N.M. Stat. § 42-14-3
Notice and right to repair.
A. Except with respect to claims for alleged construction defects involving an
immediate threat to the life or safety of persons occupying a dwelling, rendering a
dwelling uninhabitable or in which the seller, after notice from the purchaser pursuant to
this subsection, refused to make a repair under any applicable express warranty, a
purchaser shall first comply with the provisions of this section before filing a dwelling
action. A purchaser shall give written notice by the United States postal service with
delivery confirmation or electronic means, to the seller specifying the reasonable detail
of each alleged defect. A seller who receives notice pursuant to this subsection shall
promptly forward a copy of the notice to the last known address of each construction
professional that the seller reasonably believes is responsible for an alleged defect
specified in the notice. The seller's notice to each construction professional may be
delivered by electronic means.
B. Once a seller receives notice pursuant to this section, the notice does not
constitute notice of a claim or occurrence as defined by the New Mexico Insurance
Code or an insurance policy to trigger notice requirements to the seller's liability carrier,
as the notice is intended to allow the purchaser and seller an opportunity to amicably
resolve any claimed defect issues without the need for formal arbitration or legal
proceedings.
C. After receipt of the notice described in Subsection A of this section, the seller and
the seller's construction professional may inspect the dwelling to determine the nature
and cause of each alleged construction defect and the nature and extent of any repairs
or replacements necessary to remedy each alleged construction defect. The purchaser
shall ensure the dwelling is made available for inspection during normal working hours
not later than ten days after the purchaser receives the seller's and the seller's
construction professional's request for an inspection. The seller and the seller's
construction professional shall provide reasonable notice to the purchaser before
conducting the inspection. The inspection shall be conducted at a reasonable time.
The seller and the seller's construction professional may use reasonable measures,
including testing, to determine the nature and cause of each alleged construction defect
and the nature and extent of any repairs or replacements necessary to remedy each
alleged construction defect. The seller's construction professional shall restore the
dwelling within sixty days of the testing.
D. Within sixty days after receipt of the notice provided for in Subsection A of this
section, the seller shall send to the purchaser, by certified mail, return receipt
requested, a written response to the purchaser's notice. The response may:
(1)
offer to repair or replace each alleged construction defect or to have each
alleged construction defect repaired or replaced by another construction professional
chosen by the seller at the seller's or seller's construction professional's expense;
(2)
offer to provide monetary compensation to the purchaser; or
(3)
invoke any remedies provided in the construction contract between the
seller and the purchaser.
E. A written offer to repair or replace pursuant to Paragraph (1) of Subsection D of
this section shall describe in reasonable detail all repairs or replacements that the seller
and the seller's construction professional intend to make or provide to the dwelling and
a reasonable estimate of the date by which the repairs or replacements will be made.
This subsection does not prohibit the seller from offering monetary compensation or
other consideration instead of or in addition to a repair or replacement.
F. The purchaser shall allow the seller or the seller's construction professional the
opportunity to make repairs or replacements of each alleged construction defect unless
the purchaser has rejected in writing or by electronic means the seller's offer to repair or
replace. If the purchaser reasonably rejects the seller's offer, the purchaser has
complied with the requirements of this section and may initiate a dwelling action.
G. The purchaser and seller may negotiate for a release of claims regarding the
noticed construction defect if an offer involving monetary compensation or other
consideration is accepted or the purchaser is satisfied with the repairs or replacements.
H. If the response provided pursuant to Subsection D of this section includes a
notice of intent to repair or replace each alleged construction defect, and such offer to
repair or replace has not been rejected by the purchaser, the purchaser shall allow the
seller and the seller's construction professional a reasonable opportunity to repair or
replace each alleged construction defect or cause each alleged construction defect to
be repaired or replaced as follows:
(1)
the purchaser and the seller or the seller's construction professional shall
coordinate repairs or replacements within thirty days after the seller's notice of intent to
repair or replace was sent pursuant to Subsection D of this section. A construction
professional that was not involved in the construction of the dwelling resulting in each
alleged construction defect and that performs any repair or replacement of the alleged
construction defect pursuant to this section is liable to the seller or purchaser who
contracted for the contractor's or subcontractor's services only for that construction
professional's scope of work;
(2)
repairs or replacements shall begin as agreed by the purchaser and the
seller or the seller's construction professional, with reasonable efforts to begin repairs or
replacements within thirty days after the seller's notice of intent to repair or replace was
sent pursuant to Subsection D of this section. If a permit is required to perform the
repair or replacement, reasonable efforts shall be made to begin repairs or
replacements within ten days after receipt of the permit or thirty days after the seller's
notice of intent to repair or replace was sent pursuant to Subsection D of this section,
whichever is later;
(3)
all repairs or replacements shall be completed using reasonable care
under the circumstances and within a commercially reasonable time frame considering
the nature of the repair or replacement, any access issues or unforeseen events that
are not caused by the seller or the seller's construction professional;
(4)
the purchaser shall provide reasonable access during normal working
hours for the repairs or replacements;
(5)
the purchaser and seller may negotiate a release or waiver upon the
satisfaction of the purchaser or in exchange for monetary compensation or other
consideration in lieu of repair; and
(6)
at the conclusion of any repairs or replacements, the purchaser may
reinitiate the process set forth in this section regarding any claim for inadequate repair
or replacement.
I. A purchaser may send a new notice pursuant to Subsection A of this section to
include each alleged construction defect identified after submission of the original
notice. The seller and the seller's construction professional shall have a reasonable
period of time to conduct an inspection, if requested, and thereafter the parties shall
comply with the requirements of Subsections B through H of this section for each
additional alleged construction defect identified in reasonable detail in the notice.
J. The time periods provided for in this section shall be reasonably extended for
delays that are beyond the control of seller and otherwise by written agreement of the
seller and purchaser.
K. If the seller does not comply with the requirements of this section and the failure
is not due to any fault of the purchaser or a result of delays that are beyond the control
of seller, including weather conditions or government delay, the purchaser shall follow
any remedy provided for in the construction contract or file a complaint in court if no
dispute resolution mechanism is provided for in the contract with the seller.
L. Nothing in the Right to Repair Act negates or supersedes the existence of any
remedy provided for in the construction contract.
M. The statute of repose pursuant to Section 37-1-27 NMSA 1978 or other
applicable statute of limitation shall be tolled during the repair and replacement process
for items specified in the notice.