NDAC 33.1-24-05-106
Containment and detection of releases
Cite as N.D. Admin. Code ยง 33.1-24-05-106
1.
In order to prevent the release of hazardous waste or hazardous constituents to the
environment, secondary containment that meets the requirements of this section must be
provided (except as provided in subsections 6 and 7):
a.
For all new and existing tank systems or components, prior to their being put into service.
b.
For tank systems that store or treat materials that become hazardous wastes, within two
years of the hazardous waste listing, or when the tank system has reached fifteen years
of age, whichever comes later.
2.
Secondary containment systems must be:
a.
Designed, installed, and operated to prevent any migration of wastes or accumulated
liquid out of the system to the soil, ground water, or surface water at any time during the
use of the tank system; and
b.
Capable of detecting and collecting releases and accumulated liquids until the collected
material is removed.
3.
To meet the requirements of subsection 2, secondary containment systems must be at a
minimum:
a.
Constructed of or lined with materials that are compatible with the waste or wastes to be
placed in the tank system and must have sufficient strength and thickness to prevent
failure owing to pressure gradients (including static head and external hydrological
forces), physical contact with the waste to which it is exposed, climatic conditions, stress
of installation, and the stress of daily operation (including stresses from nearby vehicular
traffic);
b.
Placed on a foundation or base capable of providing support to the secondary
containment system, resistance to pressure gradients above and below the system, and
capable of preventing failure due to settlement, compression, or uplift;
c.
Provided with a leak-detection system that is designed and operated so that it will detect
the failure of either the primary or secondary containment structure or the presence of
any release of hazardous waste or accumulated liquid in the secondary containment
system within twenty-four hours, or at the earliest practicable time if the owner or
operator can demonstrate to the department that the existing detection technologies or
site conditions will not allow detection of a release within twenty-four hours; and
d.
Sloped or otherwise designed or operated to drain and remove liquids resulting from
leaks, spills, or precipitation. Spilled or leaked waste and accumulated precipitation must
be removed from the secondary containment system within twenty-four hours, or in as
timely a manner as possible to prevent harm to human health and the environment, if the
owner or operator can demonstrate to the department that removal of the released waste
or accumulated precipitation cannot be accomplished within twenty-four hours. (Note: If
the collected material is a hazardous waste under chapter 33.1-24-02, it is subject to
management as a hazardous waste in accordance with all applicable requirements of
chapters 33.1-24-03 through 33.1-24-05. If the collected material is discharged through a
point source to waters of the United States, it is subject to the requirements of sections
301, 304, and 402 of the Clean Water Act, as amended. If discharged to a publicly owned
treatment works, it is subject to the requirements of section 307 of the Clean Water Act,
as amended. If the collected material is released to the environment, it may be subject to
the reporting requirements of 40 CFR part 302.)
4.
Secondary containment for tanks must include one or more of the following devices:
a.
A liner (external to the tank);
b.
A vault;
c.
A double-walled tank; or
d.
An equivalent device as approved by the department.
5.
In addition to the requirements of subsections 2, 3, and 4, secondary containment systems
must satisfy the following requirements:
a.
External liner systems must be:
(1)
Designed or operated to contain one hundred percent of the capacity of the largest
tank within its boundary;
(2)
Designed or operated to prevent run-on or infiltration of precipitation into the
secondary containment system unless the collection system has sufficient excess
capacity to contain run-on or infiltration. Such additional capacity must be sufficient
to contain precipitation from a twenty-five-year, twenty-four-hour rainfall event;
(3)
Free of cracks or gaps; and
(4)
Designed and installed to surround the tank completely and to cover all surrounding
earth likely to come into contact with the waste if the waste is released from the
tanks (for example, capable of preventing lateral as well as vertical migration of the
waste).
b.
Vault systems must be:
(1)
Designed or operated to contain one hundred percent of the capacity of the largest
tank within its boundary;
(2)
Designed or operated to prevent run-on or infiltration of precipitation into the
secondary containment system unless the collection system has sufficient excess
capacity to contain run-on or infiltration. Such additional capacity must be sufficient
to contain precipitation from a twenty-five-year, twenty-four-hour rainfall event;
(3)
Constructed with chemical-resistant water stops in place at all joints (if any);
(4)
Provided with an impermeable interior coating or lining that is compatible with the
stored waste and that will prevent migration of waste into the concrete;
(5)
Provided with a means to protect against the formation of and ignition of vapors
within the vault, if the waste being stored or treated:
(a)
Meets the definition of ignitable wastes under section 33.1-24-02-11; or
(b)
Meets the definition of reactive wastes under section 33.1-24-02-13, and may
form an ignitable or explosive vapor; and
(6)
Provided with an exterior moisture barrier or be otherwise designed or operated to
prevent migration of moisture into the vault if the vault is subject to hydraulic
pressure.
c.
