46-137
Highways
Cite as N.D. Op. Att'y Gen. 46-137
OPINION
46-137
November 1, 1946 (OPINION)
HIGHWAYS
RE: Lowest Bidder - Bidders Bond
This will acknowledge your letter of October 31, 1946, in which you
seek an opinion of this office concerning the application of section
24-0221 of the North Dakota Revised Code of 1943 to a bid received in
your office for the construction of a grade separation project near
Kurtz, North Dakota.
The facts as I understand them are as follows:
The low bidder offered a bid of $160,033.53. Accompanying this bid
for the construction of the grade separation project near Kurtz was a
certified check on a solvent North Dakota bank in the amount of
$8,000.00. This certified check was short $1.67. The exact amount
of the certified check at five percent should have been $8,001.67.
The lowest bidder was $26,332.47 under the next lowest bid. In other
words, the low bid, if accepted by the state highway department and a
contract consummated, would result in a substantial saving to the
department.
The question that arises is whether or not the terms of section
24-0221 of the North Dakota Revised Code of 1943 bar the acceptance
of the bid by the state highway department, so as to necessitate the
rejection of all bids with the result that it would become necessary
for the department to again request bids for the construction of the
project involved.
It is true that section 24-0221 of the North Dakota Revised Code of
1943 requires a certified check to accompany a bid in an amount equal
to five percent of the bid drawn on some solvent bank in the state of
North Dakota. While the statute uses the word "shall" in referring
to the certified check, it is our opinion that in the particular case
involved there has been a substantial compliance with the statute and
that the department should accept the bid involved, and that it has a
legal authority to do so. It is apparent that failure to make the
check of the low bidder in the exact amount of five percent of the
bid is an error, and in view of the fact that the failure to do so
would result in no substantial or material loss to the state in case
of a forfeiture of the certified check, it is our opinion that the
department may properly accept the lowest bid for the construction of
this grade separation project, and that a contract should be awarded
to the low bidder.
While we have found no case exactly in point, we have found authority
which substantiates our opinion.
A requirement that bids shall be accompanied by security to be
furnished by the successful bidder for failure to enter into
the contract is for the protection of the city, and failure of
the city to require it affords no ground of objection to the
contract by a taxpayer." (McQuillin Mun. Corp. Rev. 3, 1224,
sec. 1323)
In California, a bidder accompanied his bid by a bond conditioned for
execution of a contract. The amount of the bond required was ten
percent of the amount of the contract. This amount could be
determined only upon the determination of the city council of the
amount of electric current to be used. Hence, the bond being for an
amount certain was less than the actual amount of the requirements
when the amount of current and of the contract was ascertained. The
court held that the city was justified in awarding the contract,
saying the bond was for the benefit of the city. (Cady v. City of
San Bernadino, 153 Cal. 24, 94 Pac. 242)
And where security is required, it is held that, in absence of
a showing of fraud or collusion, an injunction will not lie to
prohibit the awarding of the contract to a bidder, who has
failed to give security." (McQuillin Mu. Corp. Id.)
In New York, the sureties on a bidder's bond were not worth the
amount of the bond. It appeared that the letting of the contract
would benefit the city. Held that as the requirements were for the
benefit of the city, it might waive the irregularities. (McCord v.
Lauterbach, 86 N.Y. Supp. 503, 91 App. Div. 315)
Our statute states:
Such check shall be forfeited to the state highway fund should
the bidder fail to effect a contract within ten days after a
notice of an award."
We believe that the maxim: "De minimus non curat lex" applies to
this situation, the law does not concern itself about trifles. It is
apparent that the deficiency in the amount of the certified check
must be sufficient to subject the public body to a substantial loss
if the contract be awarded and the bidder refuses to enter into the
same. The security is for the benefit of the public department, and
it is our opinion that it may waive a slight irregularity, such as is
involved here, where even though there was a forfeiture of the amount
of the certified check there would be no substantial or material loss
to the department. Surely, in a situation such as confronts your
department, the department should have the right to waive the same in
order to secure the benefit to the highway department of this low
bid, and the saving that will be procured under it.
NELS G. JOHNSON
Attorney General