NDAC 33.1-18-01-10
Cross-connection control
Cite as N.D. Admin. Code ยง 33.1-18-01-10
All wells discharging to sources of contamination, such as livestock watering tanks, must be
provided with an approved backflow prevention device or an airgap to prevent the backflow or
siphonage of contaminants into the well. The airgap should provide a minimum vertical distance
between the potable water pipe outlet and the water surface of not less than twice the diameter of the
outlet pipe. Greater distances are preferable.
Overflow lines from stock watering tanks or other sources of contamination may not discharge to the
well.
Please consult the North Dakota state plumbing code for details.
APPENDIX
I. WELL DISINFECTION.
A. General.
Immediately after construction or repair, always disinfect with a strong chlorine solution of fifty to
one hundred milligrams per liter. Materials used in construction or repair of a well are contaminated
with dirt and bacteria and the water from a well is considered safe to drink only when laboratory
tests show that no harmful bacteria are present.
B. Procedure.
1.
Determine the amount of water in the well by referring to the table.
2.
Add the amount of chlorine compound necessary to give a dosage of fifty milligrams per liter
as indicated on the table, into the opening between the casing and the drop pipe. On new well
construction, the chlorine should be added just before installation of the pumping equipment.
a.
Chlorine tablets may be dropped in the top of the well and allowed to settle to the bottom.
b.
Deep wells with high water levels may require that chlorine solutions be added through a
hose inserted down the well casing to ensure proper diffusion of the chlorine.
Chlorine can destroy only the bacteria with which it comes in contact. Agitation of the water in
the well may be required to assure thorough mixing. After adding the chlorine, start the pump
and operate until the odor of chlorine is detected at the pump discharge.
3.
The storage and distribution system should be disinfected along with the well. Open the house
faucets and let the water run until the odor of chlorine is apparent.
4.
Allow the chlorine solution to remain in the well and distribution system for a period of
twenty-four hours. Pump the well and flush the distribution system to remove all traces of
chlorine.
5.
After pumping, collect a water sample and submit to a laboratory for a bacteriological analysis
to assure the safety of the water supply. If contamination is shown to be still present in the
water supply, the chlorination procedure should be repeated.
6.
When time does not permit well disinfection by the procedure previously described, apply to
the entire depth of the well a total volume of 50 mg/l chlorine solution at least four times
greater than the volume of water in the well. Allow the chlorine solution to remain in the well
for a period of at least two hours. Pump the well and flush the distribution system to remove all
traces of chlorine.
QUANTITY OF DISINFECTANT REQUIRED TO GIVE A DOSE OF
50 MILLIGRAMS PER LITER CHLORINE
Diameter of Well,
Spring, or Pipe, in
Inches
Gallons of Water Per
Foot of Water Depth
Ounces of Disinfectant Per 10-Ft. Depth of Water
65% Calcium
Hypochlorite
5 1/4% Sodium
Hypochlorite*
2
0.16
0.02
0.21
3
0.37
0.04
0.47
4
0.65
0.07
0.83
5
1.00
0.10
1.30
6
1.47
0.15
1.87
8
2.61
0.27
3.32
10
4.08
0.31
5.19
12
5.88
0.60
7.47
18
13.22
1.36
16.80
24
23.50
2.41
29.87
36
52.88
5.43
67.20
48
94.01
9.65
119.47
*Sodium Hypochlorite, also known as Bleach, Clorox, etc., can be purchased at most drug and
grocery stores.
One heaping tablespoon of 65% calcium hypochlorite = approximately 1/2 oz.
Six (6) 65% calcium hypochlorite tablets = approximately 1 oz.
Heavy concentrations of chlorine on or near the well screen with waters very high in iron
and/or iron bacteria may result in oxidation of iron on the well screen. Efficiency of the well
screen and well output could be reduced under such conditions.
II. LABORATORY SERVICE. Chemical and microbiological laboratory service is provided by the
department of environmental quality laboratory located at 1205 Avenue A West, Bismarck, North
Dakota. Mailing address is:
Department of Environmental Quality
Division of Laboratory Services
P.O. Box 937
Bismarck, ND 58502
Microbiological laboratory service is available from:
First District Health Unit
801 11th Avenue SW
P.O. Box 1268
Minot, ND 58702-1268
Southwestern District Health Unit
2869 Third Avenue West
Dickinson, ND 58601
Fargo Cass Public Health
Environmental Laboratory
435 14th Avenue South
Fargo, ND 58103
Grand Forks Environmental
Laboratory
503 South Fourth Street
Grand Forks, ND 58201
III. RECOMMENDED PROCEDURES.
A. Plumbness and Alignment.
Every public water well, before being officially accepted, should be tested for plumbness and
alignment. The test method to be followed should be clearly stated in the specifications. As a
minimum, a forty-foot [12.19-meter] section of pipe, or rigid dummy of the same length, having
an outside diameter not more than one-half inch [12.7 millimeters] smaller than the diameter of
the casing or hole being tested, shall move freely throughout the length of the casing or hole
to the lowest anticipated pump setting. The well should not vary from the vertical in excess of
two-thirds of the smallest inside diameter of that part of the well being tested, per one hundred
feet [30.48 meters] of depth.
