38-08-27. Controls, inspections, and engineering design on crude oil and produced water underground gathering pipelines
38-08-27. Controls, inspections, and engineering design on crude oil and produced
water underground gathering pipelines.
The application of this section is limited to an underground gathering pipeline that is
designed or intended to transfer crude oil or produced water from a production facility for
disposal, storage, or sale purposes and which was placed into service after August 1, 2015.
Upon request, the operator shall provide the commission the underground gathering pipeline
engineering construction design drawings and specifications, list of independent inspectors, and
a plan for leak protection and monitoring for the underground gathering pipeline. Within sixty
days of an underground gathering pipeline being placed into service, the operator of that
pipeline shall file with the commission an independent inspector's certificate of hydrostatic or
pneumatic testing of the underground gathering pipeline.