ARM 38.5.1908

ARM 38.5.1908. INFORMATION TO BE PROVIDED TO THE COMMISSION

Last amended: 2022Length: 100 wordsOfficial source

Cite as Mont. Admin. R. 38.5.1908

(1) Pursuant to initial contact with a potential qualifying facility, each utility shall provide the Commission with one electronic copy of the utility's initial written response. (2) No later than July 1 of each even-numbered year, each utility shall file with the Commission the following cost data: (a) the estimated avoided cost of energy as required by 18 CFR 292.302(b)(1); (b) the electric utility's latest resource plan, including any supplements, as required by 18 CFR 292.302(b)(2); and (c) the estimated capacity costs as required by 18 CFR 292.302(b)(3). These costs shall represent the avoidable resources in the utility's resource plan.
ARM 38.5.1908: ARM 38.5.1908. INFORMATION TO BE PROVIDED TO THE COMMISSION | Justis AI