N.M. Stat. § 62-18-4
Financing order; application contents; pending
applications.
A. A qualifying utility that is abandoning a qualifying generating facility may apply to
the commission for a financing order pursuant to this section to recover all of its energy
transition costs through the issuance of energy transition bonds. To obtain a financing
order, a qualifying utility shall obtain approval to abandon a qualifying generating facility
pursuant to Section 62-9-5 NMSA 1978. The application for the financing order may be
filed as part of the application for approval to abandon a qualifying generating facility.
B. An application for a financing order shall include:
(1)
a description of the facility that the qualifying utility proposes to abandon
or for which abandonment authority was granted after December 31, 2018;
(2)
an estimate of the energy transition costs and shall:
(a) identify the severance pay and job training expenses for affected
employees losing their jobs as a result of an abandoned qualifying generating facility
and any associated mine that only services the abandoned qualifying generating facility;
(b) identify costs not previously collected from the qualifying utility's
customers for plant decommissioning and mine reclamation costs, subject to any
limitations ordered by the commission prior to January 1, 2019 and affirmed by the New
Mexico supreme court prior to the effective date of the Energy Transition Act,
associated with the abandoned qualifying generating facility; and
(c) include an estimate of the financing costs associated with each series of
energy transition bonds proposed to be issued;
(3)
an estimate of the amount of energy transition charges necessary to
recover the costs in Paragraph (2) of this subsection and the proposed calculation
thereof, based on the estimated date of issuance and estimated principal amount of
each series of energy transition bonds proposed to be issued;
(4)
a description of the proposed adjustment mechanism that complies with
the provisions of Section 6 [62-18-6 NMSA 1978] of the Energy Transition Act;
(5)
a memorandum with supporting exhibits from a securities firm, such firm to
be attested to by the state board of finance as being experienced in the marketing of
bonds and capable of providing such a memorandum, that the proposed issuance
satisfies the current published AAA rating or equivalent rating criteria of at least one
nationally recognized statistical rating organization for issuances similar to the proposed
energy transition bonds. The request for such attestation may be made by a qualifying
utility prior to an application for a financing order, and the state board of finance shall
act upon such a request promptly;
(6)
a commitment by the qualifying utility to file with the commission following
the issuance of the energy transition bonds:
(a) a description of the final structure and pricing of the bonds;
(b) updated financing costs and payment amount required pursuant to
Section 16 [62-18-16 NMSA 1978] of the Energy Transition Act; and
(c) an updated calculation of the energy transition charges;
(7)
an estimate of timing of the issuance and term of the energy transition
bonds, or series of bonds; provided that the scheduled final maturity for each bond
issuance shall be no longer than twenty-five years;
(8)
identification of plans to sell, assign, transfer or convey, other than as a
security, interest in energy transition property, including identification of an assignee,
and demonstration that the assignee will be a financing entity wholly owned, directly or
indirectly, by the qualifying utility that will be initially capitalized by the qualifying utility in
such a way that equity interests in the financing entity are at least one-half percent of
the total capital of the assignee;
(9)
identification of ancillary agreements that may be necessary or
appropriate;
(10)
a description of a proposed ratemaking process to reconcile and recover
or refund any difference between the energy transition costs financed by the energy
transition bonds and the actual final energy transition costs incurred by the qualifying
utility or the assignee;
(11)
a proposed ratemaking method to account for the reduction in the
qualifying utility's cost of service associated with the amount of undepreciated
investments being recovered by the energy transition charge at the time that charge
becomes effective; and
(12)
a statement from the qualifying utility committing that the qualifying utility
will use commercially reasonable efforts to obtain the lowest cost objective.
C. The application may include requests for approvals for new resources
necessitated by the abandonment of a qualifying generating facility.
D. The qualifying utility or the commission may defer applications for needed
approvals for new resources to a separate proceeding; provided that the application
identifies adequate potential new resources sufficient to provide reasonable and proper
service to retail customers.
E. If an application for approval to abandon a qualifying generating facility is
pending before the commission on the effective date of the Energy Transition Act, the
qualifying utility may file a separate application for a financing order, and the
commission may join or consolidate the application for a financing order with the
pending proceeding involving abandonment of the qualifying generating facility, with the
consent of the applicant. On such joinder or consolidation, the time periods prescribed
by the Energy Transition Act shall become applicable to the joined or consolidated case
as of the date of the joinder or consolidation.
F. If a qualifying utility does not recover energy transition costs pursuant to the
Energy Transition Act, the energy transition costs may be recovered pursuant to other
applicable provisions of the Public Utility Act [Chapter 62, Articles 1 to 6 and 8 to 13
NMSA 1978].