B. Abandoned Wells.
For detailed procedures for abandoning wells, see Section A1-13, Sealing Abandoned Wells,
AWWA Standards for Deep Wells, A100-66 or later amendments prepared by the American
Water Works Association and the National Water Well Association.
C. Springs.
Springs should be considered as a water supply only when it is not possible to develop an
acceptable well. Springs shall be protected from entry of surface water and should be housed
in a permanent structure. Continuous chlorination of springs is recommended to assure the
bacterial purity of the water supply.
D. Continuous Chlorination of Public Well Water Supplies.
Continuous chlorination is recommended for the safeguarding of public well water supplies.
Chlorination not only assists in maintaining the bacterial purity of the water, but also eliminates
the growth of taste-and-odor-producing nuisance organisms.
E. Livestock Wells.
A check valve on the pump discharge line is not required on nonpressurized wells for livestock
use that would be damaged by freezing. The pump discharge line shall have a minimum
airgap equal to twice the effective diameter of the discharge line to prevent backflow or
siphonage into the well to prevent contamination of the well.
IV. MEASUREMENT OF WATER WELL DRAWDOWN AND SPECIFIC CAPACITY.
Pumping tests of water supply wells can serve many purposes. Properly planned and conducted
tests will reveal information about the performance and efficiency of the well being pumped. In
addition, from the data obtained, calculations can be made which interpret ground water aquifer
performance.
Measuring each well for pump and well yield, depth to water level, drawdown, and specific capacity
should be done on a routine basis. These test results should be compared with previous tests to
estimate current well and/or aquifer conditions.
A. Terminology.
It is important to understand the meaning of the terms used relating to the pumping test. Some
of these terms are as follows:
1.
Static Water Level. This is the level at which water stands in the well when no water is
being pumped. It is generally expressed as the distance in feet from the ground surface
to the water level in the well.
2.
Pumping Level. This is the level at which water stands in the well when pumping is in
progress. The pumping level may also be referred to as the dynamic water level.
3.
Drawdown. When a well is pumped, the water level in the vicinity of the well will be
lowered. Drawdown is the difference, measured in feet, between the static water level
and the pumping level.
4.
Well Yield. The well yield is the volume of water per unit of time discharged from a well
either by pumping or by free flow.
5.
Specific Capacity. Specific capacity of the well is its yield per unit of drawdown, usually
expressed as gallons per minute (gpm) per foot of drawdown.
B. Determination of Depth to Water Level.
1.
Wetted Tape Method. The wetted tape method will accurately measure the depth to water
in a well and can be used for depths up to one hundred feet [30.5 meters] or more.
Attach a lead weight to the end of a steel measuring tape, if needed. Wipe dry the lower
three or four feet [.91 or 1.22 meters] of the tape and coat with carpenter's chalk. Lower
the tape into the well through the air vent or other opening until part of the chalked
section is below water. Continue to lower the tape until the next even foot mark can be
held exactly at a reference point and record the number of feet indicated. The tape is
then removed from the well and note is made of the footage of chalked section washed
away by the water. Subtract this reading from the reading obtained at the top reference
point. The difference in these readings is the depth from the reference point to the water
level.
2.
Air Line Method. The air line method measures depth to water level by determining the
air pressure required to push all of the water out of a submerged tube of known length.
The air line consists of a one-fourth inch [6.35 millimeters] pipe, copper or plastic tubing,
extending from the top of the well to a point several feet below the lowest anticipated
water level. To avoid turbulence near the intake of the pump, the lower end of the air line
should be at least five feet [1.52 meters] above or below the point where water enters the
pump. The exact length of the air line must be known or should be measured as it is
placed in the well. Make all joints airtight with white lead or piping compound. The upper
end of the tube is fitted with suitable connections for an air gauge, a tire valve, and an air
pump.
