35-27-22. Order of priority of classes of construction liens

Year: 2026Length: 105 wordsOfficial source
35-27-22. Order of priority of classes of construction liens 1. Liens perfected under this chapter have priority in the following order: a. For manual labor. b. For materials. c. Subcontractors other than manual laborers. d. Original contractors. 2. Liens for manual labor filed within the ninety-day period must share ratably in the security. Liens for manual labor filed after the ninety-day period have priority in the order of the filing of such liens. Liens for materials filed within the ninety-day period must share ratably in the security and liens filed after the ninety-day period have priority in the order of the filing of such liens.