N.D. Cent. Code § 24-02-25.1
24-02-25.1. Claims against project - Notice of claim - When filed - Where filed
24-02-25.1. Claims against project - Notice of claim - When filed - Where filed
Any person who has furnished labor, materials, or supplies on a contract awarded under
section 24-02-23, and who has not been paid in full at the time of final acceptance of the project
by the department, has the right to file a claim against the contractor and the surety furnishing
the performance bond.
Notice of the claim must be given, in writing, to the contractor or the surety furnishing the
performance bond and must provide a clear and concise statement of the labor, materials, and
supplies furnished, to whom it was furnished, and the monetary value thereof. The claim must
bear interest, on each transaction for labor, materials, or supplies, commencing thirty days after
the last transaction. The rate of interest must be the rate provided in section 28-20-34. The
notice of the claim must be made by certified mail postage prepaid, in an envelope addressed to
the contractor at any place the contractor maintains an office or has a residence and posted
within one hundred eighty days from the date on which the person completed the contribution
giving rise to the claim.