NDAC 43-02-02-12.4
Pipeline design and construction requirements
Cite as N.D. Admin. Code ยง 43-02-02-12.4
1.
Topsoil must be removed before the installation of underground pipelines and replaced after
pipelines are installed.
2.
Pipeline systems must be constructed with materials that have the strength, thickness, and
chemical properties that prevent failure due to pressure gradients, physical contact with the
waste or fluids to which the pipes are exposed, climatic conditions, stress of installation,
seismic, and stress of daily operation.
3.
Design and construction requirements for wellfield pipelines and pipelines between the
wellfield and processing and satellite facilities must include an early detection and shutdown
capability in the event of pressure drop or loss of flow. This may include automatic
motor-operated valves with pressure transmitters and manually operated valves or devices.