1.
Submission of plans. Plans and specifications shall be prepared for all new public water
systems and for alterations or extensions to existing systems. Such plans and specifications,
together with other pertinent information, shall be submitted to the department for review and
approval prior to awarding of contracts. Such plans and specifications shall:
a.
Be submitted in triplicate and in sufficient time to permit at least a two-week period for
review and comment and with additional time to incorporate changes, if required;
b.
Be presented in legible form and of sufficient scale to facilitate review;
c.
Include supplemental information pertaining to basis of design, description of existing
facilities, appraisal of future needs and such other information normally included in an
engineer's report, as may be requested by the department; and
d.
Be replaced by "as-built" plans when change orders result in major changes in the
facilities.
2.
Submission of revised plans, change orders, and addendums. Any deviation from the
approved plans and specifications, or use of alternate equipment, which would affect capacity,
hydraulic conditions, operating units, the functioning of the water treatment process or
distribution system, or the quality of water to be delivered will require department approval
prior to contract for alternate equipment or any construction which is affected by such change.
Revised plans and specifications, change orders, or addendums, along with pertinent
supplemental information, are to be submitted to the department for review and approval.
3.
Approval of plans. Plans and specifications reviewed by the department will be approved
only when such plans and specifications fully meet and comply with existing statutes and such
standards and guidelines as have been or may be established by the department.
4.
Compliance with plan approval. Systems shall be constructed in accordance with the plans,
specifications, and applicable change orders approved by the department. The department
reserves the right to remove from service all or any part of a system found not to be
constructed in accordance with approved plans, specifications, or change orders, or for which
plans, specifications, or change orders were not approved.
5.
Operation and maintenance manual. An operation and maintenance manual shall be
prepared and supplied by the appropriate party to new or modified water supply facilities or
systems. A copy of this manual shall be submitted to the department for review prior to initial
operation of the new or modified facility or system.