1.
All electrical installations, including power limited system installations defined by the National
Electrical Code Special Occupancies, articles 500 through 517, with a value of five hundred
dollars or more, shall have an electrical wiring certificate submitted by the master, class B, or
power limited electrician supervising the installation on a form prescribed by the board. A
project with multiple address locations requires an electrical wiring certificate for each location.
2.
Before work commences on any electrical installation when a new service is installed, an
existing service is altered or repaired, a building is moved, when a mobile home service or
feeder is installed, or when the cost of the repair work or additional installation exceeds five
hundred dollars, the master, class B, or power limited electrician supervising such installation
shall submit an electrical wiring certificate and distribute as follows:
a.
A startup copy of the certificate must be submitted to the board and a copy to the power
company before work is commenced and before an electrical installation may be
energized.
b.
Within fifteen days of completion, use, or occupancy, whichever is first, the final
paperwork must be submitted to the board, along with the proper fee. The wiring
certificate must be completed with the location and a proper description of work
completed.
c.
A copy must be retained by the master, class B, or power limited electrician.
d.
A copy must be left in or on the panel or given to the owner.
3.
Certificates with job cost of twenty thousand dollars or less are valid twelve months from the
original filing date. A new wiring certificate must be filed on all unfinished work.
4.
E-certs are available upon request and submission of an application from any master, class B,
or power limited electrician holding a proper current license from the board. The master,
class B, or power limited electrician is responsible for all certificates issued to and by that
person. A charge of twenty-five dollars to cover board costs must be assessed on each lost
electrical paper wiring certificate issued to any master, class B, or power limited electrician,
unless returned to the board.
5.
Whenever an electrical installation made by or under the supervision of a master, class B, or
power limited electrician is commenced or in use without submitting an electrical wiring
certificate, as directed in subsection 2, the certificate may be considered late and the normal
inspection fee, as required under this section, is increased in the amount of fifty dollars. In
addition when time and travel are expended by employees of the board to obtain a late
certificate, an investigative fee may be charged to cover the costs incurred. Costs must be
calculated at a rate of fifty dollars per hour and mileage rates currently allowed by North
Dakota Century Code section 54-06-09 per mile of travel.
6.
Property owners who are self-wiring or doing their own electrical work shall comply with the
following before any electrical work commences:
a.
Submit an application to the board.
b.
Must own and occupy the residential property or farmstead where the electrical work will
be done.
c.
Review plans or drawings depicting wiring to be done with the local electrical inspector.
d.
Inspection fees must be calculated as stated in this section with a minimum of fifty
dollars.
e.
Certification and inspection are required as stated in this section.