ARM 38.5.8402

ARM 38.5.8402. APPLICABILITY

Last amended: 2010Length: 113 wordsOfficial source

Cite as Mont. Admin. R. 38.5.8402

(1) The interconnection procedures set forth in this subchapter apply to applicants proposing to install and interconnect a small generator facility to an EDC's system that satisfies the following criteria: (a) The small generator facility must be sited on the utility customer's premises; (b) The customer installing the small generator facility must be in good standing with the utility; (c) The proposed small generator facility's point of interconnection may not be on a transmission line; (d) The power produced from the small generator facility must be contained on the EDS and not flow onto the transmission system; and (e) The power exported by an interconnection customer can only be sold to the EDC.