NDAC 33.1-24-02-188
Standards - Pumps and valves in heavy liquid service, pressure relief devices in light liquid or heavy liquid service, and flanges and other connectors
Cite as N.D. Admin. Code § 33.1-24-02-188
1.
Pumps and valves in heavy liquid service, pressure relief devices in light liquid or heavy liquid
service, and flanges and other connectors must be monitored within five days by the method
specified in subsection 2 of section 33.1-24-02-193 if evidence of a potential leak is found by
visual, audible, olfactory, or any other detection method.
2.
If an instrument reading of ten thousand parts per million or greater is measured, a leak is
detected.
3.
Timeframe.
a.
When a leak is detected, it must be repaired as soon as practicable, but not later than
fifteen calendar days after it is detected, except as provided in section 33.1-24-02-189.
b.
The first attempt at repair must be made no later than five calendar days after each leak
is detected.
4.
First attempts at repair include the best practices described under subsection 5 of section
33.1-24-02-187.
5.
Any connector that is inaccessible or is ceramic or ceramic-lined (for example, porcelain,
glass, or glass-lined) is exempt from the monitoring requirements of subsection 1 and from the
recordkeeping requirements of section 33.1-24-02-194.