
Lab Number
Sample
Identification
Type of
Container
No.
of
Containers
Date
Time
Initials
Comp-C
Grab-B
Soil-S
Water-W
REMARKS
Relinquished by:
Date/Time:
Accepted by:
Date/Time:
Relinquished by:
Date/Time:
Accepted by:
Date/Time:
Relinquished by:
Date/Time:
Accepted by:
Date/Time:
Relinquished by:
Date/Time:
Accepted by:
Date/Time:
APPENDIX F
Industry Codes and Standards for Underground Storage Tank Closure or Change in
Service
"Removal and Disposal of Used Underground Storage Tanks", American Petroleum Institute
Recommended Practice 1604, 1220 L St., NW, Washington, DC 20005 (202) 682-8000.
"Cleaning Petroleum Storage Tanks", American Petroleum Institute Publication 2015.
"Interior Lining of Underground Storage Tanks", American Petroleum Institute Publication 1631.
"Criteria for a Recommended Standard...Working in Confined Space", The National Institute for
Occupational Safety and Health, Superintendent of Documents, U.S. Government Printing Office,
Washington, DC 20402.
"Tank Closure Without Tears: An Inspector's Safety Guide", New England Interstate Environmental
Training Center, 2 Fort Road, South Portland, ME 04106 (207) 767-2539.
"Excavation & Trenching Operations", Occupational Safety & Health Administration Publication
2226.
APPENDIX G
BORING LOG FOR UST SYSTEM CLOSURE IN PLACE
DEPTH
SOIL HYDROCARBON
(FEET)
TYPE VAPORS (PPM)
* INDICATE LOCATION OF EACH BORING ON CLOSURE DRAWING AND NUMBER
ACCORDINGLY.
Type of Instrument utilized for field screening_______________________
Manufacturer of instrument ______________________________________
Date last calibrated (mm/dd/yy)_____________ ______________________
NOTE:
Boring Logs for each borehole and the laboratory analytical results of
all sampling must be submitted at the same time the "Notice of Intent to Permanently Close
Underground Storage Tank(s)" form is submitted in order for the closure in place to be
approved by the UST Branch.
TOP SOIL
CLAY
SAND
CLAY
SAND
850 (SAMPLE COLLECTED FOR ANALYSIS)
BORE HOLE NUMBER 1
APPENDIX H - DEFINITIONS
Aliquot- Part of the whole. One sampling location may require two or more discreet containers in
order to qualify as an adequate sample. Each sample container is an aliquot.
Aquifer - Underground bodies of sand or gravel which contains groundwater.
Backfill - All of the soil which was placed in the excavation when the tank system was installed. In
UST systems installed after 1988, the backfill is normally easy to determine since tank systems were
required to be backfilled with clean sand or gravel and these materials are easily differentiated from
the native soil.
BTEX - Benzene, Toluene, Ethylbenzene, and Xylenes, the four major components of gasoline.
Convex Meniscus - Curved or rounded like the outside of a circle.
Decontamination - A process in which to clean and remove contaminants from sample equipment
and devices with detergent wash following a series of rinses with distilled water.
Groundwater - For the purposes of UST closures, it is the naturally occurring water that seeps into
the tank excavation from the aquifer.
Headspace - The air space between the sample and the top of the closed container.
Holding time - The length of time allowed between sample collection and analysis by the laboratory.
Native soil - Soil which has been undisturbed by activities of man.
PAH - Polynuclear Aromatic Hydrocarbons.
Preservative - A chemical added to a water and/or soil samples to prevent deterioration or to
maintain the original characteristics.
Repair - To restore a piping system. Repair as utilized in this document means that some minor
component, such as a flex connector or a coupling/union, of the piping system has been replaced or
simply tightened.
Septum cap - A sample container cap that has a membrane for extracting water with a syringe.
Stockpiling - Storing excavated materials on site. Correct stockpiling requires putting the excavated
material on plastic at a height not greater than 3 feet. A berm should surround the stockpiled
material in order to prevent rainwater run-off.
Teflon lined - A synthetic liner used to line the sides and caps of sample containers to prevent
samples from sticking.
VOC - Volatile Organic Compounds - chemicals which readily vaporize under normal atmospheric
conditions.
Part 5, Chapter: 3 Underground Storage Tank Regulations for the Certification of
Persons Who Install, Alter, Test, and Permanently Close Underground Storage Tanks
(Adopted January 24, 1990; Amended September 28, 1995; Last Amended August 23,
2018)
TABLE OF