15 MAC Pt. 20, R. 5.3.19
Construction Phase Submissions, Approvals, and Actions -Timeline
Cite as 15 Miss. Admin. Code Pt. 20, R. 5.3.19
Construction Phase Submissions, Approvals, and Actions -Timeline
The following submittals, approvals, and actions will be required during the construction
phase of the project. The Department may establish other time frames within the Grant
agreement when properly justified.
12.
Within 30 days after approval of plans, specifications, and contract
documents by the Department (1) all construction related contracts
shall be advertised for bids and proof of such advertisement shall be
submitted,
(2) all local funds necessary for the project shall be secured, and proof of such local funds shall
be submitted, and (3) clear site certificates from the Grant recipient and title counsel for all real
property shall be submitted.
13.
Within 60 days after approval of plans, specifications, and contract
documents by the Department 45 days after advertisement, the
Grant recipient shall open bids on all construction related contracts.
14.
Within 14 days after receipt of bids for new construction, the
Grant recipient shall submit all bid packages.
15.
Within 60 days after receipt of bids, the Grant recipient shall execute
all construction contract documents, shall submit a copy of all
executed contract documents, and shall issue and submit a copy of
the notice to proceed on all such contracts.
16.
By the date initially established in the Grant agreement (which is based
upon approximately 50% of contract time) the Grant recipient shall
submit a completed asset management plan for all drinking water
facilities to be constructed in whole or in part with ARPA RWAI Grant
funds.
17.
By the date initially established in the Grant agreement (which is
based upon approximately 90% of contract time) the Grant recipient
shall secure approval of the asset management plan.
18.
Within 10 days after construction completion of each construction
contract, the Grant recipient shall notify the Department of
construction completion.
19.
The Department will perform a final construction observation within
30 days after the current construction contract completion date, unless
further delayed by the Department pursuant to review of the Grant
recipient's request and justification for such delay. Should the
Department decide that the construction completion is being
unreasonably delayed, a final construction observation may be
immediately performed by the Department. The final construction
observation by the Department is only for the purpose of
determining final Grant allowable costs.
20.
Within 30 days after the current construction contract completion date,
all change orders which include time extensions exceeding 30 days
beyond the original contract completion date, and/or documentation
showing the Grant recipient is implementing all legal remedies
provided in the contract documents for failure to complete construction
when required, shall be submitted to the Department for an
allowability determination
21.
Within 60 days after the final construction observation performed by
the Department, the Grant recipient shall submit: the final payment
request for the awarded grant; approvable summary change orders for
all construction contracts; full scale record drawings with all revisions
shown and noted for the entire project funded in whole or in part with
ARPA RWAI Grant funds; the registered licensed engineer's
certification of compliance with plans, specifications, and contract
documents; appropriate bacteriological test results; final construction
phase professional services contract amendments, if any; and all other
administrative forms and documents required by the Grant agreement.
Grant payment requests submitted after this date are not
allowable, regardless of when the costs were incurred.
22.
Any other submittals or actions required by the Grant agreement shall
be performed when so required and are subject to review and approval
by the Department.