15 MAC Pt. 20, R. 5.3.19

Construction Phase Submissions, Approvals, and Actions -Timeline

Year: 2026Length: 578 wordsOfficial source

Cite as 15 Miss. Admin. Code Pt. 20, R. 5.3.19

Construction Phase Submissions, Approvals, and Actions -Timeline The following submittals, approvals, and actions will be required during the construction phase of the project. The Department may establish other time frames within the Grant agreement when properly justified. 12. Within 30 days after approval of plans, specifications, and contract documents by the Department (1) all construction related contracts shall be advertised for bids and proof of such advertisement shall be submitted, (2) all local funds necessary for the project shall be secured, and proof of such local funds shall be submitted, and (3) clear site certificates from the Grant recipient and title counsel for all real property shall be submitted. 13. Within 60 days after approval of plans, specifications, and contract documents by the Department 45 days after advertisement, the Grant recipient shall open bids on all construction related contracts. 14. Within 14 days after receipt of bids for new construction, the Grant recipient shall submit all bid packages. 15. Within 60 days after receipt of bids, the Grant recipient shall execute all construction contract documents, shall submit a copy of all executed contract documents, and shall issue and submit a copy of the notice to proceed on all such contracts. 16. By the date initially established in the Grant agreement (which is based upon approximately 50% of contract time) the Grant recipient shall submit a completed asset management plan for all drinking water facilities to be constructed in whole or in part with ARPA RWAI Grant funds. 17. By the date initially established in the Grant agreement (which is based upon approximately 90% of contract time) the Grant recipient shall secure approval of the asset management plan. 18. Within 10 days after construction completion of each construction contract, the Grant recipient shall notify the Department of construction completion. 19. The Department will perform a final construction observation within 30 days after the current construction contract completion date, unless further delayed by the Department pursuant to review of the Grant recipient's request and justification for such delay. Should the Department decide that the construction completion is being unreasonably delayed, a final construction observation may be immediately performed by the Department. The final construction observation by the Department is only for the purpose of determining final Grant allowable costs. 20. Within 30 days after the current construction contract completion date, all change orders which include time extensions exceeding 30 days beyond the original contract completion date, and/or documentation showing the Grant recipient is implementing all legal remedies provided in the contract documents for failure to complete construction when required, shall be submitted to the Department for an allowability determination 21. Within 60 days after the final construction observation performed by the Department, the Grant recipient shall submit: the final payment request for the awarded grant; approvable summary change orders for all construction contracts; full scale record drawings with all revisions shown and noted for the entire project funded in whole or in part with ARPA RWAI Grant funds; the registered licensed engineer's certification of compliance with plans, specifications, and contract documents; appropriate bacteriological test results; final construction phase professional services contract amendments, if any; and all other administrative forms and documents required by the Grant agreement. Grant payment requests submitted after this date are not allowable, regardless of when the costs were incurred. 22. Any other submittals or actions required by the Grant agreement shall be performed when so required and are subject to review and approval by the Department.
15 MAC Pt. 20, R. 5.3.19: Construction Phase Submissions, Approvals, and Actions -Timeline | Justis AI