NDAC 37-11-05-01
Specifications
Cite as N.D. Admin. Code ยง 37-11-05-01
The furnishing, fabricating, and installation of a tourist-oriented directional sign must be in
conformance with the following standards:
1.
Materials.
a.
General. All materials furnished and used in this work item must be new and must meet
the plans, the standard drawings, and the following requirements:
(1)
Signs, supporting structures, breakaway bases, anchor units, brackets, stringers,
and hardware must be fabricated to meet the dimensions, metal gauge, and bolt
holes set forth in the contract and standard drawings. All flat sheet sign backings
must be aluminum with reflective sheeting applied as specified.
(2)
The traffic-control sign details not otherwise specified must meet the MUTCD
published by the federal highway administration.
(3)
All sign faces must be according to the detail drawings and the alphabets shown in
the MUTCD, standard highway signs, and standard alphabets, published by the
federal highway administration. Sign faces not detailed in these publications must
meet the detailed drawings shown in the supplementary standard highway signs
booklet published by the department.
(4)
Regulatory, warning, and guide signs must be detailed and dimensioned according
to detailed drawings of the standard highway signs booklet and department
supplement. These detailed drawings are available to the sign fabricator upon
request from the department. Signs not illustrated in these booklets must be as
shown on the standard drawings. The last number in the sign numbers shown is the
width of the sign required.
(5)
Variable message sign dimensions have been computed by the department of
transportation in order to draft these signs by mechanical means. These message
computations have been tabulated and must be used to lay out these sign faces in
the fabricator's shop. These tabulated sheets will be furnished to the contractor
upon request after the contract has been awarded.
b.
Concrete. Concrete used in this item of work must be class AE portland cement concrete
mixed and proportioned as specified in section 802.
c.
Reinforcing steel. The reinforcing steel must meet section 612.
d.
Delineators. Delineators must meet section 894.06.
e.
Hardware and fittings. Signs, supporting structures, breakaway bases, anchor units,
brackets, stringers, and all hardware and fittings must meet section 894.05 A.
f.
Overhead sign structures. Overhead structures must meet section 894.08.
g.
Grout. Grout must meet section 806.
2.
Construction requirements.
a.
Locating and positioning signs and sign structures. Each sign and structure must be
located according to the plans or, where necessary, for maximum effect of the sign.
Installed signs and structures will be inspected at night for maximum effect and minimum
specular reflection. If any sign exhibits specular reflection or is ineffective at night, the
sign must be adjusted at the contractor's expense.
Signs and delineators located less than thirty feet [9.14 meters] from the pavement edge
must be erected with the sign face truly vertical and turned ninety-three degrees away
from the center and direction of travel of the lane that the facility serves. Signs located
thirty feet [9.14 meters] or more from the edge of the pavement edge must be erected
with the sign face truly vertical and aligned ninety degrees from the center and direction
of travel of the lane that the offset sign serves. Special attention must be given to the
location and positioning of signs and delineators at the point where lanes divide, or on
curves, to avoid specular reflection and to obtain maximum effectiveness of the facility.
b.
Sign fabrication.
(1)
General. All sign backing for flat sheet signs must be aluminum unless noted
otherwise, with reflective sheeting applied as specified in this chapter. On large
variable message signs the messages, symbols, and borders must consist of
directly applied reflective sheeting cut to desired shapes. The message, symbols,
and border must be applied as specified by the sheeting manufacturer.
(2)
Fabrication of sign backing. Sign backings must be cut to size and shape and must
be free of buckles, warps, dents, cockles, burrs, and all defects resulting from
fabrication. The surface of all signs must be plane surfaces.
All cutting, shearing, and drilling or punching of holes (except mounting holes for
demountable letters, numerals, symbols, and borders) must be completed before
metal degreasing and application of reflective sheeting.
(3)
Cleaning and processing. Cleaning and processing of sign backing must take place
before applying the reflective sheeting. Cleaning and processing must be performed
using the sheeting manufacturer's instructions and recommendations as well as the
requirements of section 894.
All metal sign backing material must be handled only by handling devices or clean
canvas gloves between cleaning and applying reflective sheeting. Metal must not
come in contact with greases, oils, or other contaminants before application of
reflective sheeting. When backing materials are chromate-conversion coated
beforehand and are allowed to set for several days before applying reflective
sheeting, the application surface must be given a solvent wipe before reflective
sheeting application.
(4)
Fabrication of flat sheet signs. The background or message and border must be
screened on reflective sheeting as specified by the manufacturer of the reflective
material and as specified here. Colors must meet the requirements of the contract
and as shown in the MUTCD. Care must be taken so screening inks are compatible
with reflective sheeting backgrounds.
Reflective material must meet section 894.02.
The reflective sheeting used on flat sheet sign backings larger than the
manufacturer's material must require splicing. All sheeting on one individual sign
must be from the same manufacturer's lot and must be spliced in one direction only.
