N.M. Stat. § 62-16-4
Renewable portfolio standard.
A. A public utility shall meet the renewable portfolio standard requirements, as
provided in this section, to include renewable energy in its electric energy supply
portfolio as demonstrated by its retirement of renewable energy certificates; provided
that the associated renewable energy is delivered to the public utility and assigned to
the public utility's New Mexico customers. For public utilities other than rural electric
cooperatives and municipalities, requirements of the renewable portfolio standard are:
(1)
no later than January 1, 2015, renewable energy shall comprise no less
than fifteen percent of each public utility's total retail sales to New Mexico customers;
(2)
no later than January 1, 2020, renewable energy shall comprise no less
than twenty percent of each public utility's total retail sales to New Mexico customers;
(3)
no later than January 1, 2025, renewable energy shall comprise no less
than forty percent of each public utility's total retail sales of electricity to New Mexico
customers;
(4)
no later than January 1, 2030, renewable energy shall comprise no less
than fifty percent of each public utility's total retail sales of electricity to New Mexico
customers;
(5)
no later than January 1, 2040, renewable energy resources shall supply
no less than eighty percent of all retail sales of electricity in New Mexico; provided that
compliance with this standard until December 31, 2047 shall not require the public utility
to displace zero carbon resources in the utility's generation portfolio on the effective
date of this 2019 act; and
(6)
no later than January 1, 2045, zero carbon resources shall supply one
hundred percent of all retail sales of electricity in New Mexico. Reasonable and
consistent progress shall be made over time toward this requirement.
B. In administering the standards required by Paragraphs (5) and (6) of Subsection
A of this section, the commission shall:
(1)
not jeopardize the operation of a sewage treatment facility that captures
and combusts methane gas in the facility's operations;
(2)
maintain and protect the safety, reliable operation and balancing of loads
and resources on the electric system;
(3)
prevent unreasonable impacts to customer electricity bills, taking into
consideration the economic and environmental costs and benefits of renewable energy
resources and zero carbon resources;
(4)
prevent carbon dioxide emitting electricity-generating resources from
being reassigned, redesignated or sold as a means of complying with the standard;
(5)
in consultation with the energy, minerals and natural resources
department, undertake programs not prohibited by law to achieve the standard;
(6)
in consultation with the department of environment, ensure that the
standard does not result in material increases to greenhouse gas emissions from
entities not subject to commission oversight and regulation; and
(7)
in consultation with electricity transmission system operators responsible
for balancing New Mexico electricity loads and resources, issue a report to the
legislature by July 1, 2020, and each July 1 every four years thereafter. The report shall
include:
(a) review of the standard, with a focus on technologies, forecasts, existing
transmission, environmental protection, public safety, affordability and electricity
transmission and distribution system reliability;
(b) evaluation of the anticipated financial costs and benefits to electric utilities
in implementing the standard, including the impacts and benefits to customer electricity
bills; and
(c) identification of the barriers to, and benefits of, achieving the standard.
C. Any customer that is a political subdivision of the state, or any educational
institution designated in Article 12, Section 11 of the constitution of New Mexico with an
enrollment of twenty thousand students or more during the fall semester on its main
campus, with consumption exceeding twenty thousand megawatt-hours per year at any
single location or facility and that owns facilities that produce renewable energy or hosts
such facilities through a renewable purchased power agreement, shall not be charged
by the utility for power purchases of one year or less or fuel on the amount of electricity
purchased from the utility equal to the amount of renewable energy produced or hosted
by the customer. The customer shall annually certify to the state auditor and notify the
commission and the customer's serving electric utility of the amount of renewable
energy produced at the customer-owned or customer-hosted facilities that generate
renewable energy. The customer shall also certify to the state auditor and notify the
commission that the customer will retire all renewable energy certificates associated
with the renewable energy produced by those facilities. Any financial benefits as a
result of the provisions of this subsection shall accrue to the customer immediately upon
the effective date of this 2019 act and shall be reflected in customer bills each month,
subject to annual true-up and reconciliation. The provisions of this subsection shall not
prevent the utility from recovering all of its reasonable and prudent fuel and purchased
power costs.
