93-018
Solid waste management district
Cite as 1993 Ohio Op. Att'y Gen. No. 93-018
Attorney General
OPINION NO. 93-018
Syllabus:
1.
Subject to review and approval of the Director of Environmental
Protection, the solid waste management plan of a joint solid waste
management district, prepared in accordance with R.C. 3734.53-.55, may
include a description of and schedule for closure and post-closure activities
at a solid waste disposal facility that is owned by a county participating in
the district and that ceased to accept wastes before the plan was prepared,
and may provide for use of a portion of the fees collected pursuant to
R.C. 3734.57(B) to implement those closure and post-closure activities.
2.
Subject to review and approval of the Director of Environmental
Protection, the solid waste management plan of a county solid waste
management district, prepared in accordance with R.C. 3734.53-.55, may
include a description of and schedule for closure and post-closure activities
at solid waste disposal facility that is owned by the county and that ceased
to accept wastes before the plan was prepared, and may provide for use
of a portion of the fees collected pursuant to R.C. 3734.57(B) to
implement those closure and post-closure activities.
3.
The board of county commissioners of a county that participates in a joint
solid waste management district may, with the consent of the joint district,
transfer to the joint district a county-owned landfill that is in need of
closure and post-closure care.
4.
The board of county commissioners of a county that maintains a single
county solid waste management district may designate a county-owned
landfill for use by the county solid waste management district, and may
include in the solid waste management plan of the county district a county-
owned landfill that is in need of closure and post-closure care; the
ownership of the landfill will remain in the board of county
commissioners.
OAG 93-018
2-94
1993 Opinions
To: William R. Biddlestone, Athens County Prosecuting Attorney, Athens,
Ohio
By: Lee Fisher, Attorney General, September 3, 1993
You have requested an opinion relating to the authority of a solid waste management
district to provide within its solid waste management plan for the use of a portion of the moneys
collected under R.C. 3734.57(B) to pay the costs of closure and post-closure care for a county-
owned solid waste management facility. Your specific questions are as follows:
1.
Assuming that Athens County remains a part of the joint district, in order
to meet its obligations under Ohio Revised Code, Section 3734.02(A), and
regulations adopted thereunder, requiring proper closure and post-closure care for
solid waste disposal facilities, and in accordance with the schedule required by
Ohio Revised Code, Section 3734.53(A)(12)(b),
may the Board of County
Commissioners request the board of directors to include as part of the joint
district plan a description of and schedule for closure and post-closure activities
required by the Ohio Environmental Protection Agency at an existing county-
owned solid waste disposal facility, and use a portion of the fees collected
Pursuant to Ohio Revised Code, Section 3734.57(B), to implement those closure
and post-closure activities?
2.
Assuming that the county can successfully complete the process required
under H.B. 723 to withdraw from the joint district and form its own single county
district, can the county transfer its ownership of the existing solid waste disposal
facility to the district, and include a description of and schedule for closure and
post-closure activities at the landfill in its solid waste management plan, and use
a portion of the fees collected pursuant to Ohio Revised Code, Section 3734.57(B)
to implement those closure and post-closure activities?
Solid Waste Management Districts and Plans
Pursuant to R.C. 3734.52, the board of commissioners of each county must either
establish and maintain a county solid waste management district or participate with other counties
in establishing and maintaining a joint solid waste management district.' A county solid waste
management district is managed by the board of commissioners of the county, and a joint solid
waste management district is managed by its board of directors, consisting generally of the
boards of county commissioners of the counties within the district. R.C. 343.01. Each county
or joint solid waste management district has a solid waste management policy committee,
consisting of representatives of the public and of various political subdivisions within the district.
R.C. 3734.54.
A county or joint solid waste management district is required to prepare, adopt, submit,
and implement a solid waste management plan that complies with R.C. 3734.55.
R.C.
3734.52(A), .54, .55. Each solid waste management plan must be reviewed and approved by
the Director of Environmental Protection and must be ratified by specified numbers of the
counties, municipal corporations, and townships included within the district. R.C. 3734.55; see,
e.g., 1989 Op. Att'y Gen. No. 89-054 at 2-227. If the Director of Environmental Protection
I
It is also possible to create a regional solid waste management authority. See
R.C. 343.011. That arrangement is not mentioned in your request and is not addressed in this
opinion.
September 193
OAG 93-018
2-95
Attorney General
finds that a county or joint district has "materially failed" to implement its plan, the Director
"shall issue an enforcement order" directing the board to comply with the implementation
schedule in its plan "within a specified, reasonable time." R.C. 3734.55(E); see also R.C.
3734.13.
