ARM 17.50.1109
ARM 17.50.1109. RUN-ON AND RUN-OFF CONTROL SYSTEMS
Cite as Mont. Admin. R. 17.50.1109
(1) The owner or operator of a Class II landfill unit shall design, construct, and maintain:
(a) a run-on control system to prevent flow onto the active portion of the landfill during the peak discharge from a 25-year storm; and
(b) a run-off control system from the active portion of the landfill to collect and control at least the water volume resulting from a 24-hour, 25-year storm.
(2) Run-off from the active portion of the landfill unit must be handled in accordance with 17.50.1110(1).