(1) An application for an electric transmission line must contain an explanation of the need for the facility based on, but not limited to, one or more of the following conditions: (a) transient stability considerations under normal or contingent operating conditions; (b) power transfer capacity under normal or contingent operating conditions; (c) voltage drop in the transmission or subtransmission network under normal or contingent operating conditions; (d) reliability of service considerations; and (e) economy considerations.