Pump the air into the line until the gauge pressure is constant. This indicates that all of
the water has been expelled from the tube. The gauge reading shows the pressure
necessary to support a column of water of a height equal to the depth the tube was
submerged. If the gauge indicates feet of water, then it shows directly the submerged
length of the line in feet. Subtracting the submerged length from the total length of the air
line gives the depth to static water level. Gauges calibrated in pounds per square inch
(psi) may be converted to feet of water by multiplying by 2.31.
C. Determination of Drawdown.
Example:
Depth to water before pumping
=
100 feet
Depth to water after pumping
=
125 feet
Drawdown
=
Depth after pumping - depth before pumping
=
125 feet - 100 feet = 25 feet
First, determine the static water level. Second, after the well has achieved a constant pumping
rate or yield, measure the depth to the water level. The difference of these readings before
and after pumping the well at a specific rate is measured in feet and recorded as feet of
drawdown.
D. Determination of Specific Capacity.
Example:
Yield of well
=
160 gpm
Drawdown
=
20 feet
Specific capacity
=
160/20
=
8 gpm per foot of
drawdown
Specific capacity is calculated by dividing the yield of the well in gallons per minute by the
drawdown. Both measurements shall be taken at the same time.
E. Interpretation of Water Well Problems.
With proper records of water well tests, well problems can be interpreted. Some rules to follow
are:
1.
If the output of the well (gpm) drops, the drawdown decreases, and the specific capacity
remains the same, the problem is most likely the pump.
2.
If the output of the well (gpm) drops, the static water level remains the same, the
drawdown increases and the specific capacity decreases, the well may be plugging. Acid
clean the well when the specific capacity drops about twenty-five percent.
3.
If the output of the well (gpm) drops and the static water level is declining, the aquifer
may be depleting.
V. GENERAL POLICY - GEOTHERMAL ENERGY.
Geothermal energy is the renewable thermal energy of the earth or ground water. Using this form of
energy for heating and cooling purposes has become increasingly popular for both commercial and
residential purposes. Geothermal regulations are administered by the North Dakota Geological
Survey, and require a permit from the State Geologist prior to the installation of a geothermal
system. All construction of geothermal energy systems must comply with the rules contained in
chapter 43-02-07, Geothermal Energy Production. These regulations cover both vertical-loop and
horizontal-loop systems. Installers should contact the North Dakota Geological Survey for more
information regarding installation of geothermal energy systems.
Because of the potential for contamination of drinking water systems and aquifers, and the pollution
of surface waters, the department provides the following guidance for users of geothermal energy.
This policy relates primarily to private individual systems. Commercial and industrial projects should
be constructed only after consultation with the department regarding water supply and disposal
requirements and the North Dakota Geological Survey regarding construction permitting
requirements.
1.
The department encourages the conservation of ground water resources, therefore,
closed-loop geothermal systems are recommended. Closed-loop systems also have fewer
maintenance problems. If an open-loop system is constructed, whenever possible, the water
should be reinjected into the supply aquifer or used for other beneficial purposes such as
irrigation or stock watering.
2.
Users of open-loop geothermal energy systems must be aware of the scale-forming or
corrosive nature of some of the highly mineralized water in North Dakota. Some ground water
supplies may require treatment prior to use, or serious problems with operation of the heat
exchange system can develop. Chemicals used for cleaning the heat exchange system, and
the material removed through cleaning, may not be suitable for discharge to the storm sewer
system. Problems with the development of scale will often reduce the volume of water that can
be disposed into injection wells.
3.
All supply and disposal wells shall be constructed to comply with department rules, chapter
33-18-01, "Water Well Construction and Water Well Pump Installation". The geothermal
system should be constructed to eliminate all sources of contamination to the water supply
system and the ground water aquifer.
4.
If municipal water supply systems are to be used as a source of geothermal energy, an
approved backflow prevention device shall be used to separate the geothermal energy from
the public water supply system.
5.
To protect the drinking water supply, heat exchangers, unless otherwise permitted under the
North Dakota state plumbing code, shall be of double-wall construction with a space between
the two walls which is vented to the atmosphere.
6.
Geothermal energy systems shall not discharge water to either municipal drinking water or
sanitary sewer systems. Discharge to the municipal drinking water system is a
cross-connection and could result in chemical and/or microbiological contamination of the
system. Nearly all cities in the state have sewer use ordinances specifically prohibiting the
connection of clear water discharges to the sewer system.
7.
Geothermal energy systems may discharge to municipal storm sewer systems with approval
of the municipality, and if the discharge water is compatible with the waters of the receiving
stream. Degradation of surface waters by discharges from geothermal energy systems will not
be allowed.
8.
