15 MAC Pt. 20, R. 5.8.2
Planning and Design
Cite as 15 Miss. Admin. Code Pt. 20, R. 5.8.2
Planning and Design
During preparation of the plans and specifications, the Licensed Engineer will ensure that the
appropriate intergovernmental review agencies have been consulted about the proposed project
area concerning the existence of any known or possible archaeological/cultural sites, endangered
vegetation/wildlife, wetlands, floodplain impacts, wild/scenic river impacts, shellfish/coastal
program impacts, or coastal barriers resources impact. The Licensed Engineer will certify during
the plans, specifications, and contract documents phase, that the proposed project components
have been evaluated through a intergovernmental review process and that no concerns have been
discovered that would prevent the project from moving forward and that the project has been
cleared. If feasible, the project should avoid negative impacts on areas for which a concern has
been expressed by an intergovernmental review agency. If it is not feasible to avoid negative
impacts on these areas, the appropriate intergovernmental review agency should be consulted
concerning the probability of obtaining clearance to construct the selected plan.
Source: House Bill 1421, 2022 Regular Session & Senate Bill 2444, 2023 Regular Session of the MS
Legislature
For projects submitted in the second round of funding, an additional ten points will be added to
any project combining consolidation/regionalization of public water systems with one of the
other categories listed. In order to receive the additional weight, the systems that will
consolidate shall be in a proximity of each other as determined by the department. In addition to
these additional consolidation points, an additional 10 points shall be added to any application
with at least one system that has consolidated after January 1, 2018, and before application to
this program and is otherwise eligible.
RANK
PROJECT CATEGORY
Primary Drinking Water Standards
Project facilitates compliance with Primary Drinking Water
Standards. Project must correct deficiencies resulting in non-
compliance with the primary drinking water standards.
One Well
Project to provide additional water supply to systems that
have neither a backup well nor an MSDH-approved
emergency tie-in to another system to ensure safe drinking
water; thereby protecting the health of the existing
population.
Pressure Deficiencies
Project to correct documented deficiencies that result in
existing systems routinely failing to maintain minimum
acceptable dynamic pressure.
Source Water Protection Projects
Project to manage potential sources of
contaminants/pollutants and/or prevent
contaminants/pollutants from reaching sources of drinking
water.
Capacity Expansion to Serve the Unserved
Project to either expand existing system capacity or construct a
new drinking water system to serve existing
residences/businesses in currently unserved areas safe
drinking water (source, treatment and/or distribution).
Back-up Water Supply Sources Projects
Project to provide additional supply to systems with
insufficient back-up water supply sources to ensure safe
drinking water, and thereby protect the health of the existing
population.
RANK
PROJECT CATEGORY
Existing Facilities Upgrades (Meeting Primary Standards)
Project to rehabilitate, replace, protect or upgrade
deteriorated, worn, aged or obsolete equipment, facilities,
etc., to assure continued, dependable operation of water
systems where such systems are already meeting Primary
Drinking Water Standards.
Secondary Drinking Water Standards Projects
Project to provide treatment that brings systems into
compliance with Secondary Drinking Water Regulations.
Consolidation Projects
Project to consolidate separate systems into a single system
for purposes other than those related to meeting primary
standards.
Fluoride Addition
This category is for projects that either rehabilitate existing
fluoride treatment facilities at well or treatment plant sites or
add new facilities to existing well or treatment plants.
Other
Project does not meet the criteria of any category listed above.
K. The extent to which the project promotes economic development will be
quantified based on assessment of yes (5) or no (0) with a maximum of 5
points within this category.
L. The number of people served by the project will be quantified based on
population range.
Population Range Ranking
- 3,300
3,300 - 6,600
6,600 - 9,900
9,900 - 13,200
13,200 - 16,500
16,500 - 19,800
19,800 - 23,100
23,100 - 26,400
26,400 - 29,700
29,700 - 33,000
33,000 - 36,300
36,300 - Above
M. Impacts of the proposed project on disadvantaged communities will be
quantified based on Median Household Income (MHI).
MHI Range
Ranking
$0.00
-$20,144.00
$20,144.00 -$23,073.67
$23,073.67 -$26,003.33
$26,003.33 -$28,933.00
$28,933.00 -$31,862.67
$31,862.67 -$34,792.34
$34,792.34 -$37,722.00
$37,722.00 -$40,651.67
$40,651.67 -$43,581.34
$43,581.34 -$46,511.00
$46,511.00 -
Above
N. The grant applicant's prior efforts to fund the project will be quantified based
on assessment of yes (5) or no (0) with a maximum of 5 points within this
category.
O. The grant applicant's proposed contribution will be quantified based on a
percentage range of the projects total cost with a maximum of 5 points within
this category.
Percentage Range Ranking
1% -
4%
5% -
9%
10% - Above
P. The grant applicant's long-term plans for the financial and physical operation
and maintenance of the project will be quantified based on an assessment.
Applicants with no plan will receive a zero (0). Applicants with a long-term
plan will receive five (5). Applicants certifying the development of an asset
management plan by the end of the project will receive ten (10) with a
maximum of 10 points within this category.
Q. The grant applicant's capacity to complete the proposed project by the
deadline specified by rules and guidelines of the USDT for ARPA funds will
be quantified based on an assessment. Applicants able to meet this
requirement will be quantified at 10 with a maximum of 10 points within this
category. Applicants unable to meet this requirement will be disqualified.
R. If necessary, the following will be used as the basis for breaking any ties that
occur.
a) Projects to primarily correct a MSDH documented failure to
meet primary drinking water standards or a MSDH
documented significant deficiency will be given preference.
b) If there are no projects to correct a MSDH documented
failure to meet primary drinking water standards or a MSDH
documented significant deficiency, projects primarily for
consolidation will be given preference.
c) If there are no projects primarily for consolidation, projects
with the lowest Median Household Income Range will be
given preference.
d) If all projects have the same Median Household Income
Range, projects with the lowest Population will be given
preference.
e) If all projects have the same Population Range, projects
extending potable water service to new users will be given
preference.