NDAC 43-02-02-18.1
Perforating, fracturing, and chemically treating wells
Cite as N.D. Admin. Code ยง 43-02-02-18.1
During treatment operations, the director may prescribe pretreatment casing pressure testing as
well as other operational requirements designed to protect wellhead and casing strings. If damage
results to the casing or the casing seat from perforating, fracturing, or chemically treating a well, the
operator shall immediately notify the director and proceed with diligence to use the appropriate method
and means for rectifying such damage, pursuant to section 43-02-02-18. If perforating, fracturing, or
chemical treating results in irreparable damage which threatens the mechanical integrity of the well, the
commission may require the operator to plug the well.