If water is to be reinjected into the ground water system, the discharge should be made to a
similar or inferior quality aquifer.
9.
Highly mineralized or saline waters, such as from the Dakota formation, should be returned to
those aquifers if secondary use is not possible.
10.
Evaporation ponds, which do not discharge, may be used as a means of disposal where other
methods of disposal are not feasible.
11.
Disposal permits under the Underground Injection Control Program or the National Pollutant
Discharge Elimination System Regulations may be required. Users of geothermal energy
systems should contact the department to determine whether a permit is required for their
installation.
VI. ABANDONMENT OF TEST HOLES, PARTIALLY COMPLETED WELLS, AND COMPLETED
WELLS.
Reprinted from AWWA Standard for Water Wells, A100-84, by permission. Copyright ยฉ 1984,
American Water Works Association.
Section 1.1 - General
The recommendations contained in this appendix pertain to wells and test holes in
consolidated and unconsolidated formations. Each sealing job should be considered as an
individual problem, and methods and materials should be determined only after carefully
considering the objectives outlined in the standard.
Section 1.2 - Wells in Unconsolidated Formations
Normally, abandoned wells extending only into consolidated formations near the surface and
containing water under water-table conditions can be adequately sealed by filling with concrete,
grout, neat cement, clay, or clay and sand. In the event that the water-bearing formation consists of
coarse gravel and producing wells are located nearby, care must be taken to select sealing
materials that will not affect the producing wells. Concrete may be used if the producing wells can
be shut down for a sufficient time to allow the concrete to set. Clean, disinfected sand or gravel
may also be used as fill material opposite the water-bearing formation. The remainder of the well,
especially the upper portion, should be filled with clay, concrete, grout, or neat cement to exclude
surface water. The latter method, using clay as the upper sealing material, is especially applicable
to large-diameter abandoned wells.
In gravel-packed, gravel-envelope, or other wells in which coarse material has been added
around the inner casing to within twenty to thirty feet [6.1 to 9.1 meters] of the surface, sealing
outside the casing is very important. Sometimes this sealing may require removal of the gravel or
perforation of the casing.
Section 1.4 - Wells in Noncreviced Rock Formations
Abandoned wells encountering noncreviced sandstone or other water-bearing consolidated
formations below the surface deposits may be satisfactorily sealed by filling the entire depth with
clay, provided there is no movement of water in the well. Clean sand, disinfected if other producing
wells are nearby, may also be used through the sandstone up to a point ten to twenty feet [3.0 to
6.1 meters] below the bottom of the casing. The upper portion of this type of well should be filled
with concrete, neat cement, grout, or clay to provide an effective seal against entrance of surface
water. If there is an appreciable amount of upward flow, pressure cementing or mudding may be
advisable.
Section 1.5 - Multiple Aquifer Wells
Some special problems may develop in sealing wells extending into more than one aquifer.
These wells should be filled and sealed in such a way that exchange of water from one aquifer to
another is prevented. If no appreciable movement of water is encountered, filling with concrete,
neat cement, grout, or alternate layers of these materials and sand will prove satisfactory. When
velocities are high, the procedures outlined in section 1.6 are recommended. If alternate concrete
plugs or bridges are used, they should be placed in known nonproducing horizons or, if locations of
the nonproducing horizons are not known, at frequent intervals. Sometimes when the casing is not
grouted or the formation is nocaving, it may be necessary to break, slit, or perforate the casing to fill
any annular space on the outside.
Section 1.6 - Wells With Artesian Flow
The sealing of abandoned wells that have a movement of water between aquifers or to the
surface requires special attention. Frequently the movements of water may be sufficient to make
sealing by gravity placement of concrete, cement grout, neat cement, clay, or sand impractical. In
such flow, if preshaped or precast plugs are used, they should be several times longer than the
diameter of the well, to prevent tilting.
Since it is very important in wells of this type to prevent circulation between formations or loss
of water to the surface or to the annular space outside the casing, it is recommended that pressure
cementing, using the minimum quantity of water that will permit handling, be used. The use of
wells, large stone aggregate (not more than one-third of the diameter of the hole), lead wool, steel
shavings, a well packer, or a wood or cast-lead plug or bridge will be needed to restrict the flow and
thereby permit the gravity placement of sealing material above the formation producing the
pressure mudding instead of this process if sometimes permissible.
In wells which the hydrostatic head producing flow to the surface is low, the movement of
water may be arrested by extending the well casing to an elevation above the artesian-pressure
surface. Previously described sealing methods suitable to the geologic conditions can then be
used.
