NDAC 43-02-02.4-35
containment - Loading and unloading areas
Cite as N.D. Admin. Code ยง 43-02-02.4-35
1.
A truck loading and unloading area located outside of a secondary containment area shall be
constructed and sealed in a manner that prevents the seepage of waste product, stored
product, or brine into the surrounding soils, surface waters, or ground water. In addition, a
ramp shall be constructed to contain any leakage from transfer operations at the vehicle being
loaded or unloaded. The ramp area shall contain a sump and be connected to a secondary
containment area so that any spillage drains into the sump and into the secondary
containment area. The spill containment ramp and sump shall have a combined capacity of
not less than one thousand gallons.
2.
Sumps shall be constructed of materials impervious to the waste product, stored product, and
brine and resistant to damage and deterioration during use. Sumps shall be connected to the
ramp area and the secondary containment area in a manner that prevents leakage.
3.
All loading and unloading facility transfer lines that are not in use shall be secured to prevent
spillage. A shutoff valve shall be installed at the truck connect point and at the storage vessels.
All shutoff valves shall be left in a normally closed position.