15 MAC Pt. 20, R. 5.3.9
Budget Modifications, Schedule Modifications, and Amended Grant Offer
Cite as 15 Miss. Admin. Code Pt. 20, R. 5.3.9
Budget Modifications, Schedule Modifications, and Amended Grant Offer
1.
Budget Modifications. Grant recipients can request to move funds between
eligible categories in the Grant Agreement by completing a budget
modification. This modification will be required prior to approval of
reimbursement of any costs where the costs exceed the available budget. The
contingency fund can be spent for construction costs only without a budget
modification, however these funds should be moved to the construction
category prior to the project closeout. Grant recipients can also add
additional local funds to the project as needed. After determining that the
budget modification is approvable, the Department will transmit to the Grant
recipient for approval of the modification.
2.
Schedule Modification. To amend the schedule in the Grant Agreement,
Grant Recipient should submit a letter detailing the need for schedule
revision. After determining if the schedule modification is approvable, the
Department will transmit to the Grant recipient for approval of the
modification. Schedule modifications to construction contract should be
submitted in the form of a change order.
3.
Process after Grant Agreement Amendment Request
If the budget and schedule modifications cannot address the needed
changes to the Grant Agreement, the Grant Recipient can submit a Grant
Agreement Amendment Request. After receipt, review, and approval of
the Grant agreement amendment request, the Department may prepare
and transmit an amended ARPA RWAI Grant offer to the Grant recipient.
The Grant offer will include in the project budget:
A.
The approved as-bid amounts for construction;
B.
The final allowance amounts for professional services in
accordance with Subchapter 5 of these regulations;
C.
A construction contingency as determined by the Department; and,
D.
Required local funds, if any.
Source: House Bill 1421, 2022 Regular Session & Senate Bill 2444, 2023 Regular Session of the MS
Legislature
3.
Execution of Amended Grant Offer
Upon receipt of the amended ARPA RWAI Grant offer, the Grant recipient shall completely
execute and return it to the Department within the timeframe established in the offer letter. After
execution of the amended ARPA RWAI Grant offer. Any increased project costs in excess of the
amended ARPA RWAI Grant amount shall be paid by the Grant recipient from sources other
than ARPA RWAIG funds.