Solid waste management plans must be amended and updated periodically. See R.C.
3734.56. For purposes of this opinion, any reference to a solid waste management plan includes
also an amended plan.
The solid waste management plan of a county or joint solid waste management district
must "provide for, demonstrate, and certify the availability of and access to sufficient solid waste
management facility capacity to meet the solid waste management needs of the district" for at
least a ten-year period. R.C. 3734.53(A); see also 5 Ohio Admin. Code 3745-29-02. The plan
must contain a number of items specified by statute, including an inventory of sources,
composition, and quantities of solid wastes generated in the district; an inventory of existing
facilities where solid wastes are being disposed of and an estimate of the remaining disposal
capacity; projections of amounts of solid waste to be disposed of in the district in each of the
years covered by the plan; an identification of additional facilities needed; and other projections
that are necessary or appropriate to ascertain and meet the solid waste management needs of the
district during the period covered by the plan. R.C. 3734.53(A).
Each plan must contain a
schedule for its implementation, including "[a] schedule for closure of existing solid waste
facilities,
expansion of existing facilities, and establishment of new facilities," R.C.
3734.53(A)(12)(b), and also the methods for financing the implementation of the plan and a
demonstration of the availability of financial resources, R.C. 3734.53(A)(12)(d).
In addition,
the plan must establish the schedule of fees to be levied under R.C. 3734.57(B)(1)-(3) and
provide for the allocation of moneys derived from R.C. 3734.57(B)(1)-(3) among the purposes
enumerated in R.C. 3734.57(G)(1)-(9).
R.C. 3734.53(B).
The fee provisions are discussed
below.
Allocation of Fees Levied Under R.C. 3734.57(B)(1)-(3)
R.C. 3734.57(B) authorizes the solid waste management policy committee of a county
or joint solid waste management district to levy fees upon the disposal of solid wastes at a solid
waste disposal facility located in the district.
The fees are levied "[fior the purpose of
preparing, revising, and implementing the solid waste management plan of the county or joint
solid waste management district."
R.C. 3734.57(B).
They are paid to the board of county
commissioners or board of directors of the district. R.C. 3734.57(E). R.C. 3734.57(G) states
that the moneys must be expended "in accordance with the district's solid waste management
plan or amended plan.. .exclusively for" specified purposes.
R.C. 3734.57(G).
Among the
permissible purposes is "[i]mplementation of the approved solid waste management plan or
amended plan of the district."
R.C. 3734.57(G)(2); accord 5 Ohio Admin. Code 3745-28-
03(F)(2).
Closure and Post.-Closure of a Solid Waste Disposal Facility
Your questions relate to expenses that are required for closure and post-closure activities
at a solid waste disposal facility. The facility in question is a iandfill that is owned by the
county. The landfill has no remaining disposal capacity. It stopped accepting waste several
years ago, and it now requires proper closure and post-closure care, in accordance with R.C.
3734.02(A) and rules adopted thereunder.
OAG 93-018
2-96
1993 Opinions
"Closure" is defined to include:
measures performed to protect public health or safety, to prevent air and water
pollution, or to make the facility suitable for other uses, if any, including, but not
limited to, establishment and maintenance of a suitable cover of soil and
vegetation over cells in which hazardous waste or solid wastes are buried;
minimization of erosion, the infiltration of surface water into such cells, the
production of leachate, and the accumulation anO runoff of contaminated surface
water; the final construction of facilities for the collection and treatment of
leachate and contaminated surface water runoff; the final construction of air and
water quality monitoring facilities; the final construction of methane gas
extraction and treatment systems; or the removal and proper disposal of hazardous
waste or solid wastes from a facility when necessary to protect public health or
safety or to abate or prevent air or water pollution.
R.C. 3734.01(0). The Director of Environmental Protection is authorized to provide, by rule,
requirements for the closure and post-closure of a hazardous or solid waste facility.
R.C.
3734.02, .12(D)(8); see also R.C. 3734.12(D)(7), (F)(3).2
Authority of a Joint Solid Waste Management District to Expend Fees
Collected Pursuant to R.C. 3734.57(B) for Closure and Post-Closure
Activities at a Solid Waste Disposal Facility
Your first question assumes that Athens County remains a part of a joint solid waste
management district and asks whether the board of county commissioners may request the board
of directors of the district to include, as part of the joint district plan, a description of and
schedule for closure and post-closure activities at the landfill in question and to use a portion of
the fees collected under R.C. 3734.56(B) to implement those closure and post-closure activities.