No more than one splice is permitted per sign. Vertical splices must be in the center
of the sign. Horizontal splices, if used in lieu of the vertical splice, must be in the
center of the sign with the top portion overlapping the bottom portion of the sheeting
when it is in the upright position. Heat-activated, adhesive-coated, reflective
sheeting may be overlapped not less than three-sixteenths of one inch [4.76
millimeters] or by a butted gap not to exceed one-thirty-second of one inch [0.79
millimeters]. Splices will be permitted only on sign screens processed with
transparent colors. Pressure-sensitive, adhesive-coated, reflective sheetings must
be overlapped not less than three-sixteenths of one inch [4.76 millimeters].
The overlapped splice must be made without screening paints between the
reflective sheeting.
The sign face must be processed and finished with material as specified by the
sheeting manufacturer. Processing of type III A or III B reflective sheeting with
screened-on messages must be accomplished before applying to the sign backing.
Processing of type II reflective sheeting may be accomplished before or after
applying to the sign backing.
The finished signs must have a smooth, uniform surface. All letters and numbers
must be clear cut and sharp.
(5)
Fabrication of panel signs. The background must be applied to the panels as
specified by the reflective sheeting manufacturer.
Reflective sheeting must be overlap spliced. The splice must be overlapped not less
than three-sixteenths of one inch [4.76 millimeters], and sheeting applied to panels
must extend over the edges and down the side legs a minimum of one-sixteenth of
one inch [1.59 millimeters]. Splices must be at a ninety degree angle to the length of
the panel. The splices must be uniformly and neatly made throughout their entire
length. An individual panel may not have more than two splices, and the minimum
distance between adjacent splices must be eight feet [2.44 meters].
(6)
Date of fabrication. All signs receiving new sign facings must be dated with the
month and year fabricated. The date must be placed on the back of the metal
backing on the lower corner of the sign near the edge closest to traffic so that it can
be read from the ground. The dating layout must consist of one-fourth inch [6.35
millimeters] high numbers on a two and one-fourth inches [57.15 millimeters] long
by one and three-fourths inches [44.45 millimeters] high pressure sensitive label.
The numbers imprinted on the upper part of the label must be one through twelve,
with the last two digits of four consecutive years printed across the bottom (as 92,
93, 94, 95). The month and year of fabrication must be punched out. The label must
meet section 894.04. The cost of furnishing, fabricating, and installing labels must
be included in the price bid for "flat sheet for signs type II and III A", "panel for signs
type II and III A", "refacing signs type II and III A", or "overlay panel type II and III A".
c.
Packaging, labeling, handling, and shipping. Completed signs must be dry before
packaging or storing. Packaged signs that become wet before use may not be used. A
warning label with instructions designed to prevent damage to the signs must be on the
outside of the package, and an additional warning label must be placed in the packages
between the first and second sign, before the last sign, and after each five signs in a
package. Packaged signs may not be banded and must be stored and shipped on edge.
Packaging must be done so that the signs are protected during storage, shipping, and
handling. Packaged signs must be slipsheeted using the material and methods
recommended by the sheeting manufacturer.
Unmounted reflective sheeting may be stacked flat to a maximum height of five inches
[127.0 millimeters] for temporary storage. Otherwise, they must be stored on edge. The
sheeting on signs may not be exposed to temperatures above one hundred fifty degrees
Fahrenheit [65.56 degrees Celsius]. The slipsheeting must be left on the sign face until
mounted.
Panel signs may be assembled or separated into sections for ease in handling, storing,
and shipping. In lieu of packaging, the sign faces may be turned toward each other and
fastened together firmly with sufficient spacers to prevent the sign faces from touching.
Sign faces that cannot be protected by packaging or fastening face to face must have
protective covers placed over them.
d.
Label (handling, storage, and installation instructions). The label referred to in
section 754.03 C must contain the following instructions:
(1)
Loading on vehicles. Signs must be secured vertically in racks to prevent them from
rubbing, scratching, or marring front surfaces. Signs that have protective wrappings
or slipsheeting must be kept dry.
Signs must be carefully unloaded and stacked on edge off the ground in an upright
position.
(2)
Storage at jobsite. Signs must be stored indoors and upright on edge to prevent
damage to the reflective sheeting.
Signs must be kept dry. Packaged signs that get wet will be rejected.
(3)
Installation.
(a)
Signs must be handled carefully and not scuffed or walked on.
(b)
Nylon washers must be used between flat washers and sign face for all type III
and IV reflective sheeted signs.
(c)
When washing signs is necessary, a soft bristle brush or sponge and water
must be used.
e.
Erection of sign supports and delineators.
(1)
General. The engineer shall verify the support lengths on all new sign supports prior
to the materials being ordered by the contractor. All sign supports must be firmly set
and plumb after erection. All concrete foundations must be constructed as specified,
with the top sloped enough to drain away from the sign support. All exposed
concrete above ground surface must be given a rubbed finish. Excess excavation
material removed to set sign supports must be disposed of at the contractor's
expense. A driving cap must be used when driving a sign support.
(2)
Delineator posts. Delineator posts must be driven without being damaged. If the
drilled or punched hole method is used, the hole must be large enough so the post
may be set without damage. Any damage to utilities or structures as a result of
construction operations must be repaired according to section 105.03.
