12 MAC Pt. 13, R. 1.4
Definitions
Cite as 12 Miss. Admin. Code Pt. 13, R. 1.4
Definitions.
A. Addendum: Supplementary information to bidding documents issued during the time of
bidding that is included with the proposal and becomes part of the contract.
B. Alternate: An increase or decrease to the base bid for addition or deletion of project
scope.
C. Architect: A person who engages in the practice of architecture as set forth in MISS.
CODE ANN. § 73-1-3.
D. Award: Formal acceptance of a bid or proposal.
E. Bid: A competitive offer or proposal submitted to the Owner to perform a construction
project.
F. Bid Security: A form of monetary guarantee, typically in the form of a bid bond or
certified check, required by the Owner from a bidder to safeguard against withdrawal
of the bid and to ensure the contract will be fulfilled and executed if awarded.
G. BOB: Bureau of Building, Grounds and Real Property Management
H. Change Order [CO]: Documentation of any amendment to the sum, time, scope or
terms of a construction contract.
I.
Certificate of Responsibility [COR]: A numbered certificate issued to a Contractor by
the Mississippi State Board of Contractors pursuant to MISS. CODE ANN. § 31-3-1.
J.
Completion Date: A calendar date established by the contract as the deadline for
completion of the work.
K. Construction: The process of building, altering improving, renovating or demolishing a
public structure, public building, or other public real property pursuant to MISS. CODE
ANN. § 31-7-1. Construction does not include routine operation, routine repair or
regularly scheduled maintenance of existing public structures, public buildings or other
public real property.
L. Consultant: A sub-professional retained by the Professional to perform a designated
portion of the Professional services under the contract.
M. Contractor: Any person contracting or undertaking as prime Contractor, sub-contractor
or sub-sub-contractor of any tier to do erection, building, construction, demolition,
repair, maintenance or any related work on any public or private project as set forth in
MISS. CODE ANN. § 31-7-1.
N. Emergency: Those instances set forth in MISS. CODE ANN. § 31-7-1(f).
O. Engineer: A person who engages in the practice of engineering as defined in MISS. CODE
ANN. § 73-13-3.
P. Job Order Contract [JOC]: A task order for construction executed by an agency pursuant
to a term contract for indefinite-delivery/indefinite-quantity established by DFA based
upon a nationally published and recognized cost index pursuant to MISS. CODE ANN. §
31-7-13(n).
Q. Invitation for Bid [IFB]: Pursuant to MISS. CODE ANN. § 31-7-403, an IFB is the
preferred method of procurement and includes all documents utilized for soliciting bids,
whether attached or incorporated by reference. Award is made to the lowest responsive
and responsible bidder.
R. Liquidated Damages: A predetermined assessment of damages due to delayed
completion of a project or parts thereof.
S. Notice to Proceed: Start date for a Contractor to begin construction on a project as
established by the Owner following execution of the contract.
T. Owner: The entity responsible for initiating, contracting and overseeing a project from
start to finish.
U. Project Manual: A comprehensive written document assembled and prepared for a
construction project that contains bid documents, the agreement, bonds, certificates, and
general conditions of the contract, including specifications and addenda.
V. Professional: Architect or Engineer
W. Professional Services Bulletin: Online procurement portal maintained by a
governmental entity or by an organization.
X. Public Works: Facilities and improvements financed by the government for the public
good as set forth in MISS. CODE ANN. § 31-7-1, et seq.
Y. Real Property: All land, structures, and firmly attached and integrated equipment.
Z. Request for Proposal [RFP]: All documents utilized for soliciting proposals from
potential vendors, whether attached or incorporated by reference. Awards are made to
the offeror receiving the highest score based on weighted evaluation criteria outlined in
the RFP and may include discussions with offerors.
AA. Request for Prequalification of Contractors [RFPC]: All documents, whether attached or
incorporated by reference, utilized for soliciting qualifications from potential construction
Contractors. Awards are to be made to the offeror receiving the highest score based on
weighted evaluation criteria outlined in the RFPC and may include discussions with
offerors.
BB. Request for Qualification [RFQ]: All documents, whether attached or incorporated by
reference, utilized for soliciting qualifications from potential vendors. Awards are made
to the offeror receiving the highest score based on weighted evaluation criteria outlined
in the RFQ and may include discussions with offerors.
CC. Responsive: Meets the requirements set forth in the solicitation.
DD. Responsible: Meets the minimum qualifications in the solicitation.
EE. Schedule of Values: A document that breaks down the total project costs into individual
work items along with their corresponding costs or values.
FF. Solicitation: A competitive request for proposals either through invitation and/or public
notification.
GG. Substantial Completion: The date certified by the Professional when construction is
sufficiently complete, in accordance with the contract documents, so the Owner may
occupy or otherwise utilize the work or designated portion thereof for the use for which it
is intended.
HH. Using Agency [UA]: Agency, Institution or Department of the State of Mississippi
II. Warranty: A written agreement guaranteeing the integrity of a facility or product for a period
and the Contractor’s or manufacturer’s responsibility for repair or replacement of defective
parts or workmanship.