Section 1.7 - Sealing Materials
A number of materials that can be used for sealing wells satisfactorily, including concrete,
cement grout, neat cement, clay, sand, or combinations of these materials, are mentioned in this
appendix. Each material has certain characteristics and distinctive properties; therefore, one
material may be especially suited for doing a particular job. The selection of the material must be
based on the construction of the well, the nature of the formations penetrated, the material and
equipment available, the location of the well with respect to possible sources of contamination, and
the cost of doing the work.
Concrete is generally used for filling the upper part of the well or water-bearing formations, for
plugging short sections of casings, or for filling large-diameter wells. Its use is cheaper than neat
cement or grout, and it makes a stronger plug or seal. However, concrete will not penetrate seams,
crevices, or interstices. Furthermore, if not properly placed, the aggregate is likely to separate from
the cement.
Cement grout or neat cement and water are far superior for sealing small openings, for
penetrating any annular space outside of casings, and for filling voids in the surrounding formation.
When applied under pressure, they are strongly favored for sealing wells under artesian pressure
or those encountering more than one aquifer. Neat cement is generally preferred to grout because
it does not separate.
Clay, as a heavy mud-laden or special clay fluid applied under pressure, has most of the
advantages of cement grout. Its use is preferred by some competent authorities, particularly for
sealing artesian wells. Others feel that it may, under some conditions, eventually be carried away
into the surrounding formations.
Clay in a relatively dry state, clay and sand, or sand alone may be used advantageously as
sealing materials, particularly under water-table conditions where diameters are large, depths are
great, formations are caving, and there is no need for achieving penetration of openings in casings,
liners, or formations, or for obtaining a watertight seal at any given spot.
Frequently combinations of these materials are necessary. The more expensive materials are
used when strength, penetration, or watertightness are needed. The less expensive materials are
used for the remainder of the well. Cement grout or neat cement is now being mixed with bentonite
clays and various aggregates. Superior results and lower cost are claimed for such mixtures.
ASTM STANDARD A 53*
Welded and Seamless Steel
Pipe Schedule 40 - Standard Weight
Nominal Size
(Inches)
External
Diameter
(Inches)
Internal
Diameter
(Inches)
Wall Thickness
(Inches)
Weight Per Foot (lb)
Plain End
Threads and
Couplings
1 1/4
1.660
1.380
0.140
2.27
2.28
1 1/2
1.900
1.610
0.145
2.72
2.73
2
2.375
2.067
0.154
3.65
3.68
2 1/2
2.875
2.469
0.203
5.79
5.82
3
3.500
3.068
0.216
7.58
7.62
3 1/2
4.000
3.568
0.226
9.11
9.20
4
4.500
4.026
0.237
10.79
10.89
5
5.563
5.047
0.258
14.62
14.81
6
6.625
6.065
0.280
18.97
19.18
8
8.625
7.981
0.322
28.55
29.35
10
10.750
10.020
0.365
40.48
41.85
12
12.750
12.000
0.375
49.56
51.15
14
14.000
13.250
0.375
54.57
57.00
16
16.000
15.250
0.375
62.58
65.30
18
18.000
17.250
0.375
70.59
73.00
20
20.000
19.250
0.375
78.60
81.00
22
22.000
21.000
0.500
114.81
24
24.000
23.000
0.500
125.49
26
26.000
25.000
0.500
136.17
28
28.000
27.000
0.500
146.85
30
30.000
29.000
0.500
157.53
32
32.000
31.000
0.500
168.21
34
34.000
33.000
0.500
178.89
36
36.000
35.000
0.500
189.57
ASTM STANDARD A 589*
Water-Well Reamed and Drifted Pipe
Nominal Size
(Inches)
External
Diameter
(Inches)
Internal
Diameter
(Inches)
Wall Thickness
(Inches)
Weight Per Foot (lb)
Plain End
Threads and
Couplings
1 1/4
1.660
1.380
0.140
2.27
2.30
1 1/2
1.900
1.610
0.145
2.72
2.75
2
2.375
2.067
0.154
3.65
3.75
2 1/2
2.875
2.469
0.203
5.79
5.90
3
3.500
3.068
0.216
7.58
7.70
3 1/2
4.000
3.548
0.226
9.11
9.25
4
4.500
4.026
0.237
10.79
11.00
5
5.563
5.047
0.258
14.62
15.00
6
6.625
6.065
0.280
18.97
19.45
8
8.625
7.981
0.322
28.55
29.35
10
10.750
10.020
0.365
40.48
41.85
12
12.750
12.000
0.375
49.56
51.15
*From "1973 Annual Book of ASTM Standards"