NDAC 33.1-24-06-76
Information required for equipment
Cite as N.D. Admin. Code ยง 33.1-24-06-76
If the facility has equipment to which sections 33.1-24-05-420 through 33.1-24-05-449 applies, the
following information must be kept at the facility:
1.
For each piece of equipment to which sections 33.1-24-05-420 through 33.1-24-05-449
applies:
a.
Equipment identification number and hazardous waste management unit identification;
b.
Approximate locations within the facility (for example, identify the hazardous waste
management unit on a facility plot plan);
c.
Type of equipment (for example, a pump or a pipeline valve);
d.
Percent by weight of total organics in the hazardous waste stream at the equipment;
e.
Hazardous waste state at the equipment (for example, gas or vapor, or both, or liquid);
and
f.
Method of compliance with the standard (for example, monthly leak detection and repair,
or equipped with dual mechanical seals).
2.
For facilities that cannot install a closed-vent system and control device to comply with
sections 33.1-24-05-420 through 33.1-24-05-449 on the effective date that the facility
becomes subject to sections 33.1-24-05-420 through 33.1-24-05-449 provisions, an
implementation schedule as specified in subdivision b of subsection 1 of section
33.1-24-05-403.
3.
Documentation that demonstrates compliance with the equipment standards in sections
33.1-24-05-422 and 33.1-24-05-429. This documentation must contain the records required
under section 33.1-24-05-434.
4.
Documentation to demonstrate compliance with section 33.1-24-05-430 must include the
following information:
a.
A list of all information references and sources used in preparing the documentation.
b.
Records, including the dates, of each compliance test required by subsection 10 of
section 33.1-24-05-403.
c.
A design analysis, specifications, drawings, schematics, and piping and instrumentation
diagrams based on the appropriate sections of "APTI Course 415: Control of Gaseous
Emissions" (incorporated by reference in section 33.1-24-01-05) or other engineering
texts acceptable to the department that present basic control device design information.
The design analysis must address the vent stream characteristics and control device
operation parameters as specified in paragraph 3 of subdivision d of subsection 2 of
section 33.1-24-05-405.
d.
A statement signed by the owner or operator and dated certifying that the operating
parameters used in the design analysis reasonably represent the conditions that exist
when the hazardous waste management unit is operating at the highest load or capacity
level reasonable expected to occur.
e.
A statement signed by the owner or operator and dated certifying that the control device
is designed to operate at an efficiency of ninety-five weight percent or greater.