It is clear, as your question indicates, that, if Athens County remains a part of a joint solid waste
management district, the Athens County commissioners cannot, by their own action, make
decisions on behalf of the district. Rather, those decisions must be made by the designated
representatives of the district or as otherwise provided by statute. See, e.g., R.C. 343.01(B)
(a joint solid waste management district is managed by its board of directors; a majority of the
board constitutes a quorum and a majority vote is required for the board to act); R.C. 3734.53-
.55 (preparation and adoption of joint district solid waste management plan). Thus, the Athens
County commissioners cannot include the landfill in question as part of the joint district plan
except with the consent of the district as a whole.
The essence of your question, then, is whether the joint district if it chooses, may incluri
within its plan a description of and schedule for closure and post-closure activities at a county-
owned landfill that ceased to accept wastes before the plan was prepared, and use fees collected
2 Existing provisions governing the issuance of permits and licenses for solid waste
facilities require assurances that proper closure and post-closure care will be provided. See,
e.g., R.C. 3734.02(A), .05(A)(6); 5 Ohio Admin. Code 3745-27-11, -14, -15, -16. Rules 3745-
27-15 and 3745-27-16 provide that the permittee of a solid waste facility must "establish
financial assurance" for final closure and post-closure care of the facility, in accordance with
applicable provisions. 5 Ohio Admin. Code 3745-27-15 and -16; see also 5 Ohio Admin. Code
3745-27-17. A permittee may be a public or private entity. See 5 Ohio Admin. Code 3745-27-
01(00), (PP); see also 5 Ohio Admin. Code 3745-27-15.
September 1993
OAG 93-018
2-97
Attorney General
under R.C. 3734.57(B) to implement those activities. The statutory scheme, as outlined above,
does not expressly discuss the inclusion of such an arrangement as part of a solid waste
management plan.
The provisions governing the preparation and adoption of a plan are,
however, broad enough to permit a joint district to include such an arrangement in its plan. As
discussed above, R.C. 3734.57(B) permits fees to be levied "[flor the purpose of preparing,
revising, and implementing" the solid waste management plan of the district, and R.C.
3734.57(G) provides that the proceeds may be expended, in accordance with the district's solid
waste management plan, for purposes including "[i]mplementation of the approved solid wast(
management plan or amended plan of the district." Thus, if the expenditure of such fees for the
closure and post-closure of the landfill in question is part of the joint district's approved solid
waste management plan, then the fees may be expended for that purpose.
The provisions governing solid waste management plans do not directly address the type
of situation with which you are concerned.
As discussed above, however, the statutes do
provide that the plan must include an inventory of all existing facilities within the district where
solid wastes are being disposed of, and further provide that the schedule for implementation of
the plan must inclide a schedule for closure of existing solid waste facilities.
R.C.
3734.53(A)(2), (12). The plan is designed to provide a comprehensive scheme for solid waste
disposal within the district for a period of ten years or more. The provision of closure and post-
closure care of landfills and other solid waste disposal facilities is an intrinsic part of providing
a comprehensive scheme for solid waste disposal. The provisions governing a joint district plan
do not require that the plan include all sites within the district that have in the past been used
for solid waste disposal.
Instead, the plan is primarily prospective.
The statutes do not,
however, prohibit a plan from including a publicly-owned landfill that has no remaining capacity
but is in need of closure and post-closure care as required pursuant to R.C. 3734.02(A).
The
need to close and care for a publicly-owned landfill properly is part of the solid waste disposal
demand placed upon the county and, as such, may appropriately be included within the joint
district's plan.
The plan is, of course, subject to review and approval by the Director of
Environmental Protection in accordance with R.C. 3734.54-.55 and related provisions, and,
further, must be ratified by the appropriate entities as provided in R.C. 3734.55.
The fact that the closure of solid waste disposal facilities may properly be part of a solid
waste management plan is clear from the requirement of R.C. 3734.53(A)(12)(b) that a schedule
for such closure be included in the plan. The conclusion that the plan may include sites existing
prior to creation of the plan is consistent with R.C. 3734.52, which states, in part:
The solid waste management plan or amended plan of each county or joint
district shall provide for the maximum feasible utilization of solid waste facilities
that were in operation within the district, or for which permits were issued under
[R.C. 3734.05], on or before the effective date of the plan or amended plan and
that are in compliance with [R.C. 3734.01 to 3734.13] and rules adopted under
those sections.
In conversations between your representatives and members of my staff, it has been
suggested that there may be an interest in having the board of county commissioners transfer
ownership of the landfill to the joint solid waste management district. Such a transfer would
clearly be permitted.
