NDAC 43-02-03-57
Determination of gas well potential
Cite as N.D. Admin. Code ยง 43-02-03-57
After the completion or recompletion of a gas well, the operator shall conduct tests to determine the
daily open flow potential of the well. The test results together with an analyses of the gas shall be
reported to the director within thirty days after completion of the well.
Operators shall conduct either a stabilized one-point back-pressure test or a multipoint
back-pressure test in accordance with the "Manual of Back-Pressure Testing of Gas Wells" published
by the interstate oil and gas compact commission unless otherwise approved by the director.