(3)
Anchor for telescoping perforated tubes and flange channel supports. Anchors for
telescoping perforated tubes and flange channel supports must be driven. The
perforated tube anchor must be driven to a maximum of four inches [101.6
millimeters] above the ground or sidewalk and four inches [101.6 millimeters]
maximum installed height aboveground or sidewalk for flange channel anchor.
Anchors must be installed at plan length, unless the engineer determines a shorter
length is sufficient due to good soil bearing developed when driving the anchor.
Anchor lengths may be reduced to a minimum of three feet [.91 meters]. When set
in sidewalk, the anchor plate may be omitted.
The sidewalk must be cored to install the anchor unit and the cored area must be
filled with new concrete to restore the sidewalk surface.
(4)
Tubular sign supports. Tubular sign supports must be set in a class AE portland
cement concrete base, constructed as shown on the plans. Breakaway base plates
must be assembled with the bolts torqued to plan requirements. The plates must be
carefully placed so the tapered bolt slot tapers toward approaching traffic. Either the
stub post or the anchor bolt design may be used as detailed. If the anchor bolt
design is used, a portland cement grout must be used to raise the top of the
foundation to a snug fit under the base plate.
(5)
Overhead sign structures. All overhead sign structures must be shop fabricated so
only bolted assembly is required in the field. Drilling to fasten an overhead sign to a
bridge is permitted, but field welding is not permitted.
Overhead sign structures, other than those fastened to bridges, must be set on
class AE portland cement concrete foundations as required. The foundation may be
constructed to grade elevation with the top surface level so the support set on it is
truly vertical, or the foundation may be constructed below grade and leveling nuts
used to level the base plate and bring it to grade. A portland cement grout must be
used to fill the voids between the foundation and the base plate.
(6)
Splicing. Splicing is permitted on telescoping and flange channel posts only to
obtain the required post length. A splice must be more than five feet [1.52 meters]
above the ground, and only one splice is permitted per post. Splicing costs must be
at the contractor's expense. The weight of the splice may not be added to the post
pay weight.
(7)
W-shaped sign supports.
(a)
W-shaped sign supports must be set in a class AE portland cement concrete
base, constructed as shown on the plans. Breakaway base plates must be
assembled with the bolt torqued to plan requirements. The plates must be
carefully placed so the tapered bolt slot tapers toward approaching traffic.
W-shaped supports must use the stub post design.
The contractor may install an H-pile footing in lieu of the concrete base. If the
bearing capacity specified cannot be obtained, the contractor shall install the
concrete base specified.
(b)
Flame cutting of w-shaped posts. The gas cutting torch may be used for cutting
metals or preparing joints. Carbon steel above 0.30 percent carbon, high alloy
steels, heat-treated steel, and plated metals may not be flame cut unless
subsequent corrective treatment is provided as approved by the materials and
research engineer.
All flame cutting work must be done by the oxyacetylene gas method or other
method approved by the engineer. The maximum permissible deviation from
true lines is one-sixteenth of one inch [1.59 millimeters]. Repairs of edge
defects shall be done according to section 3.2 of AWS structural welding code,
as amended by AASHTO specifications for welding of structural steel highway
bridges. In general, the roughness of flame cut surfaces may not be greater
than an ANSI roughness value of one thousand microinches. All slag from
flame cutting must be completely removed.
When flange plates or other members are cut to a curve, the curve must be
uniform to the radius required. A series of straight cut tangent to the curve is
not acceptable.
When ends of members, which are to take bearing, are cut with a torch a
suitable allowance in their length must be made to permit proper milling or
planing.
Joints for welding may be prepared by "flame cutting" or "flame gouging"
provided all slag and oxidized metals are removed.
(c)
Edge finishing. Members formed to specific size by shearing of structural steel
plates having a thickness of one-half inch [12.7 millimeters] or more, must be
machined or planed to correct size by removing not less than one-fourth inch
[6.35 millimeters] of metal. All field splice plates and stiffeners less than
one-half inch [12.7 millimeters] in thickness must have a minimum of
one-eighth inch [3.18 millimeters] of metal removed by machining or planing
after shearing.
f.
Mounting flat sheet signs type III A and III B sheeting. Flat sheet signs must be bolted to
the supports and must have a nylon washer between the flat washer and the sign face.
g.
Removing and resetting signs and supports. Existing signs and supports must be
removed and reset as specified. All signs and supports not to be reset must be stockpiled
on the project right of way at designated locations. The stockpiled signs and supports
remain the department's property.
Removed or reset signs and supports that become damaged during removing, resetting,
or stockpiling must be replaced at the contractor's expense.
Existing signs and supports must be removed as construction progresses and must be
immediately reset or installed. The contractor shall install new signs or reset signs as
shown on the plans. All signs and supports must be on the project site at the time
construction begins. The contractor may choose to temporarily reset existing signs, or
temporarily install new signs. The cost of installing and resetting signs temporarily must
be included in the price bid for other items. Any damaged signs or supports must be
replaced at the contractor's expense.