NDAC 67-09-01-02
Construction must be approved by the superintendent of public instruction -
Cite as N.D. Admin. Code ยง 67-09-01-02
Exception.
A district may not undertake construction of any school building or facility estimated to cost more
than one hundred fifty thousand dollars unless:
1.
The construction is approved by the superintendent; or
2.
The construction is required as part of a plan to correct deficiencies required under North
Dakota Century Code section 15.1-06-09, approved by the state fire marshal, and the
estimated cost does not exceed one hundred fifty thousand dollars.