NAC 618.960

Demolition of building or structure.

Last amended: 2000Year: 2026Length: 127 wordsOfficial source

Cite as Nev. Admin. Code Sec. 618.960

1. Before a building or structure which contains friable materials containing asbestos may be demolished, the asbestos must be removed pursuant to the requirements set forth in 29 C.F.R. § 1926.1101 and NAC 618.9155 . 2. Before a building or structure may be demolished, a licensed inspector must visually inspect the building or structure to determine whether the friable material containing asbestos has been removed. The inspector shall provide written proof of his or her findings to the contractor responsible for demolition and the owner of the building or structure. 3. Air monitoring for a final clearance pursuant to NAC 618.956 is not required before the demolition of a structure unless the area is to be entered by unprotected personnel before demolition or reoccupied after partial demolition.
NAC 618.960: Demolition of building or structure. | Justis AI