D. Upon a motion or application by a public utility the commission shall, or upon a
motion or application by any other person the commission may, open a docket to
develop and provide financial or other incentives to encourage public utilities to produce
or acquire renewable energy that exceeds the applicable annual renewable portfolio
standard set forth in this section; results in reductions in carbon dioxide emissions
earlier than required by Subsection A of this section; or causes a reduction in the
generation of electricity by coal-fired generating facilities, including coal-fired generating
facilities located outside of New Mexico. The incentives may include additional earnings
and capital investment opportunities for resources used in furtherance of the outcomes
described in this subsection.
E. If, in any given year, a public utility determines that the average annual levelized
cost of renewable energy that would need to be procured or generated for purposes of
compliance with the renewable portfolio standard would be greater than the reasonable
cost threshold, the public utility shall not be required to incur that excess cost; provided
that the existence of this condition excusing performance in any given year shall not
operate to delay compliance with the renewable portfolio standard in subsequent years.
The provisions of this subsection do not preclude a public utility from accepting a project
with a cost that would exceed the reasonable cost threshold. When a public utility can
generate or procure renewable energy at or below the reasonable cost threshold, it shall
be required to do so to the extent necessary to meet the applicable renewable portfolio
standard and shall not be precluded from exceeding the standard.
F. By September 1, 2007 and until June 30, 2019, a public utility shall file a report to
the commission on its procurement and generation of renewable energy during the prior
calendar year and a procurement plan that includes:
(1)
the cost of procurement for any new renewable energy resource in the
next calendar year required to comply with the renewable portfolio standard; and
(2)
testimony and exhibits that demonstrate that the proposed procurement is
reasonable as to its terms and conditions considering price, availability, reliability, any
renewable energy certificate values and diversity of the renewable energy resource; or
(3)
demonstration that the plan is otherwise in the public interest.
G. By July 1, 2020, and each July 1 thereafter, a public utility shall file a report to the
commission on the public utility's procurement and generation of renewable energy
since the last report and a procurement plan that includes:
(1)
the cost of procurement for new renewable energy required to comply with
the renewable portfolio standard;
(2)
the capital, operating and fuel costs on a per-megawatt-hour basis during
the preceding calendar year of each nonrenewable generation resource rate-based by
the utility, or dedicated to the utility through a power purchase agreement of one year or
longer, and the nonrenewable generation resources' carbon dioxide emissions on a per-
megawatt-hour basis during that same year;
(3)
information, including exhibits, as applicable, that demonstrates that the
proposed procurement:
(a) was the result of competitive procurement that included opportunities for
bidders to propose purchased power, facility self-build or facility build-transfer options;
(b) has a cost that is reasonable as evidenced by a comparison of the price of
electricity from renewable energy resources in the bids received by the public utility to
recent prices for comparable energy resources elsewhere in the southwestern United
States; and
(c) is in the public interest, considering factors such as overall cost and
economic development opportunities; and
(4)
strategies used to minimize costs of renewable energy integration,
including location, diversity, balancing area activity, demand-side management and load
management.
H. The commission shall approve or modify a public utility's procurement plan within
ninety days and may approve the plan without a hearing, unless a protest is filed that
demonstrates to the commission's reasonable satisfaction that a hearing is necessary.
The commission may modify a plan after notice and hearing. The commission may, for
good cause, extend the time to approve a procurement plan for an additional ninety
days. If the commission does not act within the ninety-day period, the procurement plan
is deemed approved.
I. The commission may reject a procurement plan if, within forty days of filing, the
commission finds that the plan does not contain the required information and, upon the
rejection, shall provide the public utility the time necessary to file a revised plan;
provided that the total amount of renewable energy required to be procured by the
public utility shall not change.