NDAC 33.1-24-02-206
Standards - Containers
Cite as N.D. Admin. Code § 33.1-24-02-206
1.
The provisions of this section apply to the control of air pollutant emissions from containers for
which subsection 2 of section 33.1-24-02-202 references the use of this section for such air
emission control.
2.
General requirements.
a.
The remanufacturer or other person that stores or treats the hazardous secondary
material shall control air pollutant emissions from each container subject to this section in
accordance with the following requirements, as applicable to the container.
(1)
For a container having a design capacity greater than one-tenth meters3 (3.5 feet3)
and less than or equal to forty-six one-hundredths meters3 (16.25 feet3), the
remanufacturer or other person that stores or treats the hazardous secondary
material shall control air pollutant emissions from the container in accordance with
the container level 1 standards specified in subsection 3.
(2)
For a container having a design capacity greater than forty-six one-hundredths
meters3 (16.25 feet3) which is not in light material service, the remanufacturer or
other person that stores or treats the hazardous secondary material shall control air
pollutant emissions from the container in accordance with the container level 1
standards specified in subsection 3.
(3)
For a container having a design capacity greater than forty-six one-hundredths
meters3 (16.25 feet3) which is in light material service, the remanufacturer or other
person that stores or treats the hazardous secondary material shall control air
pollutant emissions from the container in accordance with the container level 2
standards specified in subsection 4.
3.
Container level 1 standards.
a.
A container using container level 1 controls is one of the following:
(1)
A container that meets the applicable United States department of transportation
regulations on packaging hazardous materials for transportation as specified in
subsection 6.
(2)
A container equipped with a cover and closure devices that form a continuous
barrier over the container openings such that when the cover and closure devices
are secured in the closed position there are no visible holes, gaps, or other open
spaces into the interior of the container. The cover may be a separate cover
installed on the container (for example, a lid on a drum or a suitably secured tarp on
a roll-off box) or may be an integral part of the container structural design (for
example, a "portable tank" or bulk cargo container equipped with a screw-type cap).
(3)
An open-top container in which an organic-vapor suppressing barrier is placed on or
over the hazardous secondary material in the container such that no hazardous
secondary material is exposed to the atmosphere. One example of such a barrier is
application of a suitable organic-vapor suppressing foam.
b.
A container used to meet the requirements of paragraph 2 or 3 of subdivision a must be
equipped with covers and closure devices, as applicable to the container, which are
composed of suitable materials to minimize exposure of the hazardous secondary
material to the atmosphere and to maintain the equipment integrity, for as long as the
container is in service. Factors to be considered in selecting the materials of construction
and designing the cover and closure devices include: organic vapor permeability; the
effects of contact with the hazardous secondary material or its vapor managed in the
container; the effects of outdoor exposure of the closure device or cover material to wind,
moisture, and sunlight; and the operating practices for which the container is intended to
be used.
c.
If a hazardous secondary material is in a container using container level 1 controls, the
remanufacturer or other person that stores or treats the hazardous secondary material
shall install all covers and closure devices for the container, as applicable to the
container, and secure and maintain each closure device in the closed position except as
follows:
(1)
Opening of a closure device or cover is allowed for the purpose of adding
hazardous secondary material or other material to the container as follows:
(a)
In the case when the container is filled to the intended final level in one
continuous operation, the remanufacturer or other person that stores or treats
the hazardous secondary material promptly shall secure the closure devices in
the closed position and install the covers, as applicable to the container, upon
conclusion of the filling operation.
(b)
In the case when discrete quantities or batches of material intermittently are
added to the container over a period of time, the remanufacturer or other
person that stores or treats the hazardous secondary material promptly shall
secure the closure devices in the closed position and install covers, as
applicable to the container, upon either the container being filled to the
intended final level; the completion of a batch loading after which no additional
material will be added to the container within fifteen minutes; the person
performing the loading operation leaving the immediate vicinity of the
container; or the shutdown of the process generating the hazardous secondary
material being added to the container, whichever condition occurs first.
