Construction Projects.
All construction projects shall be designed and constructed with the objective of
maximizing cost containment, protecting the environment, and conserving
energy. Each proposal involving construction shall be accompanied by a cost
estimate and, where applicable, schematic drawings. Space allocations shall
conform to applicable local, state, or minimum standards.
The cost per square foot shall be calculated based on the total project cost, minus
the cost of land and non-fixed equipment, using the following formulas:
New Construction/Renovation (Prorated Project): Cost per sq. ft. (New
Construction) = A+C+D+(E+F+G(A%)) ÷ New Construction Sq. Ft.;
Cost per sq. ft. (Renovation) = B+(E+F+G(B%)) ÷ Renovation Sq. Ft.
New Construction Only: Cost per Sq. Ft. = (A+C+D+E+F+G) ÷ Total
Sq. Ft.
Renovation Only: Cost per Sq. Ft. = (B+C+E+F+G) ÷ Total Sq. Ft.
Where: A = New Construction; B = Renovation; C = Fixed Equipment;
D = Site Preparation; E = Fees; F = Contingency; G = Capitalized
Page 63 — Mississippi State Department of Health
Interest; A% = percentage of sq. ft. for new construction; B% =
percentage of sq. ft. for renovation.
Any cost overrun on a construction or renovation project that locates cost in or
above the upper one-fourth range for U.S. construction or renovation cost shall
require additional documentation. Construction cost overrun requests shall be
with nationally recognized construction cost data, including RS Means or
comparable industry references or other bona fide reference.