16-228
Montana Attorney General Opinion 16-228
Length: 230 wordsOfficial source
Cite as 16 Mont. Op. Att'y Gen. No. 228
Opinion No. 228.
State Highway Commission-High-
ways-Contractors-Labor-Wages.
HELD:
Contracts for state high-
way construction, repair and main-
tenance work must contain a provi-
sion that the contractor must pay the
standard prevailing wages paid in the
county seat of the county in which
the work is being performed.
January 11, 1936.
State Highway Commission
The Capitol
We are returning herewith four-
teen contracts which you have sub-
mitted to this office for approval.
In all of these contracts it is pro-
vided:
"In the performance of this
contract, the contractor will be re-
quired to pay a minimum wage rate
of $0.60 per hour for unskilled labor,
a minimum wage rate of $0.75 per
hour for the lowest classification of
intermediate grade labor, with the
higher minimum wage rates for the
higher classifications of intermediate
grade labor and a minimum wage rate
of $1.00 per hour for skilled labor, all
as described fully in the special provi-
sions for this project."
Chapter 102, Laws of Montana,
1931, makes it necessary to insert, in
all contracts for state construction,
repair and maintenance work, a pro-
vision by which the contractor must
pay the standard prevailing rate of
wages in effect as paid in the county
seat of the county in which the work
is being performed. ~
Until this statutory requirement is
inserted in these contracts we may
not approve them.