NDAC 43-02-13-24
Reclamation of facilities
Cite as N.D. Admin. Code ยง 43-02-13-24
The plugging and reclamation of high-level radioactive waste facilities must comply with all
applicable rules in chapter 43-02-03. Well bore must be filled with concrete or another plugging material
approved by the commission from the top of the waste to the ground surface.
All buildings and infrastructure not used for either site monitoring or security must be removed. All
disturbed lands must be reclaimed to a condition consistent with prior land use and productive capacity.
The exceptions to this is the area that contains signs or structures that are to be placed over the site to
warn or dissuade future generations from occupying the surface, drilling into the subsurface, or
disturbing the disposal wells, shafts, or chambers given the long-term nature of the high-level
radioactive waste.
Upon final closure of the waste disposal site, both active and passive institutional controls must be
implemented in and around the site. The means and the length of time that active institutional controls
are maintained must be determined by the commission after consulting with the advisory council. The
signs and structures comprising the passive institutional controls must be determined by the
commission after consulting with the advisory council. Documents containing the location and depth of
the waste, well construction, plugging and reclamation information, years of operation, half-lives of the
radioactive waste, and other pertinent data must be permanently stored in the local, state, and national
archives.