Double-walled tanks must be:
(1)
Designed as an integral structure (for example, an inner tank completely enveloped
within an outer shell) so that any release from the inner tank is contained by the
outer shell;
(2)
Protected, if constructed of metal, from both corrosion of the primary tank interior
and of the external surface of the outer shell; and
(3)
Provided with a built-in continuous leak detection system capable of detecting a
release within twenty-four hours, or at the earliest practical time if the owner or
operator can demonstrate to the department, and the department concludes, that
the existing detection technology or site conditions would not allow detection with a
release within twenty-four hours. (Note: The provisions outlined in the steel tank
institute's "Standard for Dual Wall Underground Steel Storage Tanks" may be used
as guidelines for aspects of the design of underground steel double-walled tanks.)
6.
Ancillary equipment must be provided with secondary containment (for example, trench,
jacketing, double-walled piping) that meets the requirements of subsections 2 and 3 except
for:
a.
Aboveground piping (exclusive of flanges, joints, valves, and other connections) that are
visually inspected for leaks on a daily basis;
b.
Welded flanges, welded joints, and welded connections that are visually inspected for
leaks on a daily basis;
c.
Sealless or magnetic coupling pumps, and sealless valves, that are visually inspected for
leaks on a daily basis; and
d.
Pressurized aboveground piping systems with automatic shutoff devices (for example,
excess flow check valves, flow metering shutdown devices, loss of pressure actuated
shutoff devices) that are visually inspected for leaks on a daily basis.
7.
The owner or operator may obtain a variance from the requirements of this section if the
department finds, as a result of a demonstration by the owner or operator that alternative
design and operating practices, together with location characteristics, will prevent the
migration of any hazardous waste or hazardous constituent into the ground water; or surface
water at least as effectively as secondary containment during the active life of the tank system
or that in the event of a release that does migrate to ground water or surface water, no
substantial present or potential hazard will be posed to human health or the environment. New
underground tank systems may not, per a demonstration in accordance with subdivision b, be
exempted from secondary containment requirements of this section.
a.
In deciding whether to grant a variance based on a demonstration of equivalent
protection of ground water and surface water, the department will consider:
(1)
The nature and quantity of the wastes;
(2)
The proposed alternate design and operation;
(3)
The hydrogeologic setting of the facility, including the thickness of soils present
between the tank system and ground water; and
(4)
All other factors that would influence the quality and mobility of the hazardous
constituents and the potential for them to migrate to ground water or surface water.
b.
In deciding whether to grant a variance based on a demonstration of no substantial
present or potential hazard, the department will consider:
(1)
The potential adverse effects on ground water, surface water, and land quality
taking into account:
(a)
The physical and chemical characteristics of the waste in the tank system,
including its potential for migration;
(b)
The hydrogeological characteristics of the facility and surrounding land;
(c)
The potential for health risks caused by human exposure to waste
constituents;
(d)
The potential for damage to wildlife, crops, vegetation, and physical structures
caused by exposure to waste constituents; and
(e)
The persistence and permanence of potential adverse effects;
(2)
The potential adverse effects of a release on ground water quality, taking into
account:
(a)
The quantity and quality of ground water and the direction of ground water
flow;
(b)
The proximity and withdrawal rates of ground water users;
(c)
The current and future uses of ground water in the area; and
(d)
The existing quality of ground water, including other sources of contamination
and their cumulative impact on the ground water quality;
(3)
The potential adverse effects of a release on surface water quality, taking into
account:
(a)
The quantity and quality of ground water and the direction of ground water
flow;
(b)
The patterns of rainfall in the region;
(c)
The proximity of the tank system to surface waters;
(d)
The current and future uses of surface waters in the area and any water quality
standards established for those surface waters; and
(e)
The existing quality of surface water, including other sources of contamination
and cumulative impact on surface water quality; and
(4)
The potential adverse effects of a release on the land surrounding the tank system,
taking into account:
(a)
The patterns of rainfall in the region; and
(b)
The current and future uses of the surrounding land.
c.
The owner or operator of a tank system, for which a variance from secondary
containment had been granted in accordance with the requirements of subdivision a, at
which a release of hazardous waste has occurred from the primary tank system, but has
not migrated beyond the zone of engineering control (as established in the variance),
must:
(1)
Comply with the requirements of section 33.1-24-05-109, except subsection 4; and
(2)
Decontaminate or remove contaminated soil to the extent necessary to:
(a)
Enable the tank system for which the variance was granted to resume
operation with the capability for the detection of releases at least equivalent to
the capability it had prior to the release; and
(b)
Prevent the migration of hazardous waste or hazardous constituents to ground
water or surface water; and
(3)
If contaminated soil cannot be removed or decontaminated in accordance with
paragraph 2, comply with the requirements of subsection 2 of section
33.1-24-05-110.
d.