R.C. 343.01 authorizes a county participating in a joint solid waste
management district to contribute lands, or rights or interests in lands, to the district, and
authorizes the board of directors of a joint solid waste management district to accept gifts and
devises and to take other actions necessary to control and manage the joint district. The rights
or interests of a particular county may be specified by agreement. R.C. 343.01(B). There is,
further, express authority for the board of directors of a joint district to "acquire, by purchase
2-98
OAG 93-018
1993 Opinions
or lease, construct, improve, enlarge, replace, maintain, and operate" such solid waste disposal
facilities as are necessary for the protection of the public health. R.C. 343.01(C).
It does not, however, appear that it is necessary for a participating county to transfer a
landfill to a joint district for the landfill to be included in the joint district's plan.
R.C.
343.01(C) authorizes a board of county commissioners to acquire real property for use by a joint
district. Further, the statutory provisions governing the preparation of plans and expenditure
of fees collected under R.C. 3734.57(B) are not expressly restricted to district-owned facilities.
See, e.g., R.C. 3734.52, .53.
Authority of a County Solid Waste Management District to Expend Fees
Collected Pursuant to R.C. 3734.57(B) for Closure and Post-Closure
Activities at a Solid Waste Disposal Facility
Your second question relates to the same landfill that is at issue in your first question.
You assume, for purposes of this question, that Athens County withdraws from the joint district
and forms a single county district.3 You ask whether, in those circumstances, the county could
transfer its ownership of the existing landfill to the district, include in its solid waste
management plan a description of and schedule for closure and post-closure activities at the
landfill, and use a portion of the fees collected under R.C. 3734.57(B) to implement those
closure and post-closure activities.
The provisions discussed above with respect to the inclusion of closure and post-closure
activities in a solid waste management plan and the use of fees collected under R.C. 3734.57(B)
for those activities apply to single county solid waste management districts as well as to joint
districts. Thus, if such activities are included in a single county solid waste management plan,
they can be implemented in accordance with that plan.
Your question also asks whether the county may transfer its ownership of the existing
solid waste disposal facility to the county district in preparation for including the closure and
post-closure activities in the plan and using a portion of the fees collected pursuant to R.C.
3734.57(B) to implement the closure and post-closu.Ire activities. In conversations between your
representatives and members of my staff, it has become apparent that transfer of ownership is
not an issue of importance, provided that the fees in question may be expended for closure and
post-closure activities if ownership remains in the county. Since this opinion concludes that the
fees may be expended for those purposes regardless of whether the county or the district owns
the landfill, provided that such expenditure is included within an approved solid waste
management plan, it is unnecessary to address in detail the question of transfer of ownership.
It may, however, be noted that, while a joint county solid waste management district is
clearly an independent entity for ownership purposes, see, R.C. 343.01(B), (C), it is not clear
that a single county solid waste management district is an entity separate from the county that
creates it. It appears, instead, that a single county solid waste management district is an agency
Your request references the reorganization process established by uncodified
Section 5 of H.B. 723. See Sub. H.B. 723, 119th Gen. A. (1992) (eff. April 16, 1993). It is
recognized that the process established by H.B. 723 has a number of steps and some distinct
time limitations. Since, however, you have not raised any questions concerning that process,
this opinion does not discuss it.
September 1993
OAG 93-018
2-99
Attorney General
of the county.' The board of county commissioners is authorized to hold property of the county,
see Carder v. Board of Commissioners, 16 Ohio St. 353 (1865), and is also granted authority
to hold property on behalf of a single county solid waste management district, see R.C.
343.01(C), .08. Moneys of a county district are held by the county treasurer and expended by
the county commissioners. See R.C. 343.08; R.C. 3734.57. The prosecuting attorney of the
county is designated as the legal adviser of a county district and is authorized to provide such
services as are provided "to other county boards" under R.C. Chapter 309. R.C. 343.01(E)(1)
(also permitting the employment of other legal counsel).
In addition, the board of county
commissioners may use county moneys and issue county bonds or bond anticipation notes to pay
costs of the district. See R.C. 343.01(D), (F). In contrast, the board of directors of a joint
solid waste management district or board of trustees of a regional solid waste management
authority may issue bonds or anticipation notes of the district or the authority.
See R.C.
343.01(F), .011.
It thus appears that a board of county commissioners, as the governing body of both the
county and a county solid waste management district, may designate certain county-owned real
property for the use of the district, and may include in the solid waste management plan of the
county district a county-owned landfill that is in need of closure and post-closure care. It does
not, however, appear that such a designation will constitute a transfer of property from the
county to the county solid waste management district. Instead, the property will continue to be
held by the board of county commissioners.'
