N.D. Cent. Code § 61-35-100
61-35-100. Insufficiency of bonds - New bonds required - Failure to furnish
61-35-100. Insufficiency of bonds - New bonds required - Failure to furnish
If the board, at any time, deems the bond of a contractor insufficient either in form or as to
sureties, it may require the successful bidder or contractor to furnish, within such reasonable
time as the board may fix, a new bond to be approved by the board. If the contractor fails, after
notice, to furnish the new bond within the time required, the contractor's contract may be
canceled, and in that event the contractor's bond will be liable as if the contractor had failed to
perform the contract.