(2)
Opening of a closure device or cover is allowed for the purpose of removing
hazardous secondary material from the container as follows:
(a)
For the purpose of meeting the requirements of this section, an empty
hazardous secondary material container may be open to the atmosphere at
any time (for example, covers and closure devices on such a container are not
required to be secured in the closed position).
(b)
In the case when discrete quantities or batches of material are removed from
the container, but the container is not an empty hazardous secondary material
container, the remanufacturer or other person that stores or treats the
hazardous secondary material promptly shall secure the closure devices in the
closed position and install covers, as applicable to the container, upon the
completion of a batch removal after which no additional material will be
removed from the container within fifteen minutes or the person performing the
unloading operation leaves the immediate vicinity of the container, whichever
condition occurs first.
(3)
Opening of a closure device or cover is allowed when access inside the container is
needed to perform routine activities other than transfer of hazardous secondary
material. Examples of such activities include those times when a worker needs to
open a port to measure the depth of or sample the material in the container, or when
a worker needs to open a manhole hatch to access equipment inside the container.
Following completion of the activity, the remanufacturer or other person that stores
or treats the hazardous secondary material promptly shall secure the closure device
in the closed position or reinstall the cover, as applicable to the container.
(4)
Opening of a spring-loaded pressure-vacuum relief valve, conservation vent, or
similar type of pressure relief device which vents to the atmosphere is allowed
during normal operations for the purpose of maintaining the internal pressure of the
container in accordance with the container design specifications. The device must
be designed to operate with no detectable organic emissions when the device is
secured in the closed position. The settings at which the device opens must be
established such that the device remains in the closed position whenever the
internal pressure of the container is within the internal pressure operating range
determined by the remanufacturer or other person that stores or treats the
hazardous secondary material based on container manufacturer recommendations,
applicable regulations, fire protection and prevention codes, standard engineering
codes and practices, or other requirements for the safe handling of flammable,
ignitable, explosive, reactive, or hazardous materials. Examples of normal operating
conditions that may require these devices to open are during those times when the
internal pressure of the container exceeds the internal pressure operating range for
the container as a result of loading operations or diurnal ambient temperature
fluctuations.
(5)
Opening of a safety device, as defined in section 33.1-24-02-201, is allowed at any
time conditions require doing so to avoid an unsafe condition.
d.
The remanufacturer or other person that stores or treats the hazardous secondary
material using containers with container level 1 controls shall inspect the containers and
their covers and closure devices as follows:
(1)
In the case when a hazardous secondary material already is in the container at the
time the remanufacturer or other person that stores or treats the hazardous
secondary material first accepts possession of the container at the facility and the
container is not emptied within twenty-four hours after the container is accepted at
the facility (for example, is not an empty hazardous secondary material container)
the remanufacturer or other person that stores or treats the hazardous secondary
material visually shall inspect the container and its cover and closure devices to
check for visible cracks, holes, gaps, or other open spaces into the interior of the
container when the cover and closure devices are secured in the closed position.
The container visual inspection must be conducted on or before the date that the
container is accepted at the facility (for example, the date the container becomes
subject to the container standards in sections 33.1-24-02-200 through
33.1-24-02-214).
(2)
In the case when a container used for managing hazardous secondary material
remains at the facility for a period of one year or more, the remanufacturer or other
person that stores or treats the hazardous secondary material visually shall inspect
the container and its cover and closure devices initially and thereafter, at least once
every twelve months, to check for visible cracks, holes, gaps, or other open spaces
into the interior of the container when the cover and closure devices are secured in
the closed position. If a defect is detected, the remanufacturer or other person that
stores or treats the hazardous secondary material shall repair the defect in
accordance with the requirements of paragraph 3.
(3)
When a defect is detected for the container, cover, or closure devices, the
remanufacturer or other person that stores or treats the hazardous secondary
material shall make first efforts at repair of the defect no later than twenty-four hours
after detection and repair must be completed as soon as possible but no later than
five calendar days after detection. If repair of a defect cannot be completed within
five calendar days, the hazardous secondary material must be removed from the
container and the container may not be used to manage hazardous secondary
material until the defect is repaired.
e.
