N.M. Stat. § 70-4-4
Claim of lien; contents and filing.
Every original contractor, within two hundred ten days after the performance of the
last labor or the furnishing or hauling of the last item of material, tools, machinery,
equipment or supplies, and every person, except the original contractor, claiming the
benefits of the Oil and Gas Lien Act within one hundred eighty days after the
performance of the last labor or the furnishing or hauling of the last item or material,
tools, machinery, equipment or supplies shall file for record with the county clerk of the
county in which the property upon which the lien is claimed or situated, a claim setting
forth the name and residence of the claimant, the amount and the items claimed, the
name of the person to whom the materials, tools, machinery, equipment or supplies
were furnished or hauled or for whom the labor was performed, the name of the owner
and a description of the property upon which the lien is claimed, verified by affidavit.