The owner or operator of a tank system, for which a variance from secondary
containment had been granted in accordance with the requirements of subdivision a, at
which a release of hazardous waste has occurred from the primary tank system and has
migrated beyond the zone of engineering control (as established in the variance), shall:
(1)
Comply with the requirements of subsections 1, 2, 3, and 4 of section
33.1-24-05-109;
(2)
Prevent the migration of hazardous waste or hazardous constituents to ground
water or surface water, if possible, and decontaminate or remove contaminated soil.
If contaminated soil cannot be decontaminated or removed or if ground water has
been contaminated, the owner or operator shall comply with the requirements of
subsection 2 of section 33.1-24-05-110;
(3)
If repairing, replacing, or reinstalling the tank system, provides secondary
containment in accordance with the requirements of subsections 1 through 6 or
reapply for a variance from the secondary containment and meet the requirements
for new tank systems in section 33.1-24-05-105 if the tank system is replaced. The
owner or operator shall comply with these requirements even if contaminated soil
can be decontaminated or removed and ground water or surface water has not
been contaminated.
8.
The following procedures must be followed in order to request a variance from secondary
containment:
a.
The department must be notified in writing by the owner or operator that the owner or
operator intends to conduct and submit a demonstration for a variance from secondary
containment as allowed in subsection 7 according to the following schedule:
(1)
For existing tank systems, at least twenty-four months prior to the date that
secondary containment must be provided in accordance with subsection 1.
(2)
For new tank systems, at least thirty days prior to entering into a contract for
installation.
b.
As part of the notification, the owner or operator shall also submit to the department a
description of the steps necessary to conduct the demonstration and a timetable for
completing each of the steps. The demonstration must address each of the factors listed
in subdivision a or b of subsection 7;
c.
The demonstration for a variance must be completed within one hundred eighty days
after notifying the department of an intent to conduct the demonstration; and
d.
If the department intends to grant a variance under this section:
(1)
The department will inform the public, through a newspaper notice, of the availability
of the demonstration for a variance. The notice shall be placed in a daily or weekly
major local newspaper of general circulation and shall provide at least thirty days
from the date of the notice for the public to review and comment on the
demonstration for a variance. The department also will hold a public hearing, in
response to a request or at the department's discretion, whenever such a hearing
might clarify one or more issues concerning the demonstration for a variance. Public
notice of the hearing will be given at least thirty days prior to the date of the hearing
and may be given at the same time as notice of the opportunity for the public to
review and comment on the demonstration. These two notices may be combined.
(2)
The department will approve or disapprove the request for a variance within ninety
days of receipt of the demonstration from the owner or operator and will notify in
writing the owner or operator and each person who submitted written comments or
requested notice of the variance decision. If the demonstration for a variance is
incomplete or does not include sufficient information, the ninety-day time period will
begin when the department receives a complete demonstration, including all
information necessary to make a final determination. If the public comment period is
extended, the ninety-day time period will be similarly extended.
(3)
If a variance is approved, the department will require the permittee to construct and
operate the tank system in the manner that was demonstrated to meet the
requirements for the variance.
9.
All tank systems, until such time as secondary containment that meets the requirements of
this section is provided, must comply with the following:
a.
For nonenterable underground tanks, a leak test that meets the requirements of
subdivision e of subsection 2 of section 33.1-24-05-104 must be conducted at least
annually.
b.
For other than nonenterable underground tanks, the owner or operator shall either
conduct a leak test as in subdivision a or develop a schedule and procedure for an
assessment of the overall condition of the tank system by a qualified professional
engineer. The schedule and procedure must be adequate to detect obvious cracks,
leaks, and corrosion or erosion that may lead to cracks and leaks. The owner or operator
shall remove the stored waste from the tank, if necessary, to allow the condition of all
internal tank surfaces to be assessed. The frequency of these assessments must be
based on the material of construction of the tank and its ancillary equipment, the age of
the system, the type of corrosion or erosion protection used, the rate of corrosion or
erosion observed during the previous inspection, and the characteristics of the waste
being stored or treated.
c.
For ancillary equipment, a leak test or other integrity assessment as approved by the
department must be conducted by a qualified professional engineer at least annually.
Note: The practices described in the American petroleum institute publication guide for
inspection of refinery equipment, chapter XIII, "Atmospheric and Low-Pressure Storage
Tanks", fourth edition 1981, may be used, where applicable, as guidelines for assessing
the overall condition of the tank system.
d.
The owner or operator shall maintain on file at the facility a record of the results of the
assessments conducted in accordance with subdivisions a through c.
e.
If a tank system or component is found to be leaking or unfit for use as a result of the
leak test or assessment in subdivisions a through c, the owner or operator shall comply
with the requirements of section 33.1-24-05-109.