15 MAC Pt. 9, R. 6.21

Department Periodic Review of Approved Projects

Year: 2026Length: 110 wordsOfficial source

Cite as 15 Miss. Admin. Code Pt. 9, R. 6.21

Department Periodic Review of Approved Projects. The Department shall periodically review the progress and time schedule of any holder issued or granted a Certificate of Need for any purpose, consistent with the mandate of Miss. Code Ann. ยง 41-7-193(2). The Department may conduct site visits, audits, inspections, correspondence reviews, file reviews, or other activities reasonably necessary to verify that approved projects are progressing in accordance with the approved time schedule and within the approved scope and capital expenditure. A CON-holder shall cooperate with the Department in the exercise of its periodic review authority. Failure to cooperate may constitute grounds for enforcement action, revocation, rescission, or other action authorized by law.