1.
All injection wells must be cased and cemented to prevent movement of fluids into or between
underground sources of drinking water or into an unauthorized zone. The casing and cement
used in construction of each new injection well must be designed for the life expectancy of the
well. All wells used for injection into a storage reservoir or salt cavern must have surface
casing set and cemented at a point not less than fifty feet [15.24 meters] below the base of the
Fox Hills formation. In determining and specifying casing and cementing requirements, all the
following factors must be considered:
a.
Depth to the injection zone and lower confining zone, or salt cavern specifics. Long string
casing must be set at least to the top of the injection zone and cemented as approved by
the director.
b.
Depth to the bottom of all underground sources of drinking water.
c.
Estimated minimum, maximum, and average injection pressures.
d.
Fluid pressure.
e.
Estimated fracture pressures.
f.
Physical and chemical characteristics of the injection zone.
2.
Appropriate logs and other tests must be conducted during the drilling and construction of
injection wells. Any well drilled or converted to an injection well must have a cement bond log
from which a presence of channels and microannulus can be determined radially. Cement
bond logs must contain elements approved by the director.
3.
After an injection well has been completed, approval must be obtained on a sundry notice filed