NDAC 33.1-24-05-126
Action leakage rate
Cite as N.D. Admin. Code ยง 33.1-24-05-126
1.
The department shall approve an action leakage rate for surface impoundment units subject to
subsection 3 or 4 of section 33.1-24-05-119. The action leakage rate is the maximum design
flow rate that the leak detection system can remove without the fluid head on the bottom liner
exceeding one foot [.3048 meters]. The action leakage rate must include an adequate safety
margin to allow for uncertainties in the design (for example, slope, hydraulic conductivity,
thickness of drainage material), construction, operation, and location of the leak detection
system, waste and leachate characteristics, likelihood and amounts of other sources of liquids
in the leak detection system, and proposed response actions (for example, the action leakage
rate must consider decreases in the flow capacity of the system over time resulting from
siltation and clogging, rib layover and creep of synthetic components of the system,
overburden pressures, etc.).
2.
To determine if the action leakage rate has been exceeded, the owner or operator must
convert the weekly or monthly flow rate from the monitoring data obtained under subsection 4
of section 33.1-24-05-120 to an average daily flow rate (gallons per acre per day) for each
sump. Unless the department approves a different calculation, the average daily flow rate for
each sump must be calculated weekly during the active life and closure period, and if the unit
is closed in accordance with subsection 2 of section 33.1-24-05-122, monthly during the
postclosure care period when monthly monitoring is required under subsection 4 of section
33.1-24-05-120.