N.D. Cent. Code § 61-24.3-20
61-24.3-20. Other pipelines - Commission approval required
61-24.3-20. Other pipelines - Commission approval required
Upon construction of the southwest pipeline project, utilities, corporations, limited liability
companies, companies, or any other person or entity which proposes to install or construct a
pipeline or other underground conveyance system which crosses or intersects the southwest
pipeline project may do so only with the approval of the commission, in accordance with the
requirements and conditions imposed by the commission for the pipeline or other crossing.