NDAC 33.1-24-05-110
Closure and postclosure care
Cite as N.D. Admin. Code ยง 33.1-24-05-110
1.
At closure of a tank system, the owner or operator shall remove or decontaminate all waste
residues, contaminated containment system components (liners, etc.), contaminated soils,
and structures and equipment contaminated with waste, and manage them as a hazardous
waste, unless subsection 4 of section 33.1-24-02-03 applies. The closure plan, closure
activities, cost estimates for closure, and financial responsibility for tank systems must meet all
of the requirements specified in sections 33.1-24-05-59 through 33.1-24-05-88.
2.
If the owner or operator demonstrates that not all contaminated soil can be practicably
removed or decontaminated as required in subsection 1, then the owner or operator shall
close the tank system and perform postclosure care in accordance with the closure and
postclosure care requirements that apply to landfills under section 33.1-24-05-180. In addition,
for the purposes of closure, postclosure, and financial responsibility, such a tank system is
then considered to be a landfill, and the owner or operator shall meet all the requirements for
landfills specified in sections 33.1-24-05-59 through 33.1-24-05-88.
3.
If an owner or operator has a tank system that does not have secondary containment that
meets the requirements of subsections 2 through 6 of section 33.1-24-05-106 and has not
been granted a variance from the secondary containment requirements in accordance with
subsection 7 of section 33.1-24-05-106, then:
a.
The closure plan for the tank system must include both a plan for complying with
subsection 1 and a contingent plan for complying with subsection 2;
b.
A contingent postclosure plan for complying with subsection 2 must be prepared and
submitted as part of the permit application;
c.
The cost estimates calculated for closure and postclosure care must reflect the cost of
complying with the contingent closure plan and the contingent postclosure plan, if those
costs are greater than the costs of complying with the closure plan prepared for the
expected closure under subsection 1;
d.
Financial assurance must be based on the cost estimates in subdivision c; and
e.
For the purposes of the contingent closure and postclosure plans, such a tank system is
considered to be a landfill, and the contingent plans must meet all of the closure,
postclosure, and financial responsibility requirements for landfills under sections
33.1-24-05-59 through 33.1-24-05-88.