11 MAC Pt. 8, R. 1.2.5
Processing of Permit Applications
Cite as 11 Miss. Admin. Code Pt. 8, R. 1.2.5
Processing of Permit Applications
A.
Applications for the issuance of any surface mining permit issued under this chapter shall
be filed with the Department. The Department shall:
(1)
conduct an initial review of a completed permit application within thirty (30) days
following receipt of the complete application.
(2)
make a recommendation to the Permit Board on the completed permit application no later
than the next regularly scheduled Permit Board meeting following the thirty-day initial
review period, unless a public hearing is held on the application or the applicant agrees in
writing to an additional time frame. If a public hearing is held, the Department shall make
its recommendation at the next regularly scheduled Permit Board meeting following the
public hearing, if practicable.
(3)
file a copy of each permit application for public inspection with the chancery clerk of the
county where any portion of the operation is proposed to occur after deleting any
confidential information according to Rule 1.1.6 of these Regulations.
(4)
submit copies, excluding all confidential information, of the permit application as soon as
possible to:
(a)
the Mississippi Soil and Water Conservation Commission, Mississippi
Department of Wildlife, Fisheries, and Parks, Mississippi Forestry Commission,
Mississippi Department of Environmental Quality, Mississippi Department of
Archives and History, Mississippi Department of Transportation, Mississippi
State Oil and Gas Board and Mississippi Department of Agriculture and
Commerce, and any other state or federal agency whose jurisdiction the
Department believes the particular mining operation may affect.
(b)
any person who requests in writing a copy of the application; and
(c)
the owner of the land.
(5)
require payment of a reasonable fee established by the Department for
reimbursement of the costs of reproducing and providing the copy.
(6)
The Department shall notify the applicant if any part of the proposed operation
lies within an area already designated as unsuitable for surface mining or for
which a petition to have lands designated unsuitable for surface mining has been
filed.
(7)
The Department shall cause an initial site inspection of the proposed affected area
to be made within 30 days following receipt of the completed application.
B.
Each agency shall review the permit application and submit, within fifteen (15) days of receipt of
the application, any comments, recommendations and evaluations as the agency deems necessary
and proper based only upon the effect of the proposed operation on matters within the agency's
jurisdiction. The comments shall include a listing of permits or licenses required under the
agency's jurisdiction. Comments and recommendations shall be made a part of the record and
one (1) copy shall be furnished to the applicant. All comments and recommendations shall be
considered by, but shall not be binding upon, the Permit Board. The failure of any agency to
submit comments shall not preclude action by the Permit Board.