NDAC 43-03-05-07
Contract modifications
Cite as N.D. Admin. Code ยง 43-03-05-07
If at any time after entering a contract the grantee desires to change any term of the contract, the
grantee shall make a written request to the commission. The request must set forth the specific change
desired and the reasons why the change is needed. Upon receipt of the request, the commission shall
convey it to the council's executive committee. If the executive committee decides that the requested
change is substantive, it shall refer the request to the council and the council shall review it and make a
recommendation to the commission. The executive committee and council may use a technical review
committee to analyze the request. If the executive committee decides that the requested change is not
substantive, the executive committee shall review the request and make a recommendation to the
commission. The commission, after receiving the recommendation of the council or of the executive
committee, shall decide whether or not to grant the request.