NDAC 33.1-15-23-02
Permit to construct fees
Cite as N.D. Admin. Code ยง 33.1-15-23-02
Any person constructing, installing, or establishing a new stationary source or altering an existing
source which requires a permit to construct under subsections 1 and 3 of section 33.1-15-14-02 is
required to pay a permit to construct application filing fee and a permit to construct processing fee to
the department.
1.
Application fee. A nonrefundable filing fee of three hundred twenty-five dollars must be
submitted with the permit application.
2.
Processing fee. The applicant shall pay a processing fee based on actual processing costs,
including computer data processing costs, incurred by the department for all sources which
would involve a major analysis the cost of which would exceed three hundred twenty-five
dollars as determined by the department. The following procedures and criteria will be utilized
in establishing the fee:
a.
A record of all permit to construct application processing costs incurred must be
maintained by the department.
b.
Upon request, the department, in consultation with the applicant, will prepare an estimate
of the processing fee and the billing schedule that will be utilized in processing the
application.
c.
Statements will be sent to the applicant containing the actual processing costs incurred
by the department.
d.
The applicant must pay the processing fee regardless of whether a permit to construct is
issued, denied, or withdrawn.
e.
Any source that initiates operation under a permit to construct prior to receiving a permit
to operate is subject to the fees outlined in section 33.1-15-23-03 or 33.1-15-23-04,
whichever is applicable.