15 MAC Pt. 20, R. 5.6.2
Environmental Review
Cite as 15 Miss. Admin. Code Pt. 20, R. 5.6.2
Environmental Review.
The Registered Licensed Engineer will take one or more of the following actions pursuant to
the review of the Environmental Review Report of Environmental Impacts:
7.
Previously Disturbed Certification
Complete certification that all work to be performed as a part of this project will be performed on
previously disturbed sites, easements, and/or rights-of-way. Certify that no new sites, easements
and/or rights-of-way will be disturbed as a result of this construction/repair project, and
therefore, no comments or responses are required from the state or federal agencies listed below
in order to ensure compliance with the state or federal laws or regulations under the jurisdiction
of these agencies. Categorical Exclusion
8.
Environmental Impacts Resolved Certification
Complete certification that comments and responses have been solicited and resolved from the
state and federal agencies listed below regarding all work to be performed under this project on
new sites, easements, and/or rights-of-way.
The Registered Engineer will issue a Categorical Exclusion (CE) from environmental review if a
project meets all of the following criteria:
A.
The project includes minor rehabilitation of existing facilities,
functional replacement of equipment, or construction of new
ancillary facilities adjacent or appurtenant to existing facilities.
B.
The project will not have a significant adverse effect on the
environment.
C.
The project will not adversely affect cultural resources, habitats of
endangered or threatened species, or environmentally important
natural resource areas.
D.
The project is not expected to cause significant public controversy.
The Department may revoke a categorical exclusion at any time if
significant adverse information becomes available.
Finding of No Significant Impact (FONSI) on the Environment
The Registered Engineer will issue a Finding of No Significant Impact (FONSI) and an
Environmental Assessment (EA) when, based upon review of the environmental impacts in the
Environmental Review Report, it appears that a project will not have a significant adverse
environmental impact, but does not qualify for a CE.
Amendment to a Finding of No Significant Impact FONSI to the Environment FONSI
amendments are occasionally needed to describe changes to proposed facilities that have already
been described in a FONSI.
Environmental Impact Statement (EIS)
If the Registered Engineer determines that an environmental impact statement (EIS) is needed,
the document will be prepared in general conformance as deemed appropriate by the
Department.
9.
No Further Action
The Registered Licensed Engineer will issue a CE, FONSI, or EIS complete the appropriate
certification on all ARPA RWAIG projects. If there are significant changes in the project after
the issuance of the environmental documents, those changes will be described in an
Amendment to a FONSI the certification. Some changes are minor, however, and the
Department may determine that a separate Amendment need not be issued. Such minor changes
may include but are not limited to:
A.
Adding work that would otherwise qualify for a
categorical exclusion previously disturbed certification.
B.
Changes in the size of pump stations, storage facilities,
wells, distribution lines, etc.
C.
Minor changes in the size of water treatment unit processes.
D.
Minor rerouting of distribution lines when the new route
i)
will be mostly on public property and
ii)
will not adversely affect cultural resources,
habitats of endangered or threatened species, or
environmentally important natural resource areas.
All affected property owners shall be notified by the Grant recipient.