The remanufacturer or other person that stores or treats the hazardous secondary
material shall maintain at the facility a copy of the procedure used to determine that
containers with capacity of forty-six one-hundredths meters3 (16.25 feet3) or greater,
which do not meet applicable department of transportation regulations as specified in
subsection 6, are not managing hazardous secondary material in light material service.
4.
Container level 2 standards.
a.
A container using container level 2 controls is one of the following:
(1)
A container that meets the applicable United States department of transportation
regulations on packaging hazardous materials for transportation as specified in
subsection 6.
(2)
A container that operates with no detectable organic emissions as defined in section
33.1-24-02-201 and determined in accordance with the procedure specified in
subsection 7.
(3)
A container that has been demonstrated within the preceding twelve months to be
vapor-tight by using 40 CFR part 60, appendix A, Method 27 in accordance with the
procedure specified in subsection 8.
b.
Transfer of hazardous secondary material in or out of a container using container level 2
controls must be conducted in such a manner as to minimize exposure of the hazardous
secondary material to the atmosphere, to the extent practical, considering the physical
properties of the hazardous secondary material and good engineering and safety
practices for handling flammable, ignitable, explosive, reactive, or other hazardous
materials. Examples of container loading procedures that the department considers to
meet the requirements of this subdivision include using any one of the following: a
submerged-fill pipe or other submerged-fill method to load liquids into the container; a
vapor-balancing system or a vapor-recovery system to collect and control the vapors
displaced from the container during filling operations; or a fitted opening in the top of a
container through which the hazardous secondary material is filled and subsequently
purging the transfer line before removing it from the container opening.
c.
Whenever a hazardous secondary material is in a container using container level 2
controls, the remanufacturer or other person that stores or treats the hazardous
secondary material shall install all covers and closure devices for the container, and
secure and maintain each closure device in the closed position except as follows:
(1)
Opening of a closure device or cover is allowed for the purpose of adding
hazardous secondary material or other material to the container as follows:
(a)
In the case when the container is filled to the intended final level in one
continuous operation, the remanufacturer or other person that stores or treats
the hazardous secondary material promptly shall secure the closure devices in
the closed position and install the covers, as applicable to the container, upon
conclusion of the filling operation.
(b)
In the case when discrete quantities or batches of material intermittently are
added to the container over a period of time, the remanufacturer or other
person that stores or treats the hazardous secondary material shall promptly
secure the closure devices in the closed position and install covers, as
applicable to the container, upon either the container being filled to the
intended final level; the completion of a batch loading after which no additional
material will be added to the container within fifteen minutes; the person
performing the loading operation leaving the immediate vicinity of the
container; or the shutdown of the process generating the material being added
to the container, whichever condition occurs first.
(2)
Opening of a closure device or cover is allowed for the purpose of removing
hazardous secondary material from the container as follows:
(a)
For the purpose of meeting the requirements of this section, an empty
hazardous secondary material container may be open to the atmosphere at
any time (for example, covers and closure devices are not required to be
secured in the closed position on an empty container).
(b)
In the case when discrete quantities or batches of material are removed from
the container, but the container is not an empty hazardous secondary materials
container, the remanufacturer or other person that stores or treats the
hazardous secondary material promptly shall secure the closure devices in the
closed position and install covers, as applicable to the container, upon the
completion of a batch removal after which no additional material will be
removed from the container within fifteen minutes or the person performing the
unloading operation leaves the immediate vicinity of the container, whichever
condition occurs first.
(3)
Opening of a closure device or cover is allowed when access inside the container is
needed to perform routine activities other than transfer of hazardous secondary
material. Examples of such activities include those times when a worker needs to
open a port to measure the depth of or sample the material in the container, or when
a worker needs to open a manhole hatch to access equipment inside the container.
Following completion of the activity, the remanufacturer or other person that stores
or treats the hazardous secondary material promptly shall secure the closure device
in the closed position or reinstall the cover, as applicable to the container.
