NDAC 43-03-05-04.1
Project duration
Cite as N.D. Admin. Code ยง 43-03-05-04.1
The project must be completed within the time specified in the contract. If the project cannot be
completed within the time specified in the contract, the grantee may make a written request to the
commission for an extension of up to one year. The request must set forth the specific additional time
requested and the reasons why an extension is needed. Upon receipt of the request, the commission
shall convey it to the council's executive committee. The executive committee may make use of a
technical review committee to analyze the request. The executive committee shall review the request
and make a recommendation to the commission. The commission, after reviewing the
recommendation, shall decide whether or not to grant the request. Additional extensions may be sought
under the same procedure described above, but may only be granted if the grantee proves that factors
beyond the grantee's control are the cause of its inability to complete the project on time and that since
receiving the first extension the grantee has been diligent in all respects in trying to complete the
project on time.