NDAC 43-02-02.4-29
Central production facility - Commingling of production
Cite as N.D. Admin. Code ยง 43-02-02.4-29
1.
The director shall have the authority to approve requests to consolidate production equipment
at a central location.
2.
Commingling of production from two or more wells in a central production facility is prohibited
unless approved by the director. There are two types of central production facilities that may
be approved by the director.
a.
A central production facility in which all production going into the facility has common
ownership (working interests, royalty interests, and overriding royalties), known as a
common ownership central production facility. The director may approve a common
ownership central production facility provided the production from each well can be
accurately determined at reasonable intervals.
b.
A central production facility in which production going into the facility has diverse
ownership, known as a diverse ownership central production facility. The director may
approve a diverse ownership central production facility provided the production from
each well is accurately metered prior to commingling. A diverse ownership central
production facility that is not metered prior to commingling may only be approved by the
commission after notice and hearing.
3.
Common ownership central production facility. The application for permission to commingle
solutions must be submitted on a sundry notice (form 4-sm) and shall include the following:
a.
A plat or map showing thereon the location of the central facility and the name, well file
number, and location of each well and flow lines from each well that will produce into the
facility.
b.
A schematic drawing of the facility which diagrams the testing, treating, routing, and
transferring of production. All pertinent items should be shown, such as treaters, tanks,
flow lines, valves, meters, and recycle pumps.
c.
An affidavit executed by a person who has knowledge as to the state of title
demonstrating common ownership.
d.
An explanation of the procedures or method to be used to accurately determine
individual well production at periodic intervals. Such procedures or method shall be
performed at least once every three months.
A copy of all tests are to be filed with the director on form 11-sm within thirty days after
the tests are completed.
4.
Diverse ownership central production facility. The application for permission to commingle
solutions must be submitted on a sundry notice (form 4-sm) and shall include the following:
a.
A plat or map showing thereon the location of the central facility and the name, well file
number, and location of each well, and flow lines from each well that will produce into the
facility.
b.
A schematic drawing of the facility which diagrams the testing, treating, routing, and
transferring of production. All pertinent items should be shown, such as treaters, tanks,
flow lines, valves, meters, and recycle pumps.
c.
The name of the manufacturer, size, and type of meters to be used. The meters must be
proved at least once every three months and the results reported to the director within
thirty days following the completion of the test.
d.
An explanation of the procedures or method to be used to accurately determine
individual well production at periodic intervals. Such procedures or method shall be
performed monthly.
A copy of all tests are to be filed with the director on form 11-sm within thirty days after
the tests are completed.
5.
Any changes to a previously approved central production facility must be reported on a sundry
notice (form 4-sm) and approved by the director.