(4)
Opening of a spring-loaded, pressure-vacuum relief valve, conservation vent, or
similar type of pressure relief device which vents to the atmosphere is allowed
during normal operations for the purpose of maintaining the internal pressure of the
container in accordance with the container design specifications. The device must
be designed to operate with no detectable organic emission when the device is
secured in the closed position. The settings at which the device opens must be
established such that the device remains in the closed position whenever the
internal pressure of the container is within the internal pressure operating range
determined by the remanufacturer or other person that stores or treats the
hazardous secondary material based on container manufacturer recommendations,
applicable regulations, fire protection and prevention codes, standard engineering
codes and practices, or other requirements for the safe handling of flammable,
ignitable, explosive, reactive, or hazardous materials. Examples of normal operating
conditions that may require these devices to open are during those times when the
internal pressure of the container exceeds the internal pressure operating range for
the container as a result of loading operations or diurnal ambient temperature
fluctuations.
(5)
Opening of a safety device, as defined in section 33.1-24-02-201, is allowed at any
time conditions require doing so to avoid an unsafe condition.
d.
The remanufacturer or other person that stores or treats the hazardous secondary
material using containers with container level 2 controls shall inspect the containers and
their covers and closure devices as follows:
(1)
In the case when a hazardous secondary material already is in the container at the
time the remanufacturer or other person that stores or treats the hazardous
secondary material first accepts possession of the container at the facility and the
container is not emptied within twenty-four hours after the container is accepted at
the facility (for example, is not an empty hazardous secondary material container),
the remanufacturer or other person that stores or treats the hazardous secondary
material visually shall inspect the container and its cover and closure devices to
check for visible cracks, holes, gaps, or other open spaces into the interior of the
container when the cover and closure devices are secured in the closed position.
The container visual inspection shall be conducted on or before the date that the
container is accepted at the facility (for example, the date the container becomes
subject to the container standards in sections 33.1-24-02-200 through
33.1-24-02-214).
(2)
In the case when a container used for managing hazardous secondary material
remains at the facility for a period of one year or more, the remanufacturer or other
person that stores or treats the hazardous secondary material visually shall inspect
the container and its cover and closure devices initially and thereafter, at least once
every twelve months, to check for visible cracks, holes, gaps, or other open spaces
into the interior of the container when the cover and closure devices are secured in
the closed position. If a defect is detected, the remanufacturer or other person that
stores or treats the hazardous secondary material shall repair the defect in
accordance with the requirements of paragraph 3.
(3)
When a defect is detected for the container, cover, or closure devices, the
remanufacturer or other person that stores or treats the hazardous secondary
material must make first efforts at repair of the defect no later than twenty-four hours
after detection, and repair shall be completed as soon as possible but no later than
five calendar days after detection. If repair of a defect cannot be completed within
five calendar days, then the hazardous secondary material must be removed from
the container and the container may not be used to manage hazardous secondary
material until the defect is repaired.
5.
Container level 3 standards.
a.
A container using container level 3 controls is one of the following:
(1)
A container that is vented directly through a closed-vent system to a control device
in accordance with the requirements of paragraph 2 of subdivision b.
(2)
A container that is vented inside an enclosure which is exhausted through a
closed-vent system to a control device in accordance with the requirements of
paragraphs 1 and 2 of subdivision b.
b.
The remanufacturer or other person that stores or treats the hazardous secondary
material shall meet the following requirements, as applicable to the type of air emission
control equipment selected by the remanufacturer or other person that stores or treats
the hazardous secondary material:
(1)
The container enclosure must be designed and operated in accordance with the
criteria for a permanent total enclosure as specified in "Procedure T - Criteria for
and Verification of a Permanent or Temporary Total Enclosure" under 40 CFR
52.741, appendix B. The enclosure may have permanent or temporary openings to
allow worker access; passage of containers through the enclosure by conveyor or
other mechanical means; entry of permanent mechanical or electrical equipment; or
direct airflow into the enclosure. The remanufacturer or other person that stores or
treats the hazardous secondary material shall perform the verification procedure for
the enclosure as specified in Section 5.0 to "Procedure T - Criteria for and
Verification of a Permanent or Temporary Total Enclosure" initially when the
enclosure is first installed and, thereafter, annually.
