58-03-19. Building permit - Decision within sixty days of application
58-03-19. Building permit - Decision within sixty days of application
1. A township that regulates the construction, erection, reconstruction, repair, or alteration
of buildings and structures and issues building permits shall respond to a building
permit application within sixty days of receiving the application either by approving the
application and delivering the building permit or by providing the applicant written
notice of the grounds for rejection of the application.
2. If the building or structure for which a permit is requested meets all applicable zoning
regulations and the board of township supervisors or other appropriate official fails to
respond as required under subsection 1, the application is deemed to be approved
and the applicant may proceed with the construction, erection, reconstruction, repair,
or alteration of the building or structure and the township shall return any permit fee
submitted with the application.
3. A township's building permit application form must include a statement that if the
building or structure for which the permit is requested meets all applicable zoning
regulations and the board of township supervisors or other appropriate official fails to
respond within sixty days of receiving the application, the application is deemed
approved. Upon receipt of a building permit application, a township shall note on the
application the date of receipt and shall provide a copy of the submitted application to
the applicant with the date of receipt noted.