Duty of the Director of Environmental Protection To Disapprove Any Solid
Waste Management Plan That Does Not Comply With R.C. 3734.53(A), (B),
and (D)
The conclusion that a solid waste management plan may include provisions for closure
and post-closure care of a county-owned landfill does not mean that the Director of
Environmental Protection must, in all cases, approve a plan that contains such provisions. The
Director is responsible for reviewing and commenting upon draft plans in accordance with R.C.
3734.54-.55.
The standard for approval is "compliance with the requirements of' R.C.
3734.53(A), (B) and (D). R.C. 3734.55(C)(1).
R.C. 3734.53(A) requires that, among other
items, a solid waste management plan include a schedule for implementation of the plan that,
when applicable, includes a schedule for closure of existing solid waste facilities and also the
"methods of financing implementation of the plan and a demonstration of the availability of
financial resources for that purpose." R.C. 3734.53(A)(12). If the Director finds that the plan
does not demonstrate financial feasibility, he may find that it fails to satisfy R.C. 3734.53(A)(12)
and disapprove it on that basis.
Similarly, R.C. 3734.53(B) provides for the solid waste management plan to establish
the schedule of fees to be levied under R.C. 3734.57(B) and to provide for their allocation
among the purposes enumerated in R.C. 3734.57(G)(l)-(9).
The plan must:
Ensure that sufficient of the moneys so credited to and available from the
special fund are available for use by the solid waste management policy
4
This conclusion is reached notwithstanding the fact that the territory encompassed
by a single county solid waste management district may differ from the territory of the county,
depending upon municipal boundaries. See R.C. 343.01(A); R.C. 3734.52(A).
5
A different result might be reached if a regional solid waste management authority
were created. See R.C. 343.011; note 1, supra.
2-100
OAG 03-018
1993 Opinions
committee of the district at the time the moneys are needed to monitor
implementation of the plan and conduct its periodic review and amendment as
required under [R.C. 3734.56].
R.C. 3734.53(B)(2)(a). A plan that allocates for closure and post-closure care moneys that are
needed for these monitoring and reviewing responsibilities is subject to disapproval by the
Director of Environmental Protection for failure to comply with R.C. 3734.53(B)(2)(a).
Thus, the conclusion reached in this opinion that a county or joint solid waste
management district may include in its solid waste management plan a description of and
schedule for closure and post-closure activities at a county-owned solid waste disposal facility,
and may provide for use of a portion of the fees collected pursuant to R.C. 3734.37(B) to
implement those closure and post-closure activities, does not mean that every plan containing
such provisions must be approved by the Director of Environmental Protection pursuant to R.C.
3734.55(C)(1). Rather, the Director has the responsibility of assuring that the financial priorities
mandated by R.C. 3734.53 are observed, and the duty of disapproving a plan that does not
provide an adequaie demonstration of the availability of financial resources to implement the
plan. As noted above, a county or joint district that materially fails to implement its plan as
approved may be subject to enforcement orders of the Director of Environmental Protection.
See R.C. 3734.55(E); see also R.C. 3734.13(A).
Conclusion
It is, therefore, my opinion, and you are advised, as follows:
1.
Subject to review and approval of the Director of Environmental
Protection, the solid waste management plan of a joint solid waste
management district, prepared in accordance with R.C. 3734.53-.55, may
include a description of and schedule for closure and post-closure activities
at a solid waste disposal facility that is owned by a county participating in
the district and that ceased to accept wastes before the plan was prepared,
and may provide for use of a portion of the fees collected pursuant to
R.C. 3734.57(B) to implement those closure and post-closure activities.
2.
Subject to review and approval of the Director of Environmental
Protection, the solid waste management plan of a county solid waste
management district, prepared in accordance with R.C. 3734.53-.55, may
include a description of and schedule for closure and post-closure activities
at solid waste disposal facility that is owned by the county and that ceased
to accept wastes before the plan was prepared, and may provide for use
of a portion of the fees collected pursuant to R.C. 3734.57(B) to
implement those closure and post-closure activities.
3.
The board of county commissioners of a county that participates in a joint
solid waste management district may, with the consent of the joint district,
transfer to the joint district a county-owned landfill that is in need of
closure and post-closure care.
4.
The board of county commissioners of a county that maintains a single
county solid waste management district may designate a county-owned
landfill for use by the county solid waste management district, and may
include in the solid waste management plan of the county district a county-
Septeinher 1993
2-101
OAG 93-018
Attorney General
owned landfill that is in need of closure and post-closure care; the
ownership of the landfill will remain in the board of county
commissioners.
OAG 93-019
2-102