(2)
The closed-vent system and control device must be designed and operated in
accordance with the requirements of section 33.1-24-02-207.
c.
Safety devices, as defined in section 33.1-24-02-201, may be installed and operated as
necessary on any container, enclosure, closed-vent system, or control device used to
comply with the requirements of subdivision a.
d.
Remanufacturers or other persons that store or treat the hazardous secondary material
using container level 3 controls in accordance with the provisions of sections
33.1-24-02-200 through 33.1-24-02-214 shall inspect and monitor the closed-vent
systems and control devices as specified in section 33.1-24-02-207.
e.
Remanufacturers or other persons that store or treat the hazardous secondary material
that use container level 3 controls in accordance with the provisions of sections
33.1-24-02-200 through 33.1-24-02-214 shall prepare and maintain the records specified
in subsection 4 of section 33.1-24-02-209.
f.
Transfer of hazardous secondary material in or out of a container using container level 3
controls must be conducted in such a manner as to minimize exposure of the hazardous
secondary material to the atmosphere, to the extent practical, considering the physical
properties of the hazardous secondary material and good engineering and safety
practices for handling flammable, ignitable, explosive, reactive, or other hazardous
materials. Examples of container loading procedures that the department considers to
meet the requirements of this subdivision include using any one of the following: a
submerged-fill pipe or other submerged-fill method to load liquids into the container; a
vapor-balancing system or a vapor-recovery system to collect and control the vapors
displaced from the container during filling operations; or a fitted opening in the top of a
container through which the hazardous secondary material is filled and subsequently
purging the transfer line before removing it from the container opening.
6.
For the purpose of compliance with paragraph 1 of subdivision a of subsection 3 or
paragraph 1 of subdivision a of subsection 4, containers must be used that meet the
applicable United States department of transportation regulations on packaging hazardous
materials for transportation as follows:
a.
The container meets the applicable requirements specified in 49 CFR part 178 -
Specifications for Packaging or 49 CFR part 179 - Specifications for Tank Cars.
b.
Hazardous secondary material is managed in the container in accordance with the
applicable requirements specified in 49 CFR part 107, subpart B - Special Permits;
49 CFR part 172 - Hazardous Materials Table, Special Provisions, Hazardous Materials
Communications, Emergency Response Information, Training Requirements, and
Security Plans; 49 CFR part 173 - Shippers - General Requirements for Shipments and
Packaging; and 49 CFR part 180 - Continuing Qualification and Maintenance of
Packagings.
c.
For the purpose of complying with sections 33.1-24-02-200 through 33.1-24-02-214, no
exceptions to the 49 CFR part 178 or part 179 regulations are allowed.
7.
To determine compliance with the no detectable organic emissions requirement of
paragraph 2 of subdivision a of subsection 4, the procedure specified in subsection 4 of
section 33.1-24-02-203 must be used.
a.
Each potential leak interface (for example, a location where organic vapor leakage could
occur) on the container, its cover, and associated closure devices, as applicable to the
container, must be checked. Potential leak interfaces that are associated with containers
include: the interface of the cover rim and the container wall; the periphery of any
opening on the container or container cover and its associated closure device; and the
sealing seat interface on a spring-loaded pressure-relief valve.
b.
The test must be performed when the container is filled with a material having a volatile
organic concentration representative of the range of volatile organic concentrations for
the hazardous secondary materials expected to be managed in this type of container.
During the test, the container cover and closure devices must be secured in the closed
position.
8.
Procedure for determining a container to be vapor-tight using Method 27 of 40 CFR part 60,
appendix A for the purpose of complying with paragraph 3 of subdivision a of subsection 4.
a.
The test must be performed in accordance with Method 27 of 40 CFR part 60,
appendix A.
b.
A pressure measurement device must be used that has a precision of plus or minus two
and five-tenths millimeters [0.1 inch] water and that is capable of measuring above the
pressure at which the container is to be tested for vapor tightness.
c.
If the test results determined by Method 27 indicate the container sustains a pressure
change less than or equal to seven hundred fifty pascals within five minutes after it is
pressurized to a minimum of four thousand five hundred pascals, the container is
determined to be vapor-tight.