NDAC 33.1-24-05-187
Action leakage rate
Cite as N.D. Admin. Code § 33.1-24-05-187
1.
The department shall approve an action leakage rate for landfill units subject to subsection 3
or 4 of section 33.1-24-05-177. The action leakage rate is the maximum design flow rate that
the leak detection system can remove without the fluid head on the bottom liner exceeding
one foot [.3048 meter]. The action leakage rate must include an adequate safety margin to
allow for uncertainties in the design (for example, slope, hydraulic conductivity, thickness of
drainage material), construction, operation, and location of the leak detection system, waste
and leachate characteristics, likelihood and amounts of other sources of liquids in the leak
detection system, and proposed response actions (for example, the action leakage rate must
consider decreases in the flow capacity of the system over time resulting from siltation and
clogging, rib layover and creep of synthetic components of the system, overburden pressures,
etc.).
2.
To determine if the action leakage rate has been exceeded, the owner or operator must
convert the weekly or monthly flow rate from the monitoring data obtained under subsection 3
of section 33.1-24-05-178, to an average daily flow rate (gallons per acre per day) for each
sump. Unless the department approves a different calculation, the average daily flow rate for
each sump must be calculated weekly during the active life and closure period, and monthly
during the postclosure care period when monthly monitoring is required under subsection 3 of
section 33.1-24-05-178.