1.
After notice and hearing, the commission may revoke a mining permit or limit its duration. The
commission may act upon its own motion or upon the application of an owner in the permit
area. In deciding whether to revoke or limit a permit, the factors that the commission may
consider include:
a.
The technical ability of the operator and other owners to conduct mining operations.
b.
The experience of the operator and other owners in similar mining operations.
c.
Contractual obligations, such as an expiring lease.
d.
The amount of ownership the operator and other owners hold in the lease. If the operator
is the majority owner or if its interest when combined with that of its supporters is a
majority of the ownership, it is presumed that the operator should retain the permit. The
presumption, even if not rebutted, does not prohibit the commission from limiting the
duration of the permit. However, if the amount of the interest owned by the owner
seeking revocation or limitation and its supporters are a majority of the ownership, the
commission will presume that the permit should be revoked.
2.
The commission may suspend a permit that is the subject of a revocation or limitation
proceeding. A permit will not be suspended or revoked after operations have commenced.
3.
If the commission revokes a permit upon the application of an owner and issues a permit to
that owner or to another owner who supported revocation, the commission may limit the
duration of such permit. The commission may also, if the parties fail to agree, order the owner
acquiring the permit to pay reasonable costs incurred by the former operator and the
conditions under which payment is to be made. The costs for which reimbursement may be
ordered may include those involving survey of the well site, title search of surface and mineral
title, and preparation of an opinion of mineral ownership.
4.
If the commission declines to revoke a permit or limit the time within which it must be
exercised, it may include a term in its order restricting the ability of the operator to renew the
permit or to acquire another